Different cost performance: different determinants?

Author

Listed:
  • Cantarelli, C.C.
  • van Wee, B.
  • Molin, E.J.E.
  • Flyvbjerg, B.

Abstract

This paper examines three independent explanatory variables and their relation with cost overrun in order to decide whether this is different for Dutch infrastructure projects compared to worldwide findings. The three independent variables are project type (road, rail, and fixed link projects), project size (measured in terms of estimated costs) and the length of the project implementation phase. For Dutch projects, average cost overrun is 10.6% for rail, 18.6% for roads and 21.7% for fixed links. For project size, small Dutch projects have the largest average percentage cost overruns but in terms of total overrun, large projects have a larger share. The length of the implementation phase and especially the length of the pre-construction phase are important determinants of cost overruns in the Netherlands. With each additional year of pre-construction, percentage cost overrun increases by five percentage points. In contrast, the length of the construction phase has hardly any influence on cost overruns. This is an important contribution to current knowledge about cost overruns, because the period in which projects are most prone to cost overruns is narrowed down considerably, at least in the Netherlands. This means that to determine the causes and cures of overruns one should focus on the period.

Suggested Citation

  • Cantarelli, C.C. & van Wee, B. & Molin, E.J.E. & Flyvbjerg, B., 2012. "Different cost performance: different determinants?," Transport Policy, Elsevier, vol. 22(C), pages 88-95.
  • Handle: RePEc:eee:trapol:v:22:y:2012:i:c:p:88-95
    DOI: 10.1016/j.tranpol.2012.04.002
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0967070X12000571
    Download Restriction: Full text for ScienceDirect subscribers only

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Mackie, Peter & Preston, John, 1998. "Twenty-one sources of error and bias in transport project appraisal," Transport Policy, Elsevier, vol. 5(1), pages 1-7, January.
    2. Bent Flyvbjerg & Mette K. Skamris holm & Søren L. Buhl, 2003. "How common and how large are cost overruns in transport infrastructure projects?," Transport Reviews, Taylor & Francis Journals, vol. 23(1), pages 71-88, January.
    3. Bent Flyvbjerg, 2007. "Policy and Planning for Large-Infrastructure Projects: Problems, Causes, Cures," Environment and Planning B, , vol. 34(4), pages 578-597, August.
    4. Odeck, James, 2004. "Cost overruns in road construction--what are their sizes and determinants?," Transport Policy, Elsevier, vol. 11(1), pages 43-53, January.
    5. Chantal C Cantarelli & Bent Flyvbjerg & Bert van Wee & Eric J E Molin, 2010. "Lock-in and its Influence on the Project Performance of Large-Scale Transportation Infrastructure Projects: Investigating the Way in Which Lock-in Can Emerge and Affect Cost Overruns," Environment and Planning B, , vol. 37(5), pages 792-807, October.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Johan Larsson & Per Erik Eriksson & Thomas Olofsson & Peter Simonsson, 2014. "Industrialized construction in the Swedish infrastructure sector: core elements and barriers," Construction Management and Economics, Taylor & Francis Journals, vol. 32(1-2), pages 83-96, February.
    2. Per Erik Eriksson & Stefan Olander & Henrik Szentes & Kristian Widén, 2014. "Managing short-term efficiency and long-term development through industrialized construction," Construction Management and Economics, Taylor & Francis Journals, vol. 32(1-2), pages 97-108, February.
    3. Miranda Sarmento, J.J., 2014. "Public private partnerships," Other publications TiSEM c7d4c978-234c-4f88-83ed-1, Tilburg University, School of Economics and Management.
    4. Jarosław Górecki & Manuel Díaz-Madroñero, 2020. "Who Risks and Wins?—Simulated Cost Variance in Sustainable Construction Projects," Sustainability, MDPI, Open Access Journal, vol. 12(8), pages 1-31, April.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:trapol:v:22:y:2012:i:c:p:88-95. See general information about how to correct material in RePEc.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: (Haili He). General contact details of provider: http://www.elsevier.com/wps/find/journaldescription.cws_home/30473/description#description .

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service hosted by the Research Division of the Federal Reserve Bank of St. Louis . RePEc uses bibliographic data supplied by the respective publishers.