Bi-objective optimization of the scheduling of risk-related resources for risk response

Author

Listed:
  • Zuo, Fei
  • Zio, Enrico
  • Xu, Yue

Abstract

Risk response is a crucial component of project risk management, playing a key role in mitigating the adverse effects of risks. However, the implementation of such risk response relies on the utilization of appropriate risk-related resources. Given the scarcity of these resources, their proper scheduling and allocation are critical. To address this issue, this paper introduces a flow-based continuous-time bi-objective optimization model for risk-related resource planning. The proposed model is then applied to a case study, deriving the global optimal solution based on the tuned parameters. Moreover, we develop a tailored rule-based metaheuristic algorithm for the model. The algorithm incorporates improved random key-based population initialization and a rule-based genetic operator, facilitating the application of the proposed model to large-scale projects. The computational results of the case study and numerical experiments not only validate the effectiveness of the algorithm, but also emphasize the importance of the precautionary principle and redundant resources in project risk management.

Suggested Citation

  • Zuo, Fei & Zio, Enrico & Xu, Yue, 2023. "Bi-objective optimization of the scheduling of risk-related resources for risk response," Reliability Engineering and System Safety, Elsevier, vol. 237(C).
  • Handle: RePEc:eee:reensy:v:237:y:2023:i:c:s0951832023003058
    DOI: 10.1016/j.ress.2023.109391
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0951832023003058
    Download Restriction: Full text for ScienceDirect subscribers only

