A Mathematical Modeling for Delivery Time in Dynamic PERT Networks

Author

Listed:
  • Mahtab Afsari
  • Hesam Javadi Vasigh

Abstract

In project management, the main purpose of proposed methods is project scheduling which helps to managementand planning. We can calculate a real average of project closure in dynamic PERT networks by identifying alower limit. According to randomness, each distribution parameter varies itself and also it is proposed thatactivity durations are exponential distributions which have casual, unstable and independent variables. We usedhypothetic kinetic programming, that project closure time would have a lower limit. Finally, delivery time wouldobtain optimal due date by minimizing the expected aggregate cost per project and also a linear function of itsdue-date.

Suggested Citation

  • Mahtab Afsari & Hesam Javadi Vasigh, 2016. "A Mathematical Modeling for Delivery Time in Dynamic PERT Networks," Modern Applied Science, Canadian Center of Science and Education, vol. 10(3), pages 214-214, March.
  • Handle: RePEc:ibn:masjnl:v:10:y:2016:i:3:p:214
    as

    Download full text from publisher

    File URL: https://ccsenet.org/journal/index.php/mas/article/download/57814/30924
    Download Restriction: no

    File URL: https://ccsenet.org/journal/index.php/mas/article/view/57814
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Abdelkader, Yousry H., 2004. "Evaluating project completion times when activity times are Weibull distributed," European Journal of Operational Research, Elsevier, vol. 157(3), pages 704-715, September.
    2. Gonçalves, J.F. & Mendes, J.J.M. & Resende, M.G.C., 2008. "A genetic algorithm for the resource constrained multi-project scheduling problem," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1171-1190, September.
    3. Arfst Ludwig & Rolf Möhring & Frederik Stork, 2001. "A Computational Study on Bounding the Makespan Distribution in Stochastic Project Networks," Annals of Operations Research, Springer, vol. 102(1), pages 49-64, February.
    4. A. Charnes & W. W. Cooper & G. L. Thompson, 1964. "Critical Path Analyses Via Chance Constrained and Stochastic Programming," Operations Research, INFORMS, vol. 12(3), pages 460-470, June.
    5. Fatemi Ghomi, S. M. T. & Rabbani, M., 2003. "A new structural mechanism for reducibility of stochastic PERT networks," European Journal of Operational Research, Elsevier, vol. 145(2), pages 394-402, March.
    6. Elmaghraby, Salah E., 2005. "On the fallacy of averages in project risk management," European Journal of Operational Research, Elsevier, vol. 165(2), pages 307-313, September.
    7. Yaghoubi, Saeed & Noori, Siamak & Azaron, Amir & Tavakkoli-Moghaddam, Reza, 2011. "Resource allocation in dynamic PERT networks with finite capacity," European Journal of Operational Research, Elsevier, vol. 215(3), pages 670-678, December.
    8. V. G. Kulkarni & V. G. Adlakha, 1986. "Markov and Markov-Regenerative pert Networks," Operations Research, INFORMS, vol. 34(5), pages 769-781, October.
    9. Schmidt, Craig W. & Grossmann, Ignacio E., 2000. "The exact overall time distribution of a project with uncertain task durations," European Journal of Operational Research, Elsevier, vol. 126(3), pages 614-636, November.
    10. Azaron, Amir & Fatemi Ghomi, S.M.T., 2008. "Lower bound for the mean project completion time in dynamic PERT networks," European Journal of Operational Research, Elsevier, vol. 186(1), pages 120-127, April.
    11. Lova, Antonio & Maroto, Concepcion & Tormos, Pilar, 2000. "A multicriteria heuristic method to improve resource allocation in multiproject scheduling," European Journal of Operational Research, Elsevier, vol. 127(2), pages 408-424, December.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Azaron, Amir & Fatemi Ghomi, S.M.T., 2008. "Lower bound for the mean project completion time in dynamic PERT networks," European Journal of Operational Research, Elsevier, vol. 186(1), pages 120-127, April.
    2. Azaron, Amir & Fynes, Brian & Modarres, Mohammad, 2011. "Due date assignment in repetitive projects," International Journal of Production Economics, Elsevier, vol. 129(1), pages 79-85, January.
