Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project

Author

Listed:
  • Basem Al Khatib

    (Department of Civil Engineering, Faculty of Engineering, University Malaya, 50603 Kuala Lumpur, Malaysia)

  • Yap Soon Poh

    (Department of Civil Engineering, Faculty of Engineering, University Malaya, 50603 Kuala Lumpur, Malaysia)

  • Ahmed El-Shafie

    (Department of Civil Engineering, Faculty of Engineering, University Malaya, 50603 Kuala Lumpur, Malaysia)

Abstract

Delays in construction projects are a common phenomenon throughout the industry. This problem has many negative impacts on the time, cost, and sustainability of the projects. Many studies were conducted to identify the main causes of this delay in new construction projects in different regions but very few studies have focused on finding an explanation for the causes of delay in major reconstruction projects that have great religious and cultural sustainability. This paper examines the factors that contributed to work delays in one of the most major reconstruction projects that took place recently in the Middle East, which is namely the Mataf Expansion Project in the city of Mecca, Saudi Arabia. Fourteen interviews were conducted with project managers, construction managers, and senior site engineers to identify the factors that they encountered and led to the delay in the reconstruction activities of this project. Some of the findings were consistent and similar to most other causes of delay that are associated with new construction projects. However, interestingly, this research has discovered the existence of other unavoidable factors that caused a delay and should be considered for any similar reconstruction projects. The results showed that these factors could be divided into two groups: the first one is related to the demolition phase (five factors) and the second group is related to construction works (nine factors). In addition, it has been observed that the building material during the reconstruction is considered one of the major delaying factors. Finally, these 14 delay factors should be carefully considered to assure the sustainability of the main object’s function during the reconstruction activities.