    File URL: https://libkey.io/10.1016/j.ress.2023.109391?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Brčić, Mario & Katić, Marija & Hlupić, Nikica, 2019. "Planning horizons based proactive rescheduling for stochastic resource-constrained project scheduling problems," European Journal of Operational Research, Elsevier, vol. 273(1), pages 58-66.
    2. Gómez Sánchez, Mariam & Lalla-Ruiz, Eduardo & Fernández Gil, Alejandro & Castro, Carlos & Voß, Stefan, 2023. "Resource-constrained multi-project scheduling problem: A survey," European Journal of Operational Research, Elsevier, vol. 309(3), pages 958-976.
    3. Balouka, Noemie & Cohen, Izack, 2021. "A robust optimization approach for the multi-mode resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 291(2), pages 457-470.
    4. Aven, Terje & Zio, Enrico, 2021. "Globalization and global risk: How risk analysis needs to be enhanced to be effective in confronting current threats," Reliability Engineering and System Safety, Elsevier, vol. 205(C).
    5. Ghorbani, Milad & Nourelfath, Mustapha & Gendreau, Michel, 2022. "A two-stage stochastic programming model for selective maintenance optimization," Reliability Engineering and System Safety, Elsevier, vol. 223(C).
    6. De Reyck, Bert & Herroelen, Willy, 1999. "The multi-mode resource-constrained project scheduling problem with generalized precedence relations," European Journal of Operational Research, Elsevier, vol. 119(2), pages 538-556, December.
    7. Fang, Chao & Marle, Franck & Zio, Enrico & Bocquet, Jean-Claude, 2012. "Network theory-based analysis of risk interactions in large engineering projects," Reliability Engineering and System Safety, Elsevier, vol. 106(C), pages 1-10.
    8. Mancuso, A. & Compare, M. & Salo, A. & Zio, E., 2017. "Portfolio optimization of safety measures for reducing risks in nuclear systems," Reliability Engineering and System Safety, Elsevier, vol. 167(C), pages 20-29.
    9. I Ben-David & T Raz, 2001. "An integrated approach for risk response development in project planning," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 52(1), pages 14-25, January.
    10. Böttcher, Jan & Drexl, A. & Kolisch, R. & Salewski, F., 1999. "Project scheduling under partially renewable resource constraints," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 345, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
    11. Zhu, Tiantian & Haugen, Stein & Liu, Yiliu & Yang, Xue, 2023. "A value of prediction model to estimate optimal response time to threats for accident prevention," Reliability Engineering and System Safety, Elsevier, vol. 232(C).
    12. Artigues, Christian & Michelon, Philippe & Reusser, Stephane, 2003. "Insertion techniques for static and dynamic resource-constrained project scheduling," European Journal of Operational Research, Elsevier, vol. 149(2), pages 249-267, September.
    13. Boctor, Fayer F., 1990. "Some efficient multi-heuristic procedures for resource-constrained project scheduling," European Journal of Operational Research, Elsevier, vol. 49(1), pages 3-13, November.
    14. Morteza Davari & Erik Demeulemeester, 2019. "Important classes of reactions for the proactive and reactive resource-constrained project scheduling problem," Annals of Operations Research, Springer, vol. 274(1), pages 187-210, March.
    15. Hartmann, Sönke & Briskorn, Dirk, 2022. "An updated survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 297(1), pages 1-14.
    16. Jan Böttcher & Andreas Drexl & Rainer Kolisch & Frank Salewski, 1999. "Project Scheduling Under Partially Renewable Resource Constraints," Management Science, INFORMS, vol. 45(4), pages 543-559, April.
    17. Seyed Mohammad Seyedhoseini & Siamak Noori & Mohammad Ali Hatefi, 2009. "An Integrated Methodology for Assessment and Selection of the Project Risk Response Actions," Risk Analysis, John Wiley & Sons, vol. 29(5), pages 752-763, May.
    18. Morteza Davari & Erik Demeulemeester, 2019. "The proactive and reactive resource-constrained project scheduling problem," Journal of Scheduling, Springer, vol. 22(2), pages 211-237, April.
    19. Aven, Terje, 2016. "Risk assessment and risk management: Review of recent advances on their foundation," European Journal of Operational Research, Elsevier, vol. 253(1), pages 1-13.
    20. Fang, Yi-Ping & Sansavini, Giovanni, 2019. "Optimum post-disruption restoration under uncertainty for enhancing critical infrastructure resilience," Reliability Engineering and System Safety, Elsevier, vol. 185(C), pages 1-11.
    21. Hanif D. Sherali & Jitamitra Desai & Theodore S. Glickman, 2008. "Optimal Allocation of Risk-Reduction Resources in Event Trees," Management Science, INFORMS, vol. 54(7), pages 1313-1321, July.
