Pricing Energy and Ancillary Services in a Day-Ahead Market for a Price-Taker Hydro Generating Company Using a Risk-Constrained Approach
Author
Abstract
Suggested Citation
Download full text from publisher
References listed on IDEAS
- Haifeng Zhang & Feng Gao & Jiang Wu & Kun Liu & Xiaolin Liu, 2012. "Optimal Bidding Strategies for Wind Power Producers in the Day-ahead Electricity Market," Energies, MDPI, vol. 5(11), pages 1-20, November.
- repec:cep:stitep:301 is not listed on IDEAS
- Ying Zheng & Xudong Fu & Jiahua Wei, 2013. "Evaluation of Power Generation Efficiency of Cascade Hydropower Plants: A Case Study," Energies, MDPI, vol. 6(2), pages 1-13, February.
- Paul Lehmann & Felix Creutzig & Melf-Hinrich Ehlers & Nele Friedrichsen & Clemens Heuson & Lion Hirth & Robert Pietzcker, 2012. "Carbon Lock-Out: Advancing Renewable Energy Policy in Europe," Energies, MDPI, vol. 5(2), pages 1-32, February.
- Bin Xu & Ping-An Zhong & Xinyu Wan & Weiguo Zhang & Xuan Chen, 2012. "Dynamic Feasible Region Genetic Algorithm for Optimal Operation of a Multi-Reservoir System," Energies, MDPI, vol. 5(8), pages 1-17, August.
- Acerbi, Carlo, 2002. "Spectral measures of risk: A coherent representation of subjective risk aversion," Journal of Banking & Finance, Elsevier, vol. 26(7), pages 1505-1518, July.
- Anthony Horsley & Andrew J Wrobel, 1996. "Efficiency Rents of Storage Plants in Peak-Load Pricing, I: Pumped Storage," STICERD - Theoretical Economics Paper Series /1996/301, Suntory and Toyota International Centres for Economics and Related Disciplines, LSE.
- Horsley, Anthony & Wrobel, Andrew J., 2007. "Profit-maximizing operation and valuation of hydroelectric plant: A new solution to the Koopmans problem," Journal of Economic Dynamics and Control, Elsevier, vol. 31(3), pages 938-970, March.
- Tjalling C. Koopmans, 1957. "Water Storage Policy in a Simplified Hydroelectric System," Cowles Foundation Discussion Papers 26, Cowles Foundation for Research in Economics, Yale University.
- Garcia-Gonzalez, Javier & Parrilla, Ernesto & Mateo, Alicia, 2007. "Risk-averse profit-based optimal scheduling of a hydro-chain in the day-ahead electricity market," European Journal of Operational Research, Elsevier, vol. 181(3), pages 1354-1369, September.
- John Kabouris & Fotis D. Kanellos, 2009. "Impacts of Large Scale Wind Penetration on Energy Supply Industry," Energies, MDPI, vol. 2(4), pages 1-11, November.
- Ioannis D. Margaris & Anca D. Hansen & Poul Sørensen & Nikolaos D. Hatziargyriou, 2010. "Illustration of Modern Wind Turbine Ancillary Services," Energies, MDPI, vol. 3(6), pages 1-13, June.
- Ivan Rajšl & Perica Ilak & Marko Delimar & Slavko Krajcar, 2012. "Dispatch Method for Independently Owned Hydropower Plants in the Same River Flow," Energies, MDPI, vol. 5(9), pages 1-17, September.
- Shenglian Guo & Jionghong Chen & Yu Li & Pan Liu & Tianyuan Li, 2011. "Joint Operation of the Multi-Reservoir System of the Three Gorges and the Qingjiang Cascade Reservoirs," Energies, MDPI, vol. 4(7), pages 1-15, July.
Citations
Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
Cited by:
- Bin Luo & Shumin Miao & Chuntian Cheng & Yi Lei & Gang Chen & Lang Gao, 2019. "Long-Term Generation Scheduling for Cascade Hydropower Plants Considering Price Correlation between Multiple Markets," Energies, MDPI, vol. 12(12), pages 1-17, June.
- Lin Herenčić & Perica Ilak & Ivan Rajšl, 2019. "Effects of Local Electricity Trading on Power Flows and Voltage Levels for Different Elasticities and Prices," Energies, MDPI, vol. 12(24), pages 1-19, December.
