IDEAS home Printed from https://ideas.repec.org/a/ijb/journl/v20y2021i2p119-140.html
   My bibliography  Save this article

The Impact of Changing the Expected Time and Variance Equations of the Project Activities on The Completion Time and Cost of the Project in PERT Model

Author

Listed:
  • Moayyad Al-Fawaeer

    (Al-Zaytoonah University of Jordan, P.O.Box 130, Amman 11733, Jordan.)

  • Abdul Sattar Al-Ali

    (Senior Member IIE, MCSCMP, EFQM, 2450 Falkland Cres, Oakville, Ontario, L8M 4Y3, Canada.)

  • Mousa Khaireddin

    (Khawarizmi University Technical College, 36 Mirza Wasfi St. Amman, Jordan.)

Abstract

Scheduling is one of the most important tools used in project management, and Programming Evaluation Revision Technique (PERT) is one of the methods used in project scheduling. PERT depends on identifying three possible times for any activity: optimistic, pessimistic, and the most likely. Using these three times, the expected time to end the activity and then the critical path of the project, as well as the activity variance, and then the project standard deviation is calculated by offering different weights for these three times. Therefore, this study aimed to suggest the use of equal weights for these times in calculating both the expected time to complete the activity as well as its variance, in order to know the effect on the completion time of project, the standard deviation of the project, as well as the cost of project crashing. To do that the both models usual PERT model and the proposed model were applied on three real construction projects. The results revealed that the proposed model (equal time weights) has a positive impact on the project crashing cost if required, but the results also revealed a negative impact of applying the proposed model on the project completion time (longer critical path), and on the standard deviation of the project.

Suggested Citation

  • Moayyad Al-Fawaeer & Abdul Sattar Al-Ali & Mousa Khaireddin, 2021. "The Impact of Changing the Expected Time and Variance Equations of the Project Activities on The Completion Time and Cost of the Project in PERT Model," International Journal of Business and Economics, School of Management Development, Feng Chia University, Taichung, Taiwan, vol. 20(2), pages 119-140, September.
  • Handle: RePEc:ijb:journl:v:20:y:2021:i:2:p:119-140
    as

    Download full text from publisher

    File URL: https://ijbe.fcu.edu.tw/assets/ijbe/past_issue/No.20-2/pdf/vol_20-2-2.pdf
    Download Restriction: no