    22. Zafra-Cabeza, Ascensión & Ridao, Miguel A. & Camacho, Eduardo F., 2008. "Using a risk-based approach to project scheduling: A case illustration from semiconductor manufacturing," European Journal of Operational Research, Elsevier, vol. 190(3), pages 708-723, November.
    23. Liu, Qiong & He, Renfei & Zhang, Limao, 2022. "Simulation-based multi-objective optimization for enhanced safety of fire emergency response in metro stations," Reliability Engineering and System Safety, Elsevier, vol. 228(C).
    24. Andrew Stirling, 1998. "Risk at a turning point?," Journal of Risk Research, Taylor & Francis Journals, vol. 1(2), pages 97-109, April.
    25. Pan, Xing & Dang, Yuheng & Wang, Huixiong & Hong, Dongpao & Li, Yuehong & Deng, Hongxu, 2022. "Resilience model and recovery strategy of transportation network based on travel OD-grid analysis," Reliability Engineering and System Safety, Elsevier, vol. 223(C).
    26. Marly Monteiro de Carvalho & Roque Rabechini Junior, 2015. "Impact of risk management on project performance: the importance of soft skills," International Journal of Production Research, Taylor & Francis Journals, vol. 53(2), pages 321-340, January.
    27. He, Xinxin & Wang, Zhijian & Li, Yanfeng & Khazhina, Svetlana & Du, Wenhua & Wang, Junyuan & Wang, Wenzhao, 2022. "Joint decision-making of parallel machine scheduling restricted in job-machine release time and preventive maintenance with remaining useful life constraints," Reliability Engineering and System Safety, Elsevier, vol. 222(C).
    28. Huang, Ding-Hsiang & Huang, Cheng-Fu & Lin, Yi-Kuei, 2020. "Exact project reliability for a multi-state project network subject to time and budget constraints," Reliability Engineering and System Safety, Elsevier, vol. 195(C).
    29. Hanif D. Sherali & Evrim Dalkiran & Theodore S. Glickman, 2011. "Selecting Optimal Alternatives and Risk Reduction Strategies in Decision Trees," Operations Research, INFORMS, vol. 59(3), pages 631-647, June.
    30. Vanhoucke, Mario, 2010. "Using activity sensitivity and network topology information to monitor project time performance," Omega, Elsevier, vol. 38(5), pages 359-370, October.
    31. Jun-ya Gotoh & Hiroshi Konno, 2000. "Third Degree Stochastic Dominance and Mean-Risk Analysis," Management Science, INFORMS, vol. 46(2), pages 289-301, February.
    32. Martin Lodge, 2009. "The Public Management of Risk: The Case for Deliberating among Worldviews," Review of Policy Research, Policy Studies Organization, vol. 26(4), pages 395-408, July.
    33. Zio, E., 2018. "The future of risk assessment," Reliability Engineering and System Safety, Elsevier, vol. 177(C), pages 176-190.
    34. Mohammad Saied Dehghani & Hanif D. Sherali, 2016. "A resource allocation approach for managing critical network-based infrastructure systems," IISE Transactions, Taylor & Francis Journals, vol. 48(9), pages 826-837, September.
    35. Fan, Miao & Lin, Neng-Pai & Sheu, Chwen, 2008. "Choosing a project risk-handling strategy: An analytical model," International Journal of Production Economics, Elsevier, vol. 112(2), pages 700-713, April.
    36. Chaabane, K. & Khatab, A. & Diallo, C. & Aghezzaf, E.-H. & Venkatadri, U., 2020. "Integrated imperfect multimission selective maintenance and repairpersons assignment problem," Reliability Engineering and System Safety, Elsevier, vol. 199(C).
    37. Nguyen, Trong-Hung & Marmier, François & Gourc, Didier, 2013. "A decision-making tool to maximize chances of meeting project commitments," International Journal of Production Economics, Elsevier, vol. 142(2), pages 214-224.
    38. Zarghami, Seyed Ashkan & Dumrak, Jantanee, 2021. "Unearthing vulnerability of supply provision in logistics networks to the black swan events: Applications of entropy theory and network analysis," Reliability Engineering and System Safety, Elsevier, vol. 215(C).
    39. KIlIç, Murat & Ulusoy, Gündüz & Serifoglu, Funda Sivrikaya, 2008. "A bi-objective genetic algorithm approach to risk mitigation in project scheduling," International Journal of Production Economics, Elsevier, vol. 112(1), pages 202-216, March.
    40. James C. Bean, 1994. "Genetic Algorithms and Random Keys for Sequencing and Optimization," INFORMS Journal on Computing, INFORMS, vol. 6(2), pages 154-160, May.
    41. Kolisch, Rainer & Sprecher, Arno, 1997. "PSPLIB - A project scheduling problem library : OR Software - ORSEP Operations Research Software Exchange Program," European Journal of Operational Research, Elsevier, vol. 96(1), pages 205-216, January.
    42. Yanwei Li & Araz Taeihagh & Martin de Jong & Andreas Klinke, 2021. "Toward a Commonly Shared Public Policy Perspective for Analyzing Risk Coping Strategies," Risk Analysis, John Wiley & Sons, vol. 41(3), pages 519-532, March.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Mahsa Parsaei Motamed & Shahrooz Bamdad, 2022. "A multi-objective optimization approach for selecting risk response actions: considering environmental and secondary risks," OPSEARCH, Springer;Operational Research Society of India, vol. 59(1), pages 266-303, March.
