On Calculating Activity Slack in Stochastic Project Networks

Author

Listed:
  • Gary Mitchell

Abstract

Problem statement: Identifying critical tasks in a project network is easily done when task times are deterministic, but doing so under stochastic task times is problematic. The few methods that have been proposed contain serious drawbacks which lead to identifying critical tasks incorrectly, leaving project managers without the means to (1) identify and rank the most probable sources of project delays, (2) assess the magnitude of each source of schedule risk, and (3) identify which tasks represent the best opportunities for successfully addressing schedule risk? Approach: In this study we considered the problem of identifying the sources of schedule risk in a stochastic project network. We developed general expressions for determining a task’s late starting and ending time distributions. We introduced the concept of stochastic slack and develop a number of metrics that help a project manager directly identify and estimate the magnitude of sources of schedule risk. Finally, we compared critical tasks identified using the activity criticality index to those found using stochastic slack metrics. Results: We have demonstrated that a task may have non-zero probability of negative stochastic slack and that expected total slack for a task may be negative. We also found that while the activity criticality index is effective for calculating the probability that a task is on a critical path, the stochastic slack based metrics discussed in this paper are better predictors of the extent to which a delay in a task will result in a project delay. Conclusion/Recommendations: Project managers should consider using stochastic slack based metrics for assessing project risk and establishing the most likely project schedule outcomes. Given the calculation complexity associated with theoretically exact stochastic slack metrics, effective heuristics are required.

Suggested Citation

  • Gary Mitchell, 2010. "On Calculating Activity Slack in Stochastic Project Networks," American Journal of Economics and Business Administration, Science Publications, vol. 2(1), pages 78-85, March.
  • Handle: RePEc:abk:jajeba:ajebasp.2010.78.85
    DOI: 10.3844/ajebasp.2010.78.85
    as

    Download full text from publisher

    File URL: https://thescipub.com/pdf/ajebasp.2010.78.85.pdf
    Download Restriction: no

    File URL: https://thescipub.com/abstract/ajebasp.2010.78.85
    Download Restriction: no