- Sara Raos & Perica Ilak & Ivan Rajšl & Tena Bilić & Ghislain Trullenque, 2019. "Multiple-Criteria Decision-Making for Assessing the Enhanced Geothermal Systems," Energies, MDPI, vol. 12(9), pages 1-23, April.
- Mario Klarić & Igor Kuzle & Ninoslav Holjevac, 2018. "Wind Power Monitoring and Control Based on Synchrophasor Measurement Data Mining," Energies, MDPI, vol. 11(12), pages 1-23, December.
- Perica Ilak & Lin Herenčić & Ivan Rajšl & Sara Raos & Željko Tomšić, 2021. "Equilibrium Pricing with Duality-Based Method: Approach for Market-Oriented Capacity Remuneration Mechanism," Energies, MDPI, vol. 14(3), pages 1-19, January.
- Ilak, Perica & Rajšl, Ivan & Krajcar, Slavko & Delimar, Marko, 2015. "The impact of a wind variable generation on the hydro generation water shadow price," Applied Energy, Elsevier, vol. 154(C), pages 197-208.
- Abiodun, Kehinde & Hood, Karoline & Cox, John L. & Newman, Alexandra M. & Zolan, Alex J., 2023. "The value of concentrating solar power in ancillary services markets," Applied Energy, Elsevier, vol. 334(C).
- Perica Ilak & Ivan Rajšl & Josip Đaković & Marko Delimar, 2018. "Duality Based Risk Mitigation Method for Construction of Joint Hydro-Wind Coordination Short-Run Marginal Cost Curves," Energies, MDPI, vol. 11(5), pages 1-12, May.
- Schillinger, Moritz & Weigt, Hannes & Barry, Michael & Schumann, René, 2017. "Hydropower Operation in a Changing Market Environment A Swiss Case Study," Working papers 2017/19, Faculty of Business and Economics - University of Basel.
- Raveendran, Visal & Alvarez-Bel, Carlos & Nair, Manjula G., 2020. "Assessing the ancillary service potential of electric vehicles to support renewable energy integration in touristic islands: A case study from Balearic island of Menorca," Renewable Energy, Elsevier, vol. 161(C), pages 495-509.
Most related items
These are the items that most often cite the same works as this one and are cited by the same works as this one.- Perica Ilak & Ivan Rajšl & Josip Đaković & Marko Delimar, 2018. "Duality Based Risk Mitigation Method for Construction of Joint Hydro-Wind Coordination Short-Run Marginal Cost Curves," Energies, MDPI, vol. 11(5), pages 1-12, May.
- Ilak, Perica & Rajšl, Ivan & Krajcar, Slavko & Delimar, Marko, 2015. "The impact of a wind variable generation on the hydro generation water shadow price," Applied Energy, Elsevier, vol. 154(C), pages 197-208.
- van Ackere, Ann & Ochoa, Patricia, 2010. "Managing a hydro-energy reservoir: A policy approach," Energy Policy, Elsevier, vol. 38(11), pages 7299-7311, November.
- Horsley, Anthony & Wrobel, Andrew J., 2002.
"Efficiency rents of pumped-storage plants and their uses for operation and investment decisions,"
Journal of Economic Dynamics and Control, Elsevier, vol. 27(1), pages 109-142, November.
- Horsley, Anthony & Wrobel, Andrew J., 2000. "Efficiency rents of pumped-storage plants and their uses for operation and investment decisions," LSE Research Online Documents on Economics 19336, London School of Economics and Political Science, LSE Library.
- Anthony Horsley & Andrew J Wrobel, 2000. "Efficiency Rents of Pumped-Storage Plants and their Uses for Operation and Investment Decisions," STICERD - Theoretical Economics Paper Series 405, Suntory and Toyota International Centres for Economics and Related Disciplines, LSE.
- Anthony Horsley & Andrew J Wrobel, 1999. "Efficiency Rents of Storage Plants in Peak-Load Pricing, II: Hydroelectricity - (Now published as Efficiency rents of hydroelectric storage plants in continuous-time peak-load pricing, in The Current ," STICERD - Theoretical Economics Paper Series 372, Suntory and Toyota International Centres for Economics and Related Disciplines, LSE.
