Re-Evaluating Megaproject Cost Overruns: Putting Changes Into Perspective

Author

Listed:
  • Alan Walsh

    (Maxwell Building, University of Salford,43 Crescent, M5 4WT, UK)

  • Peter Walker

    (Maxwell Building, University of Salford,43 Crescent, M5 4WT, UK)

Abstract

The vast sums of money involved in megaprojects, and the perceived lack of public benefit, create controversy. Flyvberg’ s iron law asserts that megaprojects are over budget, over time, under benefits, over and over again (Flyvberg, 2018). More recent research suggests that this focus on cost overruns is based on highly misleading data (Love & Ahiaga-Dagbui, 2017). This research seeks to examine live megaprojects and examine Flyvbjergs theories in practice, through an investigation of current megaprojects in the Middle East. The research provides three case studies for two recently completed and one on-going megaproject, to examine these claims further. The research questions whether the right comparisons are made between the initial offerings and final product, through consultation with professionals. Based on the findings, it is suggested that an increase of over 100% of the Contract price, may not constitute an over-budget megaproject. Professional Cost Consultants in the built environment can provide greater insight into the complexity that adds cost in the transitions from initial to final costs for megaprojects, although the validity of this insight may be reduced by a lack of distance from or overview of the megaproject. This paper investigates some of the familiar sources of megaproject cost overrun and considers the findings of Cost Consultants engaged in monitoring megaprojects in the state of Qatar. Time and Cost considerations are just two of the characteristics evident in megaprojects. This research suggests that reporting of time and cost overruns is frequently based on limited, misunderstood or misreported data, and that in order to provide higher fidelity, such ‘headline claims’ need to be careful considered in the context of the original project scope. This paper recognises that cost is just one element of a megaproject, and that megaprojects warrant more holistic considerations including acknowledgement of other significant characteristics such as their embodiment of large components of risk, political influences, organisational pressures and management complexities.

Suggested Citation

  • Alan Walsh & Peter Walker, 2021. "Re-Evaluating Megaproject Cost Overruns: Putting Changes Into Perspective," International Journal of Innovation and Economic Development, Inovatus Services Ltd., vol. 6(6), pages 19-29, February.
  • Handle: RePEc:mgs:ijoied:v:6:y:2021:i:6:p:19-29
    as

    Download full text from publisher

    File URL: https://researchleap.com/wp-content/uploads/2021/03/2-updated.pdf
    Download Restriction: no

