IDEAS home Printed from https://ideas.repec.org/a/plo/pone00/0265087.html
   My bibliography  Save this article

Research on the factors of extremely short construction period under the sufficient resources based on Grey-DEMATEL-ISM

Author

Listed:
  • Junlong Peng
  • Chao Peng
  • Mengyao Wang
  • Ke Hu
  • Dubin Wu

Abstract

Under the condition of sufficient resources, there are many factors affecting the realization of extremely short construction period of engineering construction projects. Based on literature review and questionnaire survey, this paper firstly selected 17 influencing factors from the five dimensions of design, management, technology, policy and environment. And the factor analytic hierarchy process model was established based on Grey-DEMATEL-ISM. The model introduced the improved grey system theory and combined decision-making trial and evaluation laboratory (DEMATEL) with interpretative structural modeling method (ISM). In addition, the model can not only identify the critical factors in the system, but also present the internal logical relationship between the influencing factors through the multi-level hierarchical structure diagram. Finally, through the analysis of the influencing factors of extremely short construction period under the sufficient resources, it defined that the key factor is the natural environment and second is the structure type. The methodology implemented in this paper helps decision makers and managers of construction projects to understand the interrelationship and degree of influence among factors affecting the duration under the condition of sufficient resources, to effectively grasp key factors, and to effectively achieve project success.

Suggested Citation

  • Junlong Peng & Chao Peng & Mengyao Wang & Ke Hu & Dubin Wu, 2022. "Research on the factors of extremely short construction period under the sufficient resources based on Grey-DEMATEL-ISM," PLOS ONE, Public Library of Science, vol. 17(3), pages 1-21, March.
  • Handle: RePEc:plo:pone00:0265087
    DOI: 10.1371/journal.pone.0265087
    as

    Download full text from publisher

    File URL: https://journals.plos.org/plosone/article?id=10.1371/journal.pone.0265087
    Download Restriction: no

    File URL: https://journals.plos.org/plosone/article/file?id=10.1371/journal.pone.0265087&type=printable
    Download Restriction: no

    File URL: https://libkey.io/10.1371/journal.pone.0265087?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2020. "Delay Factors Management and Ranking for Reconstruction and Rehabilitation Projects Based on the Relative Importance Index (RII)," Sustainability, MDPI, vol. 12(15), pages 1-21, July.
    2. Tan, Samson & Moinuddin, Khalid, 2019. "Systematic review of human and organizational risks for probabilistic risk analysis in high-rise buildings," Reliability Engineering and System Safety, Elsevier, vol. 188(C), pages 233-250.
    3. Abdulquadri Ade Bilau & Emlyn Witt & Irene Lill, 2018. "Practice Framework for the Management of Post-Disaster Housing Reconstruction Programmes," Sustainability, MDPI, vol. 10(11), pages 1-26, October.
    4. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2018. "Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project," Sustainability, MDPI, vol. 10(12), pages 1-18, December.
    5. Kettunen, Janne & Bunn, Derek W., 2016. "Risk induced resource dependency in capacity investments," European Journal of Operational Research, Elsevier, vol. 250(3), pages 914-924.
    6. Weglarz, Jan & Józefowska, Joanna & Mika, Marek & Waligóra, Grzegorz, 2011. "Project scheduling with finite or infinite number of activity processing modes - A survey," European Journal of Operational Research, Elsevier, vol. 208(3), pages 177-205, February.
    7. Lotfabadi, Pooya, 2014. "High-rise buildings and environmental factors," Renewable and Sustainable Energy Reviews, Elsevier, vol. 38(C), pages 285-295.
    8. Jih-Kuang Chen, 2021. "Improved DEMATEL-ISM integration approach for complex systems," PLOS ONE, Public Library of Science, vol. 16(7), pages 1-16, July.
    9. Kamali, Mohammad & Hewage, Kasun, 2016. "Life cycle performance of modular buildings: A critical review," Renewable and Sustainable Energy Reviews, Elsevier, vol. 62(C), pages 1171-1183.
    10. P. Velumani & N. V. N. Nampoothiri & M. Urbański, 2021. "A Comparative Study of Models for the Construction Duration Prediction in Highway Road Projects of India," Sustainability, MDPI, vol. 13(8), pages 1-13, April.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Estévez-Fernández, Arantza, 2012. "A game theoretical approach to sharing penalties and rewards in projects," European Journal of Operational Research, Elsevier, vol. 216(3), pages 647-657.
    2. Byung-Cheon Choi & Changmuk Kang, 2019. "A linear time–cost tradeoff problem with multiple milestones under a comb graph," Journal of Combinatorial Optimization, Springer, vol. 38(2), pages 341-361, August.
    3. Servranckx, Tom & Vanhoucke, Mario, 2019. "Strategies for project scheduling with alternative subgraphs under uncertainty: similar and dissimilar sets of schedules," European Journal of Operational Research, Elsevier, vol. 279(1), pages 38-53.
    4. Nima Zoraghi & Aria Shahsavar & Babak Abbasi & Vincent Peteghem, 2017. "Multi-mode resource-constrained project scheduling problem with material ordering under bonus–penalty policies," TOP: An Official Journal of the Spanish Society of Statistics and Operations Research, Springer;Sociedad de Estadística e Investigación Operativa, vol. 25(1), pages 49-79, April.
    5. Luis F. Machado-Domínguez & Carlos D. Paternina-Arboleda & Jorge I. Vélez & Agustin Barrios-Sarmiento, 2021. "A memetic algorithm to address the multi-node resource-constrained project scheduling problem," Journal of Scheduling, Springer, vol. 24(4), pages 413-429, August.
    6. Ellinas, Christos & Allan, Neil & Johansson, Anders, 2016. "Project systemic risk: Application examples of a network model," International Journal of Production Economics, Elsevier, vol. 182(C), pages 50-62.
    7. Chris Turner & John Oyekan & Lampros K. Stergioulas, 2021. "Distributed Manufacturing: A New Digital Framework for Sustainable Modular Construction," Sustainability, MDPI, vol. 13(3), pages 1-16, February.
    8. Juliet Akola & James Chakwizira & Emaculate Ingwani & Peter Bikam, 2023. "Awareness Level of Spatial Planning Tools for Disaster Risk Reduction in Informal Settlements in Mopani District, South Africa," Sustainability, MDPI, vol. 15(6), pages 1-13, March.
    9. Ripon K. Chakrabortty & Ruhul A. Sarker & Daryl L. Essam, 2020. "Single mode resource constrained project scheduling with unreliable resources," Operational Research, Springer, vol. 20(3), pages 1369-1403, September.
    10. Moahd Alghuson, 2023. "Exploring the Transport Infrastructure Sustainability Performance: An Investigation of the Transportation Projects in Saudi Arabia," Sustainability, MDPI, vol. 15(19), pages 1-17, September.
    11. Lovely S. Mores & Jeongwoo Lee & Woongkyoo Bae, 2019. "University-Community Partnerships: A Local Planning Co-Production Study on Calabarzon, Philippines," Sustainability, MDPI, vol. 11(7), pages 1-16, March.
    12. Lei Jiang & Zhongfu Li & Long Li & Yunli Gao, 2018. "Constraints on the Promotion of Prefabricated Construction in China," Sustainability, MDPI, vol. 10(7), pages 1, July.
    13. Liu, Zhichen & Li, Ying & Zhang, Zhaoyi & Yu, Wenbo, 2022. "A new evacuation accessibility analysis approach based on spatial information," Reliability Engineering and System Safety, Elsevier, vol. 222(C).
    14. Pei Dang & Zhanwen Niu & Shang Gao & Lei Hou & Guomin Zhang, 2020. "Critical Factors Influencing the Sustainable Construction Capability in Prefabrication of Chinese Construction Enterprises," Sustainability, MDPI, vol. 12(21), pages 1-21, October.
    15. Beşikci, Umut & Bilge, Ümit & Ulusoy, Gündüz, 2015. "Multi-mode resource constrained multi-project scheduling and resource portfolio problem," European Journal of Operational Research, Elsevier, vol. 240(1), pages 22-31.
    16. Naber, Anulark & Kolisch, Rainer, 2014. "MIP models for resource-constrained project scheduling with flexible resource profiles," European Journal of Operational Research, Elsevier, vol. 239(2), pages 335-348.
    17. Kim, Rakhyun & Tae, Sungho & Roh, Seungjun, 2017. "Development of low carbon durability design for green apartment buildings in South Korea," Renewable and Sustainable Energy Reviews, Elsevier, vol. 77(C), pages 263-272.
    18. Mauricio Diéguez & Jaime Bustos & Carlos Cares, 2020. "Mapping the variations for implementing information security controls to their operational research solutions," Information Systems and e-Business Management, Springer, vol. 18(2), pages 157-186, June.
    19. Jeunet, Jully & Bou Orm, Mayassa, 2020. "Optimizing temporary work and overtime in the Time Cost Quality Trade-off Problem," European Journal of Operational Research, Elsevier, vol. 284(2), pages 743-761.
    20. Chen, Liang & Kettunen, Janne, 2017. "Is certainty in carbon policy better than uncertainty?," European Journal of Operational Research, Elsevier, vol. 258(1), pages 230-243.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:plo:pone00:0265087. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: plosone (email available below). General contact details of provider: https://journals.plos.org/plosone/ .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.