A key problem in project management is to decide which activities are the most important to manage and how best to manage them. A considerable amount of literature has been devoted to assigning “importance” measures to activities to help with this important task. When activity times are modeled as random variables, these activity importance measures are more complex and difficult to use. A key problem with all existing measures is that they summarize the importance in a single number. The result is that it is difficult for managers to determine a range of times for an activity that might be acceptable or unacceptable. In this paper, we develop sensitivity curves that display the most useful measures of project performance (in terms of schedule) as a function of an activity's time. The structure of the networks allows us to efficiently estimate these curves for all desired activities, all desired time ranges, and all desired measures in a single set of simulation runs. The resulting curves provide insights that are not available when considering summarized measures alone. Chief among these insights is the ability to identify an acceptable range of times for an activity that will not lead to negative scheduling consequences. © 2003 Wiley Periodicals, Inc. Naval Research Logistics 50: 481–497, 2003

Suggested Citation

  • R. Alan Bowman, 2003. "Sensitivity curves for effective project management," Naval Research Logistics (NRL), John Wiley & Sons, vol. 50(5), pages 481-497, August.
  • Handle: RePEc:wly:navres:v:50:y:2003:i:5:p:481-497
    DOI: 10.1002/nav.10064
    as

    Download full text from publisher

    File URL: https://doi.org/10.1002/nav.10064
    Download Restriction: no

    File URL: https://libkey.io/10.1002/nav.10064?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Bajis M. Dodin & Salah E. Elmaghraby, 1985. "Approximating the Criticality Indices of the Activities in PERT Networks," Management Science, INFORMS, vol. 31(2), pages 207-223, February.
    2. R. A. Bowman & J. A. Muckstadt, 1993. "Stochastic Analysis of Cyclic Schedules," Operations Research, INFORMS, vol. 41(5), pages 947-958, October.
    3. Sigal, C.E. & Pritsker, A.A.B. & Solberg, J.J., 1979. "The use of cutsets in Monte Carlo analysis of stochastic networks," Mathematics and Computers in Simulation (MATCOM), Elsevier, vol. 21(4), pages 376-384.
    4. D. G. Malcolm & J. H. Roseboom & C. E. Clark & W. Fazar, 1959. "Application of a Technique for Research and Development Program Evaluation," Operations Research, INFORMS, vol. 7(5), pages 646-669, October.
    5. Elmaghraby, S. E. & Fathi, Y. & Taner, M. R., 1999. "On the sensitivity of project variability to activity mean duration," International Journal of Production Economics, Elsevier, vol. 62(3), pages 219-232, September.
    6. V. G. Kulkarni & V. G. Adlakha, 1986. "Markov and Markov-Regenerative pert Networks," Operations Research, INFORMS, vol. 34(5), pages 769-781, October.
    7. J. J. Martin, 1965. "Distribution of the Time Through a Directed, Acyclic Network," Operations Research, INFORMS, vol. 13(1), pages 46-66, February.
    8. R. A. Bowman, 1995. "Efficient Estimation of Arc Criticalities in Stochastic Activity Networks," Management Science, INFORMS, vol. 41(1), pages 58-67, January.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Elmaghraby, Salah E., 2000. "On criticality and sensitivity in activity networks," European Journal of Operational Research, Elsevier, vol. 127(2), pages 220-238, December.
    2. Madadi, M. & Iranmanesh, H., 2012. "A management oriented approach to reduce a project duration and its risk (variability)," European Journal of Operational Research, Elsevier, vol. 219(3), pages 751-761.
    3. Bregman, Robert L., 2009. "A heuristic procedure for solving the dynamic probabilistic project expediting problem," European Journal of Operational Research, Elsevier, vol. 192(1), pages 125-137, January.