    File URL: https://researchleap.com/re-evaluating-megaproject-cost-overruns-putting-changes-into-perspective/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Peter Barrett & Monty Sutrisna, 2009. "Methodological strategies to gain insights into informality and emergence in construction project case studies," Construction Management and Economics, Taylor & Francis Journals, vol. 27(10), pages 935-948.
    2. Flyvbjerg, Bent, 2016. "The Fallacy of Beneficial Ignorance: A Test of Hirschman’s Hiding Hand," World Development, Elsevier, vol. 84(C), pages 176-189.
    3. Love, Peter E.D. & Ahiaga-Dagbui, Dominic D., 2018. "Debunking fake news in a post-truth era: The plausible untruths of cost underestimation in transport infrastructure projects," Transportation Research Part A: Policy and Practice, Elsevier, vol. 113(C), pages 357-368.
    4. Room, Graham, 2018. "The Hiding Hand: A Rejoinder to Flyvbjerg on Hirschman," World Development, Elsevier, vol. 103(C), pages 366-368.
    5. Flyvbjerg,Bent & Bruzelius,Nils & Rothengatter,Werner, 2003. "Megaprojects and Risk," Cambridge Books, Cambridge University Press, number 9780521009461.
    6. Lepenies, Philipp H., 2018. "Statistical Tests as a Hindrance to Understanding," World Development, Elsevier, vol. 103(C), pages 360-365.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Love, Peter E.D. & Ika, Lavagnon A. & Ahiaga-Dagbui, Dominic D., 2019. "On de-bunking ‘fake news’ in a post truth era: Why does the Planning Fallacy explanation for cost overruns fall short?," Transportation Research Part A: Policy and Practice, Elsevier, vol. 126(C), pages 397-408.
    2. Flyvbjerg, Bent & Ansar, Atif & Budzier, Alexander & Buhl, Søren & Cantarelli, Chantal & Garbuio, Massimo & Glenting, Carsten & Holm, Mette Skamris & Lovallo, Dan & Molin, Eric & Rønnest, Arne & Stewa, 2019. "On de-bunking “Fake News” in the post-truth era: How to reduce statistical error in research," Transportation Research Part A: Policy and Practice, Elsevier, vol. 126(C), pages 409-411.
    3. Flyvbjerg, Bent & Ansar, Atif & Budzier, Alexander & Buhl, Søren & Cantarelli, Chantal & Garbuio, Massimo & Glenting, Carsten & Holm, Mette Skamris & Lovallo, Dan & Lunn, Daniel & Molin, Eric & Rønnes, 2018. "Five things you should know about cost overrun," Transportation Research Part A: Policy and Practice, Elsevier, vol. 118(C), pages 174-190.
    4. Andrius Montrimas & Jurgita Bruneckienė & Vaidas Gaidelys, 2021. "Beyond the Socio-Economic Impact of Transport Megaprojects," Sustainability, MDPI, vol. 13(15), pages 1-29, July.
    5. Love, Peter E.D. & Sing, Michael C.P. & Ika, Lavagnon A. & Newton, Sidney, 2019. "The cost performance of transportation projects: The fallacy of the Planning Fallacy account," Transportation Research Part A: Policy and Practice, Elsevier, vol. 122(C), pages 1-20.
    6. Moschouli, Eleni & Soecipto, Raden Murwantara & Vanelslander, Thierry, 2019. "Cost performance of transport infrastructure projects before and after the global financial crisis (GFC): Are differences observed in the conditions of project performance?," Research in Transportation Economics, Elsevier, vol. 75(C), pages 21-35.
    7. Bent Flyvbjerg, 2021. "Four Ways to Scale Up: Smart, Dumb, Forced, and Fumbled," Papers 2101.11104, arXiv.org.
    8. Schreiner, Lena & Madlener, Reinhard, 2022. "Investing in power grid infrastructure as a flexibility option: A DSGE assessment for Germany," Energy Economics, Elsevier, vol. 107(C).
    9. Ahsan Nawaz & Xing Su & Qaiser Mohi Ud Din & Muhammad Irslan Khalid & Muhammad Bilal & Syyed Adnan Raheel Shah, 2020. "Identification of the H&S (Health and Safety Factors) Involved in Infrastructure Projects in Developing Countries-A Sequential Mixed Method Approach of OLMT-Project," IJERPH, MDPI, vol. 17(2), pages 1-18, January.
    10. Cantarelli, C.C. & Flyvbjerg, B. & Buhl, S.L., 2012. "Geographical variation in project cost performance: the Netherlands versus worldwide," Journal of Transport Geography, Elsevier, vol. 24(C), pages 324-331.
    11. Alexander Budzier & Bent Flyvbjerg & Andi Garavaglia & Andreas Leed, 2019. "Quantitative Cost and Schedule Risk Analysis of Nuclear Waste Storage," Papers 1901.11123, arXiv.org.
    12. Zhao, Na, 2019. "Managing interactive collaborative mega project supply chains under infectious risks," International Journal of Production Economics, Elsevier, vol. 218(C), pages 275-286.
    13. Michael Regan, 2013. "Public project procurement and the case for public–private partnerships," Chapters, in: John Farrar & David G. Mayes (ed.), Globalisation, the Global Financial Crisis and the State, chapter 8, pages 172-196, Edward Elgar Publishing.
    14. Holz-Rau, Christian & Scheiner, Joachim, 2011. "Safety and travel time in cost-benefit analysis: A sensitivity analysis for North Rhine-Westphalia," Transport Policy, Elsevier, vol. 18(2), pages 336-346, March.
    15. Leheis, Stéphanie, 2012. "High-speed train planning in France: Lessons from the Mediterranean TGV-line," Transport Policy, Elsevier, vol. 21(C), pages 37-44.
    16. Morgenroth, Edgar & FitzGerald, John & FitzGerald, John, 2006. "Summary and Conclusions," Book Chapters, in: Morgenroth, Edgar (ed.),Ex-Ante Evaluation of the Investment Priorities for the National Development Plan 2007-2013, chapter 24, pages 317-333, Economic and Social Research Institute (ESRI).
      • Baker, Terence J. & FitzGerald, John & Honohan, Patrick & FitzGerald, John & Honohan, Patrick, 1996. "Summary and Conclusions," Book Chapters, in: Baker, Terence J. (ed.),Economic Implications for Ireland of EMU, chapter 12, pages 339-352, Economic and Social Research Institute (ESRI).
    17. Litsiou, Konstantia & Polychronakis, Yiannis & Karami, Azhdar & Nikolopoulos, Konstantinos, 2022. "Relative performance of judgmental methods for forecasting the success of megaprojects," International Journal of Forecasting, Elsevier, vol. 38(3), pages 1185-1196.
    18. Bent Flyvbjerg & Allison Stewart & Alexander Budzier, 2016. "The Oxford Olympics Study 2016: Cost and Cost Overrun at the Games," Papers 1607.04484, arXiv.org.
    19. Proost, S. & Van der Loo, S. & de Palma, Andre & Lindsey, Robin, 2005. "A cost-benefit analysis of tunnel investment and tolling alternatives in Antwerp," European Transport \ Trasporti Europei, ISTIEE, Institute for the Study of Transport within the European Economic Integration, issue 31, pages 83-100.
    20. Al-Noor Abdullah & Sanzidur Rahman, 2021. "Social Impacts of a Mega-Dam Project as Perceived by Local, Resettled and Displaced Communities: A Case Study of Merowe Dam, Sudan," Economies, MDPI, vol. 9(4), pages 1-32, September.

    More about this item

    Keywords

    Cost Overruns; Megaprojects; Megaproject characteristics;
    All these keywords.

    JEL classification:

    • M00 - Business Administration and Business Economics; Marketing; Accounting; Personnel Economics - - General - - - General

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:mgs:ijoied:v:6:y:2021:i:6:p:19-29. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Bojan Obrenovic (email available below). General contact details of provider: https://researchleap.com/ .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.