    3. Yaghoubi, Saeed & Noori, Siamak & Azaron, Amir & Fynes, Brian, 2015. "Resource allocation in multi-class dynamic PERT networks with finite capacity," European Journal of Operational Research, Elsevier, vol. 247(3), pages 879-894.
    4. Azaron, Amir & Katagiri, Hideki & Sakawa, Masatoshi & Kato, Kosuke & Memariani, Azizollah, 2006. "A multi-objective resource allocation problem in PERT networks," European Journal of Operational Research, Elsevier, vol. 172(3), pages 838-854, August.
    5. Amir Azaron & Hideki Katagiri & Masatoshi Sakawa, 2007. "Time-cost trade-off via optimal control theory in Markov PERT networks," Annals of Operations Research, Springer, vol. 150(1), pages 47-64, March.
    6. Yaghoubi, Saeed & Noori, Siamak & Azaron, Amir & Tavakkoli-Moghaddam, Reza, 2011. "Resource allocation in dynamic PERT networks with finite capacity," European Journal of Operational Research, Elsevier, vol. 215(3), pages 670-678, December.
    7. Hahn, Eugene David, 2008. "Mixture densities for project management activity times: A robust approach to PERT," European Journal of Operational Research, Elsevier, vol. 188(2), pages 450-459, July.
    8. Davaadorjin Monhor, 2011. "A new probabilistic approach to the path criticality in stochastic PERT," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 19(4), pages 615-633, December.
    9. Bredael, Dries & Vanhoucke, Mario, 2023. "Multi-project scheduling: A benchmark analysis of metaheuristic algorithms on various optimisation criteria and due dates," European Journal of Operational Research, Elsevier, vol. 308(1), pages 54-75.
    10. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    11. Creemers, Stefan & De Reyck, Bert & Leus, Roel, 2015. "Project planning with alternative technologies in uncertain environments," European Journal of Operational Research, Elsevier, vol. 242(2), pages 465-476.
    12. Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
    13. Azaron, Amir & Katagiri, Hideki & Kato, Kosuke & Sakawa, Masatoshi, 2006. "Longest path analysis in networks of queues: Dynamic scheduling problems," European Journal of Operational Research, Elsevier, vol. 174(1), pages 132-149, October.
    14. Sobel, Matthew J. & Szmerekovsky, Joseph G. & Tilson, Vera, 2009. "Scheduling projects with stochastic activity duration to maximize expected net present value," European Journal of Operational Research, Elsevier, vol. 198(3), pages 697-705, November.
    15. Azaron, Amir & Katagiri, Hideki & Kato, Kosuke & Sakawa, Masatoshi, 2006. "Modelling complex assemblies as a queueing network for lead time control," European Journal of Operational Research, Elsevier, vol. 174(1), pages 150-168, October.
    16. Ben Issa, Samer & Patterson, Raymond A. & Tu, Yiliu, 2021. "Solving resource-constrained multi-project environment under different activity assumptions," International Journal of Production Economics, Elsevier, vol. 232(C).
    17. Gary Mitchell, 2010. "On Calculating Activity Slack in Stochastic Project Networks," American Journal of Economics and Business Administration, Science Publications, vol. 2(1), pages 78-85, March.
    18. Hartmann, Sönke & Briskorn, Dirk, 2008. "A survey of variants and extensions of the resource-constrained project scheduling problem," Working Paper Series 02/2008, Hamburg School of Business Administration (HSBA).
    19. Masoud Arjmand & Amir Abbas Najafi & Majid Ebrahimzadeh, 2020. "Evolutionary algorithms for multi-objective stochastic resource availability cost problem," OPSEARCH, Springer;Operational Research Society of India, vol. 57(3), pages 935-985, September.
    20. Luise-Sophie Hoffmann & Carolin Kellenbrink & Stefan Helber, 2020. "Simultaneous structuring and scheduling of multiple projects with flexible project structures," Journal of Business Economics, Springer, vol. 90(5), pages 679-711, June.

    More about this item

    JEL classification:

    • R00 - Urban, Rural, Regional, Real Estate, and Transportation Economics - - General - - - General
    • Z0 - Other Special Topics - - General

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:ibn:masjnl:v:10:y:2016:i:3:p:214. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Canadian Center of Science and Education (email available below). General contact details of provider: https://edirc.repec.org/data/cepflch.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.