Project risk management from the bottom-up: Activity Risk Index

Author

Listed:
  • Fernando Acebes

    (Universidad de Valladolid)

  • Javier Pajares

    (Universidad de Valladolid)

  • José M. González-Varona

    (Universidad de Valladolid)

  • Adolfo López-Paredes

    (Universidad de Valladolid)

Abstract

Project managers need to manage risks throughout the project lifecycle and, thus, need to know how changes in activity durations influence project duration and risk. We propose a new indicator (the Activity Risk Index, ARI) that measures the contribution of each activity to the total project risk while it is underway. In particular, the indicator informs us about what activities contribute the most to the project’s uncertainty so that project managers can pay closer attention to the performance of these activities. The main difference between our indicator and other activity sensitivity metrics in the literature (e.g. Cruciality, Criticality, Significance, or Schedule Sensitivity Indices) is that our indicator is based on the Schedule Risk Baseline concept instead of on cost or schedule baselines. The new metric not only provides information at the beginning of the project, but also while it is underway. Furthermore, the ARI is the only one to offer a normalized result: if we add its value for each activity, the total sum is 100%.

Suggested Citation

  • Fernando Acebes & Javier Pajares & José M. González-Varona & Adolfo López-Paredes, 2021. "Project risk management from the bottom-up: Activity Risk Index," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 29(4), pages 1375-1396, December.
  • Handle: RePEc:spr:cejnor:v:29:y:2021:i:4:d:10.1007_s10100-020-00703-8
    DOI: 10.1007/s10100-020-00703-8
    as

    Download full text from publisher

    File URL: http://link.springer.com/10.1007/s10100-020-00703-8
    File Function: Abstract
    Download Restriction: Access to the full text of the articles in this series is restricted.

    File URL: https://libkey.io/10.1007/s10100-020-00703-8?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Bajis M. Dodin & Salah E. Elmaghraby, 1985. "Approximating the Criticality Indices of the Activities in PERT Networks," Management Science, INFORMS, vol. 31(2), pages 207-223, February.
    2. Fatemi Ghomi, S. M. T. & Teimouri, E., 2002. "Path critical index and activity critical index in PERT networks," European Journal of Operational Research, Elsevier, vol. 141(1), pages 147-152, August.
    3. Richard M. Van Slyke, 1963. "Letter to the Editor---Monte Carlo Methods and the PERT Problem," Operations Research, INFORMS, vol. 11(5), pages 839-860, October.
    4. R. A. Bowman & J. A. Muckstadt, 1993. "Stochastic Analysis of Cyclic Schedules," Operations Research, INFORMS, vol. 41(5), pages 947-958, October.
    5. Genaro Gutierrez & Anand Paul, 2000. "Analysis of the Effects of Uncertainty, Risk-Pooling, and Subcontracting Mechanisms on Project Performance," Operations Research, INFORMS, vol. 48(6), pages 927-938, December.
    6. J. J. Martin, 1965. "Distribution of the Time Through a Directed, Acyclic Network," Operations Research, INFORMS, vol. 13(1), pages 46-66, February.
    7. Mario Vanhoucke, 2016. "Integrated Project Management Sourcebook," Springer Books, Springer, edition 1, number 978-3-319-27373-0, September.
    8. Madadi, M. & Iranmanesh, H., 2012. "A management oriented approach to reduce a project duration and its risk (variability)," European Journal of Operational Research, Elsevier, vol. 219(3), pages 751-761.
    9. Chen, Shih-Pin, 2007. "Analysis of critical paths in a project network with fuzzy activity times," European Journal of Operational Research, Elsevier, vol. 183(1), pages 442-459, November.
    10. Chanas, Stefan & Zielinski, Pawel, 2002. "The computational complexity of the criticality problems in a network with interval activity times," European Journal of Operational Research, Elsevier, vol. 136(3), pages 541-550, February.
    11. A. R. Klingel, Jr., 1966. "Bias in Pert Project Completion Time Calculations for a Real Network," Management Science, INFORMS, vol. 13(4), pages 194-201, December.
    12. Vanhoucke, Mario, 2010. "Using activity sensitivity and network topology information to monitor project time performance," Omega, Elsevier, vol. 38(5), pages 359-370, October.
    13. Elmaghraby, Salah E., 2000. "On criticality and sensitivity in activity networks," European Journal of Operational Research, Elsevier, vol. 127(2), pages 220-238, December.
    14. Elmaghraby, S. E. & Fathi, Y. & Taner, M. R., 1999. "On the sensitivity of project variability to activity mean duration," International Journal of Production Economics, Elsevier, vol. 62(3), pages 219-232, September.
    15. R. A. Bowman, 1995. "Efficient Estimation of Arc Criticalities in Stochastic Activity Networks," Management Science, INFORMS, vol. 41(1), pages 58-67, January.
    16. Vanhoucke, Mario, 2011. "On the dynamic use of project performance and schedule risk information during projecttracking," Omega, Elsevier, vol. 39(4), pages 416-426, August.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Josefa Mula & Marija Bogataj, 2021. "OR in the industrial engineering of Industry 4.0: experiences from the Iberian Peninsula mirrored in CJOR," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 29(4), pages 1163-1184, December.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Madadi, M. & Iranmanesh, H., 2012. "A management oriented approach to reduce a project duration and its risk (variability)," European Journal of Operational Research, Elsevier, vol. 219(3), pages 751-761.
    2. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2021. "Using Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 288(3), pages 736-752.
    3. Vanhoucke, Mario, 2010. "Using activity sensitivity and network topology information to monitor project time performance," Omega, Elsevier, vol. 38(5), pages 359-370, October.
    4. Martens, Annelies & Vanhoucke, Mario, 2019. "The impact of applying effort to reduce activity variability on the project time and cost performance," European Journal of Operational Research, Elsevier, vol. 277(2), pages 442-453.
    5. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2022. "Using Earned Value Management and Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 297(2), pages 451-466.
    6. R. Alan Bowman, 2003. "Sensitivity curves for effective project management," Naval Research Logistics (NRL), John Wiley & Sons, vol. 50(5), pages 481-497, August.
    7. Vanhoucke, Mario, 2011. "On the dynamic use of project performance and schedule risk information during projecttracking," Omega, Elsevier, vol. 39(4), pages 416-426, August.
    8. Colin, Jeroen & Vanhoucke, Mario, 2014. "Setting tolerance limits for statistical project control using earned value management," Omega, Elsevier, vol. 49(C), pages 107-122.
    9. Elmaghraby, Salah E., 2000. "On criticality and sensitivity in activity networks," European Journal of Operational Research, Elsevier, vol. 127(2), pages 220-238, December.
    10. Cui, Nanfang & Demeulemeester, Erik & Bie, Li, 2016. "Incorporation of activity sensitivity measures into buffer management to manage project schedule riskAuthor-Name: Hu, Xuejun," European Journal of Operational Research, Elsevier, vol. 249(2), pages 717-727.
    11. Tao, Liangyan & Wu, Desheng & Liu, Sifeng & Lambert, James H., 2017. "Schedule risk analysis for new-product development: The GERT method extended by a characteristic function," Reliability Engineering and System Safety, Elsevier, vol. 167(C), pages 464-473.
    12. Stefan Creemers & Erik Demeulemeester & Stijn Vonder, 2014. "A new approach for quantitative risk analysis," Annals of Operations Research, Springer, vol. 213(1), pages 27-65, February.
    13. J-G Cho & B-J Yum, 2004. "Functional estimation of activity criticality indices and sensitivity analysis of expected project completion time," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 55(8), pages 850-859, August.
    14. Zarghami, Seyed Ashkan & Dumrak, Jantanee, 2021. "Aleatory uncertainty quantification of project resources and its application to project scheduling," Reliability Engineering and System Safety, Elsevier, vol. 211(C).
    15. R A Bowman, 2007. "Efficient sensitivity analysis of PERT network performance measures to significant changes in activity time parameters," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 58(10), pages 1354-1360, October.
    16. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2020. "The impact of a limited budget on the corrective action taking process," European Journal of Operational Research, Elsevier, vol. 286(3), pages 1070-1086.
    17. Luz Stella Cardona-Meza & Gerard Olivar-Tost, 2017. "Modeling and Simulation of Project Management through the PMBOK® Standard Using Complex Networks," Complexity, Hindawi, vol. 2017, pages 1-12, December.
    18. Martens, Annelies & Vanhoucke, Mario, 2017. "A buffer control method for top-down project control," European Journal of Operational Research, Elsevier, vol. 262(1), pages 274-286.
    19. Xing Pan & Lunhu Hu & Ziling Xin & Shenghan Zhou & Yanmei Lin & Yong Wu, 2018. "Risk Scenario Generation Based on Importance Measure Analysis," Sustainability, MDPI, vol. 10(9), pages 1-18, September.
    20. Bregman, Robert L., 2009. "A heuristic procedure for solving the dynamic probabilistic project expediting problem," European Journal of Operational Research, Elsevier, vol. 192(1), pages 125-137, January.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:spr:cejnor:v:29:y:2021:i:4:d:10.1007_s10100-020-00703-8. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Sonal Shukla or Springer Nature Abstracting and Indexing (email available below). General contact details of provider: http://www.springer.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.