Delay Factors Management and Ranking for Reconstruction and Rehabilitation Projects Based on the Relative Importance Index (RII)

Author

Listed:
  • Basem Al Khatib

    (Department of Civil Engineering, Faculty of Engineering, University Malaya, Kuala Lumpur 50603, Malaysia)

  • Yap Soon Poh

    (Department of Civil Engineering, Faculty of Engineering, University Malaya, Kuala Lumpur 50603, Malaysia)

  • Ahmed El-Shafie

    (Department of Civil Engineering, Faculty of Engineering, University Malaya, Kuala Lumpur 50603, Malaysia)

Abstract

In recent decades, the construction industry has developed rapidly. Delay was and remains one of the most important challenges negatively affecting not only this industry but also the economy and sustainable development. This study aims to conduct a comprehensive analysis of the delay factors in reconstruction projects because of the vital importance of these types of projects. This is the first attempt to conduct such an analysis for reconstruction projects in particular, and it is a continuation of the previous case study, which was considered one of the most important reconstruction projects in the Middle East region. The previous study focused on determining the types of delay factors used in this project. It is necessary to carry out advance in-depth analysis to sort the delay factors based on their effect on the project plan. In order to achieve the study goal, 93 questionnaires were distributed by hand to experts working on the project: some of them working the day shift, and the others working the night shift. The questionnaire results were analyzed and delay factors were sorted in descending order according to the relative importance index (RII). The three main factors affecting the overall reconstruction project duration were site restrictions and conditions, electrical and mechanical rerouting works, and design buildability and adjustment.

