Developing a Risk Management Process for Infrastructure Projects Using IDEF0

Author

Listed:
  • Hui-Ping Tserng

    (Department of Civil Engineering, National Taiwan University, No. 1, Sec. 4, Roosevelt Road, Taipei 10617, Taiwan)

  • I-Cheng Cho

    (Department of Civil Engineering, National Taiwan University, No. 1, Sec. 4, Roosevelt Road, Taipei 10617, Taiwan)

  • Chun-Hung Chen

    (Second District Project Office, Department of Rapid Transit Systems, Taipei City Government, No. 7, Lane 48, Sec. 2, Zhongshan N. Rd, Taipei 10537, Taiwan)

  • Yu-Fan Liu

    (CTCI Smart Engineering Corporation, No. 16, Lane 270, Sec. 3, Bei Shen Road, New Taipei City 11155, Taiwan)

Abstract

The Mass Rapid Transit (MRT) project is a massive, large-scale construction venture with a complex interface. In order to reduce the risk of disasters and industrial accidents in the project and to save costs, a simple and flexible risk management system is necessary for projects such as MRT. A set of risk management processes was identified through a literature review and data collection, and the Integration Definition for Function Modeling (IDEF0) process was used for logical analysis. The IDEF0 diagram clearly depicts the items to be delivered at each interface, and risk is reduced by facilitating the flow of data on various risk items. The results of this research will be applied to other practical projects, with special emphasis on the project planning and design stages. Future work will verify whether the implementation of the proposed risk management process does indeed effectively reduce risks in the completed project.

Suggested Citation

  • Hui-Ping Tserng & I-Cheng Cho & Chun-Hung Chen & Yu-Fan Liu, 2021. "Developing a Risk Management Process for Infrastructure Projects Using IDEF0," Sustainability, MDPI, vol. