Incorporation of activity sensitivity measures into buffer management to manage project schedule riskAuthor-Name: Hu, Xuejun
Author
Abstract
Suggested Citation
DOI: 10.1016/j.ejor.2015.08.066
Download full text from publisher
As the access to this document is restricted, you may want to search for a different version of it.
References listed on IDEAS
- Bowman, R. Alan, 2006. "Developing activity duration specification limits for effective project control," European Journal of Operational Research, Elsevier, vol. 174(2), pages 1191-1204, October.
- Junguang Zhang & Xiwei Song & Hongyu Chen & Ruixia (Sandy) Shi, 2015. "Optimisation of critical chain sequencing based on activities’ information flow interactions," International Journal of Production Research, Taylor & Francis Journals, vol. 53(20), pages 6231-6241, October.
- Mohamed Ali Khemakhem & Hédi Chtourou, 2013. "Efficient robustness measures for the resource-constrained project scheduling problem," International Journal of Industrial and Systems Engineering, Inderscience Enterprises Ltd, vol. 14(2), pages 245-267.
- Erik Demeulemeester & Willy Herroelen, 1992. "A Branch-and-Bound Procedure for the Multiple Resource-Constrained Project Scheduling Problem," Management Science, INFORMS, vol. 38(12), pages 1803-1818, December.
- Junguang Zhang & Ruixia Shi & Estrella Diaz, 2015. "Dynamic monitoring and control of software project effort based on an effort buffer," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 66(9), pages 1555-1565, September.
- Vanhoucke, Mario, 2010. "Using activity sensitivity and network topology information to monitor project time performance," Omega, Elsevier, vol. 38(5), pages 359-370, October.
- Wendi Tian & Erik Demeulemeester, 2014. "Railway scheduling reduces the expected project makespan over roadrunner scheduling in a multi-mode project scheduling environment," Annals of Operations Research, Springer, vol. 213(1), pages 271-291, February.
- Elmaghraby, Salah E., 2000. "On criticality and sensitivity in activity networks," European Journal of Operational Research, Elsevier, vol. 127(2), pages 220-238, December.
- Tukel, Oya I. & Rom, Walter O. & Eksioglu, Sandra Duni, 2006. "An investigation of buffer sizing techniques in critical chain scheduling," European Journal of Operational Research, Elsevier, vol. 172(2), pages 401-416, July.
- Herroelen, Willy & Leus, Roel, 2005. "Project scheduling under uncertainty: Survey and research potentials," European Journal of Operational Research, Elsevier, vol. 165(2), pages 289-306, September.
- R A Bowman, 2007. "Efficient sensitivity analysis of PERT network performance measures to significant changes in activity time parameters," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 58(10), pages 1354-1360, October.
- Stefan Creemers & Erik Demeulemeester & Stijn Vonder, 2014.
"A new approach for quantitative risk analysis,"
Annals of Operations Research, Springer, vol. 213(1), pages 27-65, February.
- S. Creemers & E. Demeulemeester & S. van de Vonder, 2013. "A new approach for quantitative risk analysis," Post-Print hal-00846528, HAL.
- Kolisch, Rainer & Sprecher, Arno, 1996. "PSPLIB - a project scheduling problem library," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 396, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Xuejun Hu & Nanfang Cui & Erik Demeulemeester, 2015. "Effective expediting to improve project due date and cost performance through buffer management," International Journal of Production Research, Taylor & Francis Journals, vol. 53(5), pages 1460-1471, March.
- Rabbani, M. & Fatemi Ghomi, S.M.T. & Jolai, F. & Lahiji, N.S., 2007. "A new heuristic for resource-constrained project scheduling in stochastic networks using critical chain concept," European Journal of Operational Research, Elsevier, vol. 176(2), pages 794-808, January.
- Vanhoucke, Mario, 2011. "On the dynamic use of project performance and schedule risk information during projecttracking," Omega, Elsevier, vol. 39(4), pages 416-426, August.
- Madadi, M. & Iranmanesh, H., 2012. "A management oriented approach to reduce a project duration and its risk (variability)," European Journal of Operational Research, Elsevier, vol. 219(3), pages 751-761.
- Umble, Michael & Umble, Elisabeth J., 2006. "Utilizing buffer management to improve performance in a healthcare environment," European Journal of Operational Research, Elsevier, vol. 174(2), pages 1060-1075, October.
- James H. Patterson, 1984. "A Comparison of Exact Approaches for Solving the Multiple Constrained Resource, Project Scheduling Problem," Management Science, INFORMS, vol. 30(7), pages 854-867, July.
Citations
Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
Cited by:
- Bordley, Robert F. & Keisler, Jeffrey M. & Logan, Tom M., 2019. "Managing projects with uncertain deadlines," European Journal of Operational Research, Elsevier, vol. 274(1), pages 291-302.
- Junguang Zhang & Xiwei Song & Estrella Díaz, 2017. "Critical chain project buffer sizing based on resource constraints," International Journal of Production Research, Taylor & Francis Journals, vol. 55(3), pages 671-683, February.
- Tao, Liangyan & Wu, Desheng & Liu, Sifeng & Lambert, James H., 2017. "Schedule risk analysis for new-product development: The GERT method extended by a characteristic function," Reliability Engineering and System Safety, Elsevier, vol. 167(C), pages 464-473.
- Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
- Martens, Annelies & Vanhoucke, Mario, 2019. "The impact of applying effort to reduce activity variability on the project time and cost performance," European Journal of Operational Research, Elsevier, vol. 277(2), pages 442-453.
- Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2022. "Using Earned Value Management and Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 297(2), pages 451-466.
- Mengqi Zhao & Xiaoling Wang & Jia Yu & Lei Bi & Yao Xiao & Jun Zhang, 2020. "Optimization of Construction Duration and Schedule Robustness Based on Hybrid Grey Wolf Optimizer with Sine Cosine Algorithm," Energies, MDPI, vol. 13(1), pages 1-17, January.
- Öncü Hazir & Gündüz Ulusoy, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," Post-Print hal-02898162, HAL.
- Xuejun Hu & Jianjiang Wang & Kaijun Leng, 2019. "The Interaction Between Critical Chain Sequencing, Buffer Sizing, and Reactive Actions in a CC/BM Framework," Asia-Pacific Journal of Operational Research (APJOR), World Scientific Publishing Co. Pte. Ltd., vol. 36(03), pages 1-22, June.
- Xuejun Hu & Erik Demeulemeester & Nanfang Cui & Jianjiang Wang & Wendi Tian, 2017. "Improved critical chain buffer management framework considering resource costs and schedule stability," Flexible Services and Manufacturing Journal, Springer, vol. 29(2), pages 159-183, June.
- Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2021. "Using Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 288(3), pages 736-752.
- Servranckx, Tom & Vanhoucke, Mario & Aouam, Tarik, 2021. "Practical application of reference class forecasting for cost and time estimations: Identifying the properties of similarity," European Journal of Operational Research, Elsevier, vol. 295(3), pages 1161-1179.
- Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2020. "The impact of a limited budget on the corrective action taking process," European Journal of Operational Research, Elsevier, vol. 286(3), pages 1070-1086.
- Junguang Zhang & Dan Wan, 2021. "Determination of early warning time window for bottleneck resource buffer," Annals of Operations Research, Springer, vol. 300(1), pages 289-305, May.
Most related items
These are the items that most often cite the same works as this one and are cited by the same works as this one.- Xuejun Hu & Erik Demeulemeester & Nanfang Cui & Jianjiang Wang & Wendi Tian, 2017. "Improved critical chain buffer management framework considering resource costs and schedule stability," Flexible Services and Manufacturing Journal, Springer, vol. 29(2), pages 159-183, June.
- Yan Zhao & Nanfang Cui & Wendi Tian, 2020. "A two-stage approach for the critical chain project rescheduling," Annals of Operations Research, Springer, vol. 285(1), pages 67-95, February.
- Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
- Vaseghi, Forough & Martens, Annelies & Vanhoucke, Mario, 2024. "Analysis of the impact of corrective actions for stochastic project networks," European Journal of Operational Research, Elsevier, vol. 316(2), pages 503-518.
- Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2021. "Using Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 288(3), pages 736-752.
- Martens, Annelies & Vanhoucke, Mario, 2019. "The impact of applying effort to reduce activity variability on the project time and cost performance," European Journal of Operational Research, Elsevier, vol. 277(2), pages 442-453.
- Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2022. "Using Earned Value Management and Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 297(2), pages 451-466.
- Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2020. "The impact of a limited budget on the corrective action taking process," European Journal of Operational Research, Elsevier, vol. 286(3), pages 1070-1086.
- Fernando Acebes & Javier Pajares & Jose M Gonzalez-Varona & Adolfo Lopez-Paredes, 2024. "Project Risk Management from the bottom-up: Activity Risk Index," Papers 2406.00078, arXiv.org.
- Martens, Annelies & Vanhoucke, Mario, 2017. "A buffer control method for top-down project control," European Journal of Operational Research, Elsevier, vol. 262(1), pages 274-286.
- She, Bingling & Chen, Bo & Hall, Nicholas G., 2021. "Buffer sizing in critical chain project management by network decomposition," Omega, Elsevier, vol. 102(C).
- Yangyang Liang & Nanfang Cui & Tian Wang & Erik Demeulemeester, 2019. "Robust resource-constrained max-NPV project scheduling with stochastic activity duration," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 41(1), pages 219-254, March.
- Zhang, Junguang & Song, Xiwei & Díaz, Estrella, 2016. "Project buffer sizing of a critical chain based on comprehensive resource tightness," European Journal of Operational Research, Elsevier, vol. 248(1), pages 174-182.
- Öncü Hazir & Gündüz Ulusoy, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," Post-Print hal-02898162, HAL.
- Fernando Acebes & Javier Pajares & José M. González-Varona & Adolfo López-Paredes, 2021. "Project risk management from the bottom-up: Activity Risk Index," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 29(4), pages 1375-1396, December.
- Colin, Jeroen & Vanhoucke, Mario, 2014. "Setting tolerance limits for statistical project control using earned value management," Omega, Elsevier, vol. 49(C), pages 107-122.
- Wendi Tian & Erik Demeulemeester, 2014. "Railway scheduling reduces the expected project makespan over roadrunner scheduling in a multi-mode project scheduling environment," Annals of Operations Research, Springer, vol. 213(1), pages 271-291, February.
- Xiong, Jian & Leus, Roel & Yang, Zhenyu & Abbass, Hussein A., 2016. "Evolutionary multi-objective resource allocation and scheduling in the Chinese navigation satellite system project," European Journal of Operational Research, Elsevier, vol. 251(2), pages 662-675.
- Sönke Hartmann, 1998. "A competitive genetic algorithm for resource‐constrained project scheduling," Naval Research Logistics (NRL), John Wiley & Sons, vol. 45(7), pages 733-750, October.
- Junguang Zhang & Dan Wan, 2021. "Determination of early warning time window for bottleneck resource buffer," Annals of Operations Research, Springer, vol. 300(1), pages 289-305, May.
More about this item
Keywords
Buffer management; Schedule monitoring; Activity sensitivity; Schedule risk; Action threshold;All these keywords.
Statistics
Access and download statisticsCorrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:ejores:v:249:y:2016:i:2:p:717-727. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/eor .
Please note that corrections may take a couple of weeks to filter through the various RePEc services.