    File URL: https://ijbe.fcu.edu.tw/assets/ijbe/past_issue/No.20-2/abstract/02.html
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Christian Stoy & Spiro Pollalis & Onur Dursun, 2012. "A concept for developing construction element cost models for German residential building projects," International Journal of Project Organisation and Management, Inderscience Enterprises Ltd, vol. 4(1), pages 38-53.
    2. M. W. Sasieni, 1986. "Note---A Note on Pert Times," Management Science, INFORMS, vol. 32(12), pages 1652-1653, December.
    3. D. R. Fulkerson, 1962. "Expected Critical Path Lengths in PERT Networks," Operations Research, INFORMS, vol. 10(6), pages 808-817, December.
    4. Chen, Shih-Pin, 2007. "Analysis of critical paths in a project network with fuzzy activity times," European Journal of Operational Research, Elsevier, vol. 183(1), pages 442-459, November.
    5. Frank E. Grubbs, 1962. "Letter to the Editor---Attempts to Validate Certain PERT Statistics or “Picking on PERT”," Operations Research, INFORMS, vol. 10(6), pages 912-915, December.
    6. Georgios N. Aretoulis, 2019. "Neural network models for actual cost prediction in Greek public highway projects," International Journal of Project Organisation and Management, Inderscience Enterprises Ltd, vol. 11(1), pages 41-64.
    7. Kristian Ditlev Bohnstedt & Søren Wandahl, 2019. "Selecting the right collaborative components in a construction project," International Journal of Project Organisation and Management, Inderscience Enterprises Ltd, vol. 11(1), pages 65-92.
    8. Azadeh Rezvani & Pouria Khosravi, 2019. "Identification of failure factors in large scale complex projects: an integrative framework and review of emerging themes," International Journal of Project Organisation and Management, Inderscience Enterprises Ltd, vol. 11(1), pages 1-21.
    9. Titus Ebenezer Kwofie & Clinton Ohis Aigbavboa & Zanele Sally-Sue Matsane, 2018. "Dimensions of social barriers to effective collaborative working in construction supply chain," International Journal of Project Organisation and Management, Inderscience Enterprises Ltd, vol. 10(1), pages 37-53.
    10. Azaron, Amir & Katagiri, Hideki & Sakawa, Masatoshi & Kato, Kosuke & Memariani, Azizollah, 2006. "A multi-objective resource allocation problem in PERT networks," European Journal of Operational Research, Elsevier, vol. 172(3), pages 838-854, August.
    11. Charles E. Clark, 1962. "Letter to the Editor---The PERT Model for the Distribution of an Activity Time," Operations Research, INFORMS, vol. 10(3), pages 405-406, June.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Moayyad Al-Fawaeer & Abdul Sattar Al-Ali & Mousa Khaireddin, 2021. "The Impact of Changing the Expected Time and Variance Equations of the Project Activities on The Completion Time and Cost of the Project in PERT Model," International Journal of Business and Economics, School of Management Development, Feng Chia University, Taichung, Taiwan, vol. 20(2), pages 1-22, September.
    2. Azaron, Amir & Fatemi Ghomi, S.M.T., 2008. "Lower bound for the mean project completion time in dynamic PERT networks," European Journal of Operational Research, Elsevier, vol. 186(1), pages 120-127, April.
    3. Catalina García & José Pérez & Salvador Rambaud, 2010. "Proposal of a new distribution in PERT methodology," Annals of Operations Research, Springer, vol. 181(1), pages 515-538, December.
    4. Hajdu M. & Isaac S., 2016. "Sixty years of project planning: history and future," Organization, Technology and Management in Construction, Sciendo, vol. 8(1), pages 1499-1510, December.
    5. Hahn, Eugene David, 2008. "Mixture densities for project management activity times: A robust approach to PERT," European Journal of Operational Research, Elsevier, vol. 188(2), pages 450-459, July.
    6. Kamburowski, J., 1997. "New validations of PERT times," Omega, Elsevier, vol. 25(3), pages 323-328, June.
    7. Pérez, José García & Martín, María del Mar López & García, Catalina García & Sánchez Granero, Miguel Ángel, 2016. "Project management under uncertainty beyond beta: The generalized bicubic distribution," Operations Research Perspectives, Elsevier, vol. 3(C), pages 67-76.
    8. Chen, Shih-Pin & Tsai, Ming-Jiun, 2011. "Time-cost trade-off analysis of project networks in fuzzy environments," European Journal of Operational Research, Elsevier, vol. 212(2), pages 386-397, July.
    9. Azaron, Amir & Fynes, Brian & Modarres, Mohammad, 2011. "Due date assignment in repetitive projects," International Journal of Production Economics, Elsevier, vol. 129(1), pages 79-85, January.
    10. Alasdair Reid, 2023. "Closing the Affordable Housing Gap: Identifying the Barriers Hindering the Sustainable Design and Construction of Affordable Homes," Sustainability, MDPI, vol. 15(11), pages 1-27, May.
    11. Zhen Song & Håkan Schunnesson & Mikael Rinne & John Sturgul, 2015. "An Approach to Realizing Process Control for Underground Mining Operations of Mobile Machines," PLOS ONE, Public Library of Science, vol. 10(6), pages 1-17, June.
    12. Lucas Coffman & Clayton R. Featherstone & Judd B. Kessler, 2024. "A Model of Information Nudges," Boston College Working Papers in Economics 1077, Boston College Department of Economics.
    13. Gary Mitchell, 2010. "On Calculating Activity Slack in Stochastic Project Networks," American Journal of Economics and Business Administration, Science Publications, vol. 2(1), pages 78-85, March.
    14. Dorota Kuchta, 2010. "Generalization of the critical chain method supporting the management of projects with a high degree of uncertainty and imperfect information," Operations Research and Decisions, Wroclaw University of Science and Technology, Faculty of Management, vol. 20(2), pages 77-90.
    15. García Pérez, J., 1998. "El método de subasta como complemento al PERT clásico," Estudios de Economia Aplicada, Estudios de Economia Aplicada, vol. 10, pages 71-88, Diciembre.
    16. Nicholas G. Hall & Marc E. Posner, 2001. "Generating Experimental Data for Computational Testing with Machine Scheduling Applications," Operations Research, INFORMS, vol. 49(6), pages 854-865, December.
    17. Mathieu, Hervé & Colin, Jean-Yves & Nakechbandi, Moustafa, 2014. "Computing Dynamic Routes in Maritime Logistic Networks," Chapters from the Proceedings of the Hamburg International Conference of Logistics (HICL), in: Blecker, Thorsten & Kersten, Wolfgang & Ringle, Christian M. (ed.), Innovative Methods in Logistics and Supply Chain Management: Current Issues and Emerging Practices. Proceedings of the Hamburg International Conferenc, volume 19, pages 187-200, Hamburg University of Technology (TUHH), Institute of Business Logistics and General Management.
    18. Verónica Morales-Sánchez & Antonio Hernández-Mendo & Pedro Sánchez-Algarra & Ángel Blanco-Villaseñor & María-Teresa Anguera-Argilaga, 2009. "Random PERT: application to physical activity/sports programs," Quality & Quantity: International Journal of Methodology, Springer, vol. 43(2), pages 225-236, March.
    19. A. Hernández-Bastida & M. P. Fernández-Sánchez, 2019. "How adding new information modifies the estimation of the mean and the variance in PERT: a maximum entropy distribution approach," Annals of Operations Research, Springer, vol. 274(1), pages 291-308, March.
    20. Wright, Daniel G. & Dey, Prasanta K. & Brammer, John G., 2013. "A fuzzy levelised energy cost method for renewable energy technology assessment," Energy Policy, Elsevier, vol. 62(C), pages 315-323.

    More about this item

    Keywords

    ;
    ;
    ;
    ;
    ;

    JEL classification:

    • L7 - Industrial Organization - - Industry Studies: Primary Products and Construction
    • L74 - Industrial Organization - - Industry Studies: Primary Products and Construction - - - Construction
    • N6 - Economic History - - Manufacturing and Construction

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:ijb:journl:v:20:y:2021:i:2:p:119-140. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Szu-Hsien Ho (email available below). General contact details of provider: https://edirc.repec.org/data/cbfcutw.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.