    4. Fernando Acebes & Javier Pajares & José M. González-Varona & Adolfo López-Paredes, 2021. "Project risk management from the bottom-up: Activity Risk Index," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 29(4), pages 1375-1396, December.
    5. Elmaghraby, S. E. & Fathi, Y. & Taner, M. R., 1999. "On the sensitivity of project variability to activity mean duration," International Journal of Production Economics, Elsevier, vol. 62(3), pages 219-232, September.
    6. Li, Xiaobo & Natarajan, Karthik & Teo, Chung-Piaw & Zheng, Zhichao, 2014. "Distributionally robust mixed integer linear programs: Persistency models with applications," European Journal of Operational Research, Elsevier, vol. 233(3), pages 459-473.
    7. Vanhoucke, Mario, 2010. "Using activity sensitivity and network topology information to monitor project time performance," Omega, Elsevier, vol. 38(5), pages 359-370, October.
    8. Azaron, Amir & Katagiri, Hideki & Sakawa, Masatoshi & Kato, Kosuke & Memariani, Azizollah, 2006. "A multi-objective resource allocation problem in PERT networks," European Journal of Operational Research, Elsevier, vol. 172(3), pages 838-854, August.
    9. Lee, Heejung & Suh, Hyo-Won, 2008. "Estimating the duration of stochastic workflow for product development process," International Journal of Production Economics, Elsevier, vol. 111(1), pages 105-117, January.
    10. Fatemi Ghomi, S. M. T. & Teimouri, E., 2002. "Path critical index and activity critical index in PERT networks," European Journal of Operational Research, Elsevier, vol. 141(1), pages 147-152, August.
    11. Hahn, Eugene David, 2008. "Mixture densities for project management activity times: A robust approach to PERT," European Journal of Operational Research, Elsevier, vol. 188(2), pages 450-459, July.
    12. Fatemi Ghomi, S. M. T. & Rabbani, M., 2003. "A new structural mechanism for reducibility of stochastic PERT networks," European Journal of Operational Research, Elsevier, vol. 145(2), pages 394-402, March.
    13. Azaron, Amir & Fatemi Ghomi, S.M.T., 2008. "Lower bound for the mean project completion time in dynamic PERT networks," European Journal of Operational Research, Elsevier, vol. 186(1), pages 120-127, April.
    14. R A Bowman, 2007. "Efficient sensitivity analysis of PERT network performance measures to significant changes in activity time parameters," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 58(10), pages 1354-1360, October.
    15. Azaron, Amir & Fynes, Brian & Modarres, Mohammad, 2011. "Due date assignment in repetitive projects," International Journal of Production Economics, Elsevier, vol. 129(1), pages 79-85, January.
    16. Azaron, Amir & Katagiri, Hideki & Kato, Kosuke & Sakawa, Masatoshi, 2006. "Longest path analysis in networks of queues: Dynamic scheduling problems," European Journal of Operational Research, Elsevier, vol. 174(1), pages 132-149, October.
    17. Williams, Terry, 1999. "Towards realism in network simulation," Omega, Elsevier, vol. 27(3), pages 305-314, June.
    18. Sobel, Matthew J. & Szmerekovsky, Joseph G. & Tilson, Vera, 2009. "Scheduling projects with stochastic activity duration to maximize expected net present value," European Journal of Operational Research, Elsevier, vol. 198(3), pages 697-705, November.
    19. Azaron, Amir & Katagiri, Hideki & Kato, Kosuke & Sakawa, Masatoshi, 2006. "Modelling complex assemblies as a queueing network for lead time control," European Journal of Operational Research, Elsevier, vol. 174(1), pages 150-168, October.
    20. Hermans, Ben & Leus, Roel & Looy, Bart Van, 2023. "Deciding on scheduling, secrecy, and patenting during the new product development process: The relevance of project planning models," Omega, Elsevier, vol. 116(C).

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:wly:navres:v:50:y:2003:i:5:p:481-497. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Wiley Content Delivery (email available below). General contact details of provider: https://doi.org/10.1002/(ISSN)1520-6750 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.