Different Cost Performance: Different Determinants? The Case of Cost Overruns in Dutch Transportation Infrastructure Projects

Author

Listed:
  • Chantal C. Cantarelli
  • Bert van Wee
  • Eric J. E. Molin
  • Bent Flyvbjerg

Abstract

This paper examines three independent explanatory variables and their relation with cost overrun in order to decide whether this is different for Dutch infrastructure projects compared to worldwide findings. The three independent variables are project type (road, rail, and fixed link projects), project size (measured in terms of estimated costs) and the length of the project implementation phase. For Dutch projects, average cost overrun is 10.6% for rail, 18.6% for roads and 21.7% for fixed links. For project size, small Dutch projects have the largest average percentage cost overruns but in terms of total overrun, large projects have a larger share. The length of the implementation phase and especially the length of the pre-construction phase are important determinants of cost overruns in the Netherlands. With each additional year of pre-construction, percentage cost overrun increases by five percentage points. In contrast, the length of the construction phase has hardly any influence on cost overruns. This is an important contribution to current knowledge about cost overruns, because the period in which projects are most prone to cost overruns is narrowed down considerably, at least in the Netherlands. This means that period can be focused on to determine the causes and cures of overruns.

Suggested Citation

  • Chantal C. Cantarelli & Bert van Wee & Eric J. E. Molin & Bent Flyvbjerg, 2013. "Different Cost Performance: Different Determinants? The Case of Cost Overruns in Dutch Transportation Infrastructure Projects," Papers 1307.2179, arXiv.org, revised Jan 2015.
  • Handle: RePEc:arx:papers:1307.2179
    as