    File URL: https://libkey.io/10.3844/ajebasp.2010.78.85?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Elmaghraby, Salah E., 2005. "On the fallacy of averages in project risk management," European Journal of Operational Research, Elsevier, vol. 165(2), pages 307-313, September.
    2. Elmaghraby, Salah E., 2000. "On criticality and sensitivity in activity networks," European Journal of Operational Research, Elsevier, vol. 127(2), pages 220-238, December.
    3. George B. Kleindorfer, 1971. "Bounding Distributions for a Stochastic Acyclic Network," Operations Research, INFORMS, vol. 19(7), pages 1586-1601, December.
    4. V. G. Kulkarni & V. G. Adlakha, 1986. "Markov and Markov-Regenerative pert Networks," Operations Research, INFORMS, vol. 34(5), pages 769-781, October.
    5. J. J. Martin, 1965. "Distribution of the Time Through a Directed, Acyclic Network," Operations Research, INFORMS, vol. 13(1), pages 46-66, February.
    6. Bajis Dodin, 1984. "Determining the K Most Critical Paths in PERT Networks," Operations Research, INFORMS, vol. 32(4), pages 859-877, August.
    7. D. R. Fulkerson, 1962. "Expected Critical Path Lengths in PERT Networks," Operations Research, INFORMS, vol. 10(6), pages 808-817, December.
    8. Pierre Robillard & Michel Trahan, 1976. "Technical Note—Expected Completion Time in Pert Networks," Operations Research, INFORMS, vol. 24(1), pages 177-182, February.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Azaron, Amir & Fatemi Ghomi, S.M.T., 2008. "Lower bound for the mean project completion time in dynamic PERT networks," European Journal of Operational Research, Elsevier, vol. 186(1), pages 120-127, April.
    2. Tetsuo Iida, 2000. "Computing bounds on project duration distributions for stochastic PERT networks," Naval Research Logistics (NRL), John Wiley & Sons, vol. 47(7), pages 559-580, October.
    3. Azaron, Amir & Fynes, Brian & Modarres, Mohammad, 2011. "Due date assignment in repetitive projects," International Journal of Production Economics, Elsevier, vol. 129(1), pages 79-85, January.
    4. Madadi, M. & Iranmanesh, H., 2012. "A management oriented approach to reduce a project duration and its risk (variability)," European Journal of Operational Research, Elsevier, vol. 219(3), pages 751-761.
    5. Fatemi Ghomi, S. M. T. & Hashemin, S. S., 1999. "A new analytical algorithm and generation of Gaussian quadrature formula for stochastic network," European Journal of Operational Research, Elsevier, vol. 114(3), pages 610-625, May.
    6. Azaron, Amir & Katagiri, Hideki & Sakawa, Masatoshi & Kato, Kosuke & Memariani, Azizollah, 2006. "A multi-objective resource allocation problem in PERT networks," European Journal of Operational Research, Elsevier, vol. 172(3), pages 838-854, August.
    7. Davaadorjin Monhor, 2011. "A new probabilistic approach to the path criticality in stochastic PERT," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 19(4), pages 615-633, December.
    8. Yousry Abdelkader, 2010. "Adjustment of the moments of the project completion times when activity times are exponentially distributed," Annals of Operations Research, Springer, vol. 181(1), pages 503-514, December.
    9. Elmaghraby, Salah E., 2000. "On criticality and sensitivity in activity networks," European Journal of Operational Research, Elsevier, vol. 127(2), pages 220-238, December.
    10. Elmaghraby, S. E. & Fathi, Y. & Taner, M. R., 1999. "On the sensitivity of project variability to activity mean duration," International Journal of Production Economics, Elsevier, vol. 62(3), pages 219-232, September.
    11. Stefan Creemers & Erik Demeulemeester & Stijn Vonder, 2014. "A new approach for quantitative risk analysis," Annals of Operations Research, Springer, vol. 213(1), pages 27-65, February.
    12. Vanhoucke, Mario, 2010. "Using activity sensitivity and network topology information to monitor project time performance," Omega, Elsevier, vol. 38(5), pages 359-370, October.
    13. Wiesemann, Wolfram & Kuhn, Daniel & Rustem, Berç, 2010. "Maximizing the net present value of a project under uncertainty," European Journal of Operational Research, Elsevier, vol. 202(2), pages 356-367, April.
    14. Zhichao Zheng & Karthik Natarajan & Chung-Piaw Teo, 2016. "Least Squares Approximation to the Distribution of Project Completion Times with Gaussian Uncertainty," Operations Research, INFORMS, vol. 64(6), pages 1406-1421, December.
    15. Amir Azaron & Hideki Katagiri & Masatoshi Sakawa, 2007. "Time-cost trade-off via optimal control theory in Markov PERT networks," Annals of Operations Research, Springer, vol. 150(1), pages 47-64, March.
    16. Bregman, Robert L., 2009. "A heuristic procedure for solving the dynamic probabilistic project expediting problem," European Journal of Operational Research, Elsevier, vol. 192(1), pages 125-137, January.
    17. Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
    18. Azaron, Amir & Katagiri, Hideki & Kato, Kosuke & Sakawa, Masatoshi, 2006. "Longest path analysis in networks of queues: Dynamic scheduling problems," European Journal of Operational Research, Elsevier, vol. 174(1), pages 132-149, October.
    19. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2022. "Using Earned Value Management and Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 297(2), pages 451-466.
    20. Sobel, Matthew J. & Szmerekovsky, Joseph G. & Tilson, Vera, 2009. "Scheduling projects with stochastic activity duration to maximize expected net present value," European Journal of Operational Research, Elsevier, vol. 198(3), pages 697-705, November.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:abk:jajeba:ajebasp.2010.78.85. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Jeffery Daniels (email available below). General contact details of provider: https://thescipub.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.