- Andrew J. Wrobel, 2020. "Bounded topologies on Banach spaces and some of their uses in economic theory: a review," Papers 2005.05202, arXiv.org, revised Sep 2020.
- Liping Wang & Minghao Liu & Boquan Wang & Jiajie Wu & Chuangang Li, 2017. "Study on Nested-Structured Load Shedding Method of Thermal Power Stations Based on Output Fluctuations," Energies, MDPI, vol. 10(10), pages 1-16, September.
- Lejun Ma & Huan Wang & Baohong Lu & Changjun Qi, 2018. "Application of Strongly Constrained Space Particle Swarm Optimization to Optimal Operation of a Reservoir System," Sustainability, MDPI, vol. 10(12), pages 1-15, November.
- Shuai Liu & Zhong-Kai Feng & Wen-Jing Niu & Hai-Rong Zhang & Zhen-Guo Song, 2019. "Peak Operation Problem Solving for Hydropower Reservoirs by Elite-Guide Sine Cosine Algorithm with Gaussian Local Search and Random Mutation," Energies, MDPI, vol. 12(11), pages 1-24, June.
- Zhong-Kai Feng & Wen-Jing Niu & Jian-Zhong Zhou & Chun-Tian Cheng & Hui Qin & Zhi-Qiang Jiang, 2017. "Parallel Multi-Objective Genetic Algorithm for Short-Term Economic Environmental Hydrothermal Scheduling," Energies, MDPI, vol. 10(2), pages 1-22, January.
- Shang, Yizi & Lu, Shibao & Ye, Yuntao & Liu, Ronghua & Shang, Ling & Liu, Chunna & Meng, Xianyong & Li, Xiaofei & Fan, Qixiang, 2018. "China’ energy-water nexus: Hydropower generation potential of joint operation of the Three Gorges and Qingjiang cascade reservoirs," Energy, Elsevier, vol. 142(C), pages 14-32.
- Jianjian Shen & Chuntian Cheng & Jun Zhang & Jianyu Lu, 2015. "Peak Operation of Cascaded Hydropower Plants Serving Multiple Provinces," Energies, MDPI, vol. 8(10), pages 1-20, October.
- Oscar Barambones, 2012. "Sliding Mode Control Strategy for Wind Turbine Power Maximization," Energies, MDPI, vol. 5(7), pages 1-21, July.
- Ivan Rajšl & Perica Ilak & Marko Delimar & Slavko Krajcar, 2012. "Dispatch Method for Independently Owned Hydropower Plants in the Same River Flow," Energies, MDPI, vol. 5(9), pages 1-17, September.
- Crampes, Claude & Moreaux, Michel, 2010. "Pumped storage and cost saving," Energy Economics, Elsevier, vol. 32(2), pages 325-333, March.
- Sofiane Aboura, 2014. "When the U.S. Stock Market Becomes Extreme?," Risks, MDPI, vol. 2(2), pages 1-15, May.
- Choo, Weihao & de Jong, Piet, 2015. "The tradeoff insurance premium as a two-sided generalisation of the distortion premium," Insurance: Mathematics and Economics, Elsevier, vol. 65(C), pages 238-246.
- Durmaz, Tunç, 2016.
"Precautionary Storage in Electricity Markets,"
Discussion Papers
2016/5, Norwegian School of Economics, Department of Business and Management Science.
- Tunç Durmaz, 2016. "Precautionary Storage in Electricity Markets," Working Papers 2016.07, FAERE - French Association of Environmental and Resource Economists.
- Dimitrios G. Konstantinides & Georgios C. Zachos, 2019. "Exhibiting Abnormal Returns Under a Risk Averse Strategy," Methodology and Computing in Applied Probability, Springer, vol. 21(2), pages 551-566, June.
- Alois Pichler, 2013. "Premiums And Reserves, Adjusted By Distortions," Papers 1304.0490, arXiv.org.
More about this item
Keywords
hydropower plant; opportunity cost; water shadow price; day-ahead market; risk-aversion; conditional value at risk; ancillary services;All these keywords.
Statistics
Access and download statisticsCorrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jeners:v:7:y:2014:i:4:p:2317-2342:d:35035. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .
Please note that corrections may take a couple of weeks to filter through the various RePEc services.