    Download full text from publisher

    File URL: http://arxiv.org/pdf/1307.2179
    File Function: Latest version
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Bent Flyvbjerg & Mette K. Skamris holm & Søren L. Buhl, 2003. "How common and how large are cost overruns in transport infrastructure projects?," Transport Reviews, Taylor & Francis Journals, vol. 23(1), pages 71-88, January.
    2. Odeck, James, 2004. "Cost overruns in road construction--what are their sizes and determinants?," Transport Policy, Elsevier, vol. 11(1), pages 43-53, January.
    3. Chantal C Cantarelli & Bent Flyvbjerg & Bert van Wee & Eric J E Molin, 2010. "Lock-in and its Influence on the Project Performance of Large-Scale Transportation Infrastructure Projects: Investigating the Way in Which Lock-in Can Emerge and Affect Cost Overruns," Environment and Planning B, , vol. 37(5), pages 792-807, October.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Cantarelli, C.C. & Molin, E.J.E. & van Wee, B. & Flyvbjerg, B., 2012. "Characteristics of cost overruns for Dutch transport infrastructure projects and the importance of the decision to build and project phases," Transport Policy, Elsevier, vol. 22(C), pages 49-56.
    2. Abeysekara, Baudhi & Perera, Piyaruwan & Chhipi Shrestha, Gyan Kumar & Gunaruwan, Lalithasiri & Kumarage, Amal & Sadiq, Rehan & Hewage, Kasun, 2021. "Improving the capital deployment efficiency: An infrastructure investment planning process in transportation project," Research in Transportation Economics, Elsevier, vol. 88(C).
    3. Love, Peter E.D. & Sing, Michael C.P. & Ika, Lavagnon A. & Newton, Sidney, 2019. "The cost performance of transportation projects: The fallacy of the Planning Fallacy account," Transportation Research Part A: Policy and Practice, Elsevier, vol. 122(C), pages 1-20.
    4. Cantarelli, C.C. & van Wee, B. & Molin, E.J.E. & Flyvbjerg, B., 2012. "Different cost performance: different determinants?," Transport Policy, Elsevier, vol. 22(C), pages 88-95.
    5. Cantarelli, C.C. & Flyvbjerg, B. & Buhl, S.L., 2012. "Geographical variation in project cost performance: the Netherlands versus worldwide," Journal of Transport Geography, Elsevier, vol. 24(C), pages 324-331.
    6. Holz-Rau, Christian & Scheiner, Joachim, 2011. "Safety and travel time in cost-benefit analysis: A sensitivity analysis for North Rhine-Westphalia," Transport Policy, Elsevier, vol. 18(2), pages 336-346, March.
    7. Love, Peter E.D. & Ika, Lavagnon A. & Ahiaga-Dagbui, Dominic D., 2019. "On de-bunking ‘fake news’ in a post truth era: Why does the Planning Fallacy explanation for cost overruns fall short?," Transportation Research Part A: Policy and Practice, Elsevier, vol. 126(C), pages 397-408.
    8. Hugo Priemus & Bert van Wee (ed.), 2013. "International Handbook on Mega-Projects," Books, Edward Elgar Publishing, number 14791.
    9. Chantal C. Cantarelli & Bent Flyvbjerg, 2013. "Mega-projects’ cost performance and lock-in: problems and solutions," Chapters, in: Hugo Priemus & Bert van Wee (ed.), International Handbook on Mega-Projects, chapter 15, pages 333-355, Edward Elgar Publishing.
    10. Chong, Uven & Hopkins, Omar, 2016. "An international experience on the evolution of road costs during the project life cycle," Transport Policy, Elsevier, vol. 48(C), pages 60-66.
    11. Agnieszka Huterska, 2017. "Public-Private Partnership in Building Sustainable Development of the Kuyavian-Pomeranian Voivodship," European Journal of Interdisciplinary Studies Articles, Revistia Research and Publishing, vol. 3, September.
    12. Petter Osmundsen & Kristin Helen Roll, 2016. "Rig Rates and Drilling Speed: Reinforcing Effects," CESifo Working Paper Series 5895, CESifo.
    13. Steen Lichtenberg, 2016. "Successful Control of Major Project Budgets," Administrative Sciences, MDPI, vol. 6(3), pages 1-14, July.
    14. Lindsey, Robin & de Palma, André, 2014. "Cost recovery from congestion tolls with long-run uncertainty," Economics of Transportation, Elsevier, vol. 3(2), pages 119-132.
    15. C. Guccio & G. Pignataro & I. Rizzo, 2012. "Determinants of adaptation costs in procurement: an empirical estimation on Italian public works contracts," Applied Economics, Taylor & Francis Journals, vol. 44(15), pages 1891-1909, May.
    16. Miranda Sarmento, J.J. & Renneboog, Luc, 2017. "Cost overruns in public sector investment projects," Other publications TiSEM 51799a3e-4c78-4dbd-b330-b, Tilburg University, School of Economics and Management.
    17. Dejan Makovšek & Marian Moszoro, 2018. "Risk pricing inefficiency in public–private partnerships," Transport Reviews, Taylor & Francis Journals, vol. 38(3), pages 298-321, May.
    18. Catalão, Francisco Pinheiro & Cruz, Carlos Oliveira & Sarmento, Joaquim Miranda, 2019. "The determinants of cost deviations and overruns in transport projects, an endogenous models approach," Transport Policy, Elsevier, vol. 74(C), pages 224-238.
    19. Nandita Vadali & Anand Prakash Tiwari & Thillai Rajan A., 2014. "Effect of the Political Environment on Public Private Partnership Projects," Journal of Infrastructure Development, India Development Foundation, vol. 6(2), pages 145-165, December.
    20. Cavalieri, Marina & Cristaudo, Rossana & Guccio, Calogero, 2019. "On the magnitude of cost overruns throughout the project life-cycle: An assessment for the Italian transport infrastructure projects," Transport Policy, Elsevier, vol. 79(C), pages 21-36.

    More about this item

    NEP fields

    This paper has been announced in the following NEP Reports:

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:arx:papers:1307.2179. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: arXiv administrators (email available below). General contact details of provider: http://arxiv.org/ .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.