Suggested Citation

  • Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2020. "Delay Factors Management and Ranking for Reconstruction and Rehabilitation Projects Based on the Relative Importance Index (RII)," Sustainability, MDPI, vol. 12(15), pages 1-21, July.
  • Handle: RePEc:gam:jsusta:v:12:y:2020:i:15:p:6171-:d:392537
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/2071-1050/12/15/6171/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/2071-1050/12/15/6171/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Mohammed Al-Khalil & Mohammed Al-Ghafly, 1999. "Important causes of delay in public utility projects in Saudi Arabia," Construction Management and Economics, Taylor & Francis Journals, vol. 17(5), pages 647-655.
    2. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2018. "Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project," Sustainability, MDPI, vol. 10(12), pages 1-18, December.
    3. Arshi Shakeel Faridi & Sameh Monir El-Sayegh, 2006. "Significant factors causing delay in the UAE construction industry," Construction Management and Economics, Taylor & Francis Journals, vol. 24(11), pages 1167-1176.
    4. Peter Kaming & Paul Olomolaiye & Gary Holt & Frank Harris, 1997. "Factors influencing construction time and cost overruns on high-rise projects in Indonesia," Construction Management and Economics, Taylor & Francis Journals, vol. 15(1), pages 83-94.
    5. Shamas-Ur-Rehman Toor & Stephen Ogunlana, 2008. "Problems causing delays in major construction projects in Thailand," Construction Management and Economics, Taylor & Francis Journals, vol. 26(4), pages 395-408.
    6. Adel Al-Kharashi & Martin Skitmore, 2009. "Causes of delays in Saudi Arabian public sector construction projects," Construction Management and Economics, Taylor & Francis Journals, vol. 27(1), pages 3-23.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Junlong Peng & Mengyao Wang & Chao Peng & Ke Hu, 2022. "Research on extremely short construction period of engineering project based on labor balance under resource tolerance," PLOS ONE, Public Library of Science, vol. 17(3), pages 1-18, March.
    2. Kyunghwan Kim, 2020. "Generalized Resource-Constrained Critical Path Method to Improve Sustainability in Construction Project Scheduling," Sustainability, MDPI, vol. 12(21), pages 1-19, October.
    3. Juliet Akola & James Chakwizira & Emaculate Ingwani & Peter Bikam, 2023. "Awareness Level of Spatial Planning Tools for Disaster Risk Reduction in Informal Settlements in Mopani District, South Africa," Sustainability, MDPI, vol. 15(6), pages 1-13, March.
    4. Moahd Alghuson, 2023. "Exploring the Transport Infrastructure Sustainability Performance: An Investigation of the Transportation Projects in Saudi Arabia," Sustainability, MDPI, vol. 15(19), pages 1-17, September.
    5. Mohammad Ajmal Nikjow & Li Liang & Xijing Qi & Samad M. E. Sepasgozar & Nicholas Chileshe, 2021. "Triggers of Delays in International Projects Using Engineering Procurement and Construction Delivery Methods in the Belt and Road Initiative: Case Study of a High-Speed Railway Projects," Sustainability, MDPI, vol. 13(17), pages 1-21, August.
    6. Alain Teddy Bimenyimana & Sepanta Naimi, 2025. "Evaluating the Sustainability Consequences of Omitting Structural Analysis in Reinforced Concrete Projects in Burundi," Sustainability, MDPI, vol. 17(18), pages 1-24, September.
    7. Junlong Peng & Chao Peng & Mengyao Wang & Ke Hu & Dubin Wu, 2022. "Research on the factors of extremely short construction period under the sufficient resources based on Grey-DEMATEL-ISM," PLOS ONE, Public Library of Science, vol. 17(3), pages 1-21, March.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2018. "Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project," Sustainability, MDPI, vol. 10(12), pages 1-18, December.
    2. Goutom K. Pall & Adrian J. Bridge & Jason Gray & Martin Skitmore, 2019. "Causes of Delay in Power Transmission Projects: An Empirical Study," Energies, MDPI, vol. 13(1), pages 1-29, December.
    3. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2019. "Materials Challenges in Reconstruction of Historical Projects: A Case Study of the Old Riwaq Project," Sustainability, MDPI, vol. 11(17), pages 1-19, August.
    4. Hemanta Doloi & Anil Sawhney & K.C. Iyer, 2012. "Structural equation model for investigating factors affecting delay in Indian construction projects," Construction Management and Economics, Taylor & Francis Journals, vol. 30(10), pages 869-884, October.
    5. Lerche, J. & Lorentzen, S. & Enevoldsen, P. & Neve, H.H., 2022. "The impact of COVID -19 on offshore wind project productivity – A case study," Renewable and Sustainable Energy Reviews, Elsevier, vol. 158(C).
    6. Yazan Issa Abu Aisheh, 2021. "Lessons Learned, Barriers, and Improvement Factors for Mega Building Construction Projects in Developing Countries: Review Study," Sustainability, MDPI, vol. 13(19), pages 1-17, September.
    7. Giuliano Marella & Valentina Antoniucci, 2019. "Time Overrun in Public Works—Evidence from North-East Italy," Sustainability, MDPI, vol. 11(24), pages 1-17, December.
    8. Herve Kabanda & Alex Romard & Fuze Yurtsever & Anjali Wadhera & Joshua Andrews & Craig Merrett, 2021. "Construction Time Estimation Function for Canadian Utility Scale Power Plants," Energies, MDPI, vol. 14(17), pages 1-16, August.
    9. Minh Van Nguyen & Tu Thanh Nguyen & Chien Thanh Phan & Khanh Duy Ha, 2024. "Sustainable redevelopment of urban areas: Assessment of key barriers for the reconstruction of old residential buildings," Sustainable Development, John Wiley & Sons, Ltd., vol. 32(3), pages 2282-2297, June.
    10. R. Jayaraman, 2021. "An Empirical Study of Delays in Large Engineering Projects: An Indian Experience," Jindal Journal of Business Research, , vol. 10(1), pages 49-76, June.
    11. Achintya Ghatak & Adarsh Garg, 2022. "Power transmission project: a framework to align project success with organization goal," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 13(4), pages 1817-1833, August.
    12. Safi Ullah & Muhammad Siddiq & Deng Xiaopeng & Sun Jun & Diana R. Anbar & Chiemela Victor Amaechi & Muhammad Waqas Ashraf, 2025. "Identifying the Most Effective Delaying Factors Using FCEM-AHP: A Case Study of Pakistan’s Construction Industry," Journal of the Knowledge Economy, Springer;Portland International Center for Management of Engineering and Technology (PICMET), vol. 16(3), pages 13589-13623, September.
    13. Ajayi Babatunde Oluwaseun & Chinda Thanwadee, 2022. "Dynamics of Pertinent Project Delay Variables in the Thai Construction Sector: Mathematical Analysis," Engineering Management in Production and Services, Sciendo, vol. 14(2), pages 26-45, June.
    14. Dr. Mwenda, Mary Nyawira & Dr. Otieno- Omutoko Lillian & Prof. Christopher Gakuu, 2021. "The Nexus between Project Monitoring and Evaluation and Quality of Residential Buildings in Nairobi County, Kenya," International Journal of Research and Innovation in Social Science, International Journal of Research and Innovation in Social Science (IJRISS), vol. 5(1), pages 354-362, January.
    15. Ihsan Issa Ahmad Hosani & Fikri T. Dweiri & Udechukwu Ojiako, 0. "A study of cost overruns in complex multi-stakeholder road projects in the United Arab Emirates," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 0, pages 1-10.
    16. Miranda Sarmento, J.J. & Renneboog, Luc, 2017. "Cost overruns in public sector investment projects," Other publications TiSEM 51799a3e-4c78-4dbd-b330-b, Tilburg University, School of Economics and Management.
    17. Nur Fatin Syazwani Abu Bakar* & Syuhaida Ismail & Rohayah Che Amat & Serdar Durdyev, 2018. "Sustainable Construction in Malaysian Mixed Development Projects: The Barriers and Critical Success Factors," The Journal of Social Sciences Research, Academic Research Publishing Group, pages 885-892:6.
    18. Myung-Hun Kim & Eul-Bum Lee, 2019. "A Forecast Model for the Level of Engineering Maturity Impact on Contractor’s Procurement and Construction Costs for Offshore EPC Megaprojects," Energies, MDPI, vol. 12(12), pages 1-18, June.
    19. Aftab Hameed Memon & Abdul Qadir Memon & Shabir Hussain Khahro & Yasir Javed, 2023. "Investigation of Project Delays: Towards a Sustainable Construction Industry," Sustainability, MDPI, vol. 15(2), pages 1-17, January.
    20. Alessandra Montenegro & Marina Dobrota & Marija Todorovic & Teodora Slavinski & Vladimir Obradovic, 2021. "Impact of Construction Project Managers’ Emotional Intelligence on Project Success," Sustainability, MDPI, vol. 13(19), pages 1-18, September.

    More about this item

    Keywords

    ;
    ;
    ;
    ;
    ;

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jsusta:v:12:y:2020:i:15:p:6171-:d:392537. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.