    2. Andreas Schirmer, 2000. "Case‐based reasoning and improved adaptive search for project scheduling," Naval Research Logistics (NRL), John Wiley & Sons, vol. 47(3), pages 201-222, April.
    3. Abdollah Arasteh, 2020. "Considering Project Management Activities for Engineering Design Groups," SN Operations Research Forum, Springer, vol. 1(4), pages 1-29, December.
    4. Ma, Weining & Zhang, Qin & Xiahou, Tangfan & Liu, Yu & Jia, Xisheng, 2023. "Integrated selective maintenance and task assignment optimization for multi-state systems executing multiple missions," Reliability Engineering and System Safety, Elsevier, vol. 237(C).
    5. Schirmer, Andreas & Riesenberg, Sven, 1997. "Parameterized heuristics for project scheduling: Biased random sampling methods," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 456, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    6. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    7. Saad Muslet Albogami & Mohd Khairol Anuar Bin Mohd Ariffin & Eris Elianddy Bin Supeni & Kamarul Arifin Ahmad, 2021. "A New Hybrid AHP and Dempster—Shafer Theory of Evidence Method for Project Risk Assessment Problem," Mathematics, MDPI, vol. 9(24), pages 1-30, December.
    8. Alfredo S. Ramos & Pablo A. Miranda-Gonzalez & Samuel Nucamendi-Guillén & Elias Olivares-Benitez, 2023. "A Formulation for the Stochastic Multi-Mode Resource-Constrained Project Scheduling Problem Solved with a Multi-Start Iterated Local Search Metaheuristic," Mathematics, MDPI, vol. 11(2), pages 1-25, January.
    9. Buddhakulsomsiri, Jirachai & Kim, David S., 2007. "Priority rule-based heuristic for multi-mode resource-constrained project scheduling problems with resource vacations and activity splitting," European Journal of Operational Research, Elsevier, vol. 178(2), pages 374-390, April.
    10. Hartmann, Sönke & Briskorn, Dirk, 2008. "A survey of variants and extensions of the resource-constrained project scheduling problem," Working Paper Series 02/2008, Hamburg School of Business Administration (HSBA).
    11. Pejman Peykani & Jafar Gheidar-Kheljani & Sheida Shahabadi & Seyyed Hassan Ghodsypour & Mojtaba Nouri, 2023. "A two-phase resource-constrained project scheduling approach for design and development of complex product systems," Operational Research, Springer, vol. 23(1), pages 1-25, March.
    12. Kolisch, R. & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Omega, Elsevier, vol. 29(3), pages 249-272, June.
    13. Weglarz, Jan & Józefowska, Joanna & Mika, Marek & Waligóra, Grzegorz, 2011. "Project scheduling with finite or infinite number of activity processing modes - A survey," European Journal of Operational Research, Elsevier, vol. 208(3), pages 177-205, February.
    14. Balouka, Noemie & Cohen, Izack, 2021. "A robust optimization approach for the multi-mode resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 291(2), pages 457-470.
    15. Osman Hürol Türkakın & David Arditi & Ekrem Manisalı, 2021. "Comparison of Heuristic Priority Rules in the Solution of the Resource-Constrained Project Scheduling Problem," Sustainability, MDPI, vol. 13(17), pages 1-17, September.
    16. Chen, Jiaqiong & Askin, Ronald G., 2009. "Project selection, scheduling and resource allocation with time dependent returns," European Journal of Operational Research, Elsevier, vol. 193(1), pages 23-34, February.
    17. Zhang, Yao & Zuo, Fei & Guan, Xin, 2020. "Integrating case-based analysis and fuzzy optimization for selecting project risk response actions," Physica A: Statistical Mechanics and its Applications, Elsevier, vol. 545(C).
    18. Paola Festa & Panos Pardalos, 2012. "Efficient solutions for the far from most string problem," Annals of Operations Research, Springer, vol. 196(1), pages 663-682, July.
    19. Ayşegül Altın & Bernard Fortz & Mikkel Thorup & Hakan Ümit, 2013. "Intra-domain traffic engineering with shortest path routing protocols," Annals of Operations Research, Springer, vol. 204(1), pages 65-95, April.
    20. Dengsheng Wu & Xiaoqian Zhu & Jie Wan & Chunbing Bao & Jianping Li, 2019. "A Multiobjective Optimization Approach for Selecting Risk Response Strategies of Software Project: From the Perspective of Risk Correlations," International Journal of Information Technology & Decision Making (IJITDM), World Scientific Publishing Co. Pte. Ltd., vol. 18(01), pages 339-364, January.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:reensy:v:237:y:2023:i:c:s0951832023003058. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: https://www.journals.elsevier.com/reliability-engineering-and-system-safety .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.