Suggested Citation

  • Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2018. "Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project," Sustainability, MDPI, vol. 10(12), pages 1-18, December.
  • Handle: RePEc:gam:jsusta:v:10:y:2018:i:12:p:4772-:d:190492
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/2071-1050/10/12/4772/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/2071-1050/10/12/4772/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Mohammed Al-Khalil & Mohammed Al-Ghafly, 1999. "Important causes of delay in public utility projects in Saudi Arabia," Construction Management and Economics, Taylor & Francis Journals, vol. 17(5), pages 647-655.
    2. Arshi Shakeel Faridi & Sameh Monir El-Sayegh, 2006. "Significant factors causing delay in the UAE construction industry," Construction Management and Economics, Taylor & Francis Journals, vol. 24(11), pages 1167-1176.
    3. Peter Kaming & Paul Olomolaiye & Gary Holt & Frank Harris, 1997. "Factors influencing construction time and cost overruns on high-rise projects in Indonesia," Construction Management and Economics, Taylor & Francis Journals, vol. 15(1), pages 83-94.
    4. Shamas-Ur-Rehman Toor & Stephen Ogunlana, 2008. "Problems causing delays in major construction projects in Thailand," Construction Management and Economics, Taylor & Francis Journals, vol. 26(4), pages 395-408.
    5. Adel Al-Kharashi & Martin Skitmore, 2009. "Causes of delays in Saudi Arabian public sector construction projects," Construction Management and Economics, Taylor & Francis Journals, vol. 27(1), pages 3-23.
    6. Menoka Bal & David Bryde & Damian Fearon & Edward Ochieng, 2013. "Stakeholder Engagement: Achieving Sustainability in the Construction Sector," Sustainability, MDPI, vol. 5(2), pages 1-16, February.
    7. Agnieszka Leśniak & Krzysztof Zima, 2018. "Cost Calculation of Construction Projects Including Sustainability Factors Using the Case Based Reasoning (CBR) Method," Sustainability, MDPI, vol. 10(5), pages 1-14, May.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2019. "Materials Challenges in Reconstruction of Historical Projects: A Case Study of the Old Riwaq Project," Sustainability, MDPI, vol. 11(17), pages 1-19, August.
    2. Edwin Thomas Banobi & Wooyong Jung, 2019. "Causes and Mitigation Strategies of Delay in Power Construction Projects: Gaps between Owners and Contractors in Successful and Unsuccessful Projects," Sustainability, MDPI, vol. 11(21), pages 1-16, October.
    3. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2020. "Delay Factors Management and Ranking for Reconstruction and Rehabilitation Projects Based on the Relative Importance Index (RII)," Sustainability, MDPI, vol. 12(15), pages 1-21, July.
    4. Junlong Peng & Chao Peng & Mengyao Wang & Ke Hu & Dubin Wu, 2022. "Research on the factors of extremely short construction period under the sufficient resources based on Grey-DEMATEL-ISM," PLOS ONE, Public Library of Science, vol. 17(3), pages 1-21, March.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2020. "Delay Factors Management and Ranking for Reconstruction and Rehabilitation Projects Based on the Relative Importance Index (RII)," Sustainability, MDPI, vol. 12(15), pages 1-21, July.
    2. Goutom K. Pall & Adrian J. Bridge & Jason Gray & Martin Skitmore, 2019. "Causes of Delay in Power Transmission Projects: An Empirical Study," Energies, MDPI, vol. 13(1), pages 1-29, December.
    3. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2019. "Materials Challenges in Reconstruction of Historical Projects: A Case Study of the Old Riwaq Project," Sustainability, MDPI, vol. 11(17), pages 1-19, August.
    4. Yazan Issa Abu Aisheh, 2021. "Lessons Learned, Barriers, and Improvement Factors for Mega Building Construction Projects in Developing Countries: Review Study," Sustainability, MDPI, vol. 13(19), pages 1-17, September.
    5. Giuliano Marella & Valentina Antoniucci, 2019. "Time Overrun in Public Works—Evidence from North-East Italy," Sustainability, MDPI, vol. 11(24), pages 1-17, December.
    6. Hemanta Doloi & Anil Sawhney & K.C. Iyer, 2012. "Structural equation model for investigating factors affecting delay in Indian construction projects," Construction Management and Economics, Taylor & Francis Journals, vol. 30(10), pages 869-884, October.
    7. Lerche, J. & Lorentzen, S. & Enevoldsen, P. & Neve, H.H., 2022. "The impact of COVID -19 on offshore wind project productivity – A case study," Renewable and Sustainable Energy Reviews, Elsevier, vol. 158(C).
    8. Zhengxun Jin & Jonghyeob Kim & Chang-taek Hyun & Sangwon Han, 2019. "Development of a Model for Predicting Probabilistic Life-Cycle Cost for the Early Stage of Public-Office Construction," Sustainability, MDPI, vol. 11(14), pages 1-18, July.
    9. Herve Kabanda & Alex Romard & Fuze Yurtsever & Anjali Wadhera & Joshua Andrews & Craig Merrett, 2021. "Construction Time Estimation Function for Canadian Utility Scale Power Plants," Energies, MDPI, vol. 14(17), pages 1-16, August.
    10. Jean Baptiste Habumuremyi & Thomas K Tarus, 2021. "Effect of Stakeholders’ Participation on Sustainability of Community Projects in Ruhango District, Rwanda," International Journal of Research and Innovation in Social Science, International Journal of Research and Innovation in Social Science (IJRISS), vol. 5(09), pages 429-433, September.
    11. Sang-Guk Yum & Kiyoung Son & Seunghyun Son & Ji-Myong Kim, 2020. "Identifying Risk Indicators for Natural Hazard-Related Power Outages as a Component of Risk Assessment: An Analysis Using Power Outage Data from Hurricane Irma," Sustainability, MDPI, vol. 12(18), pages 1-15, September.
    12. Edyta Plebankiewicz & Damian Wieczorek, 2020. "Prediction of Cost Overrun Risk in Construction Projects," Sustainability, MDPI, vol. 12(22), pages 1-15, November.
    13. Shabir Hussain Malik & Weizhong Fu & Samma Faiz Rasool & Gowhar Ahmad Wani & Shah Zaman & Najaf Ali Wani, 2023. "Investigating the Impact of Communication Factors and Stakeholders Engagement on Renewable Energy Projects in Pakistan," Sustainability, MDPI, vol. 15(14), pages 1-14, July.
    14. Andri Ottesen & Dieter Thom & Rupali Bhagat & Rola Mourdaa, 2023. "Learning from the Future of Kuwait: Scenarios as a Learning Tool to Build Consensus for Actions Needed to Realize Vision 2035," Sustainability, MDPI, vol. 15(9), pages 1-25, April.
    15. R. Jayaraman, 2021. "An Empirical Study of Delays in Large Engineering Projects: An Indian Experience," Jindal Journal of Business Research, , vol. 10(1), pages 49-76, June.
    16. Achintya Ghatak & Adarsh Garg, 2022. "Power transmission project: a framework to align project success with organization goal," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 13(4), pages 1817-1833, August.
    17. Ajayi Babatunde Oluwaseun & Chinda Thanwadee, 2022. "Dynamics of Pertinent Project Delay Variables in the Thai Construction Sector: Mathematical Analysis," Engineering Management in Production and Services, Sciendo, vol. 14(2), pages 26-45, June.
    18. Antonio Héctor Álvarez-Pozo & Miguel Ignacio Parma-García & Isabel Ortiz-Marcos & Luis Fernando Bautista & Evangelina Atanes-Sánchez, 2024. "Analysis of Causes of Delays and Cost Overruns as Well as Mitigation Measures to Improve Profitability and Sustainability in Turnkey Industrial Projects," Sustainability, MDPI, vol. 16(4), pages 1-16, February.
    19. Agata Klaus-Rosińska & Joanna Iwko, 2021. "Stakeholder Management—One of the Clues of Sustainable Project Management—As an Underestimated Factor of Project Success in Small Construction Companies," Sustainability, MDPI, vol. 13(17), pages 1-27, September.
    20. Zhengqi He & Dechun Huang & Changzheng Zhang & Junmin Fang, 2018. "Toward a Stakeholder Perspective on Social Stability Risk of Large Hydraulic Engineering Projects in China: A Social Network Analysis," Sustainability, MDPI, vol. 10(4), pages 1-15, April.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jsusta:v:10:y:2018:i:12:p:4772-:d:190492. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.