Different Cost Performance: Different Determinants? The Case of Cost Overruns in Dutch Transportation Infrastructure Projects

Author

Listed:
  • Chantal C. Cantarelli
  • Bert van Wee
  • Eric J. E. Molin
  • Bent Flyvbjerg

Abstract

This paper examines three independent explanatory variables and their relation with cost overrun in order to decide whether this is different for Dutch infrastructure projects compared to worldwide findings. The three independent variables are project type (road, rail, and fixed link projects), project size (measured in terms of estimated costs) and the length of the project implementation phase. For Dutch projects, average cost overrun is 10.6% for rail, 18.6% for roads and 21.7% for fixed links. For project size, small Dutch projects have the largest average percentage cost overruns but in terms of total overrun, large projects have a larger share. The length of the implementation phase and especially the length of the pre-construction phase are important determinants of cost overruns in the Netherlands. With each additional year of pre-construction, percentage cost overrun increases by five percentage points. In contrast, the length of the construction phase has hardly any influence on cost overruns. This is an important contribution to current knowledge about cost overruns, because the period in which projects are most prone to cost overruns is narrowed down considerably, at least in the Netherlands. This means that period can be focused on to determine the causes and cures of overruns.

Suggested Citation

  • Chantal C. Cantarelli & Bert van Wee & Eric J. E. Molin & Bent Flyvbjerg, 2013. "Different Cost Performance: Different Determinants? The Case of Cost Overruns in Dutch Transportation Infrastructure Projects," Papers 1307.2179, arXiv.org, revised Jan 2015.
  • Handle: RePEc:arx:papers:1307.2179
    as

    Download full text from publisher

    File URL: http://arxiv.org/pdf/1307.2179
    File Function: Latest version
    Download Restriction: no

    References listed on IDEAS

    as
    1. Chantal C Cantarelli & Bent Flyvbjerg & Bert van Wee & Eric J E Molin, 2010. "Lock-in and its Influence on the Project Performance of Large-Scale Transportation Infrastructure Projects: Investigating the Way in Which Lock-in Can Emerge and Affect Cost Overruns," Environment and Planning B, , vol. 37(5), pages 792-807, October.
    2. Bent Flyvbjerg & Mette K. Skamris holm & Søren L. Buhl, 2003. "How common and how large are cost overruns in transport infrastructure projects?," Transport Reviews, Taylor & Francis Journals, vol. 23(1), pages 71-88, January.
    Full references (including those not matched with items on IDEAS)

    More about this item

    NEP fields

    This paper has been announced in the following NEP Reports:

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:arx:papers:1307.2179. See general information about how to correct material in RePEc.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: (arXiv administrators). General contact details of provider: http://arxiv.org/ .

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service hosted by the Research Division of the Federal Reserve Bank of St. Louis . RePEc uses bibliographic data supplied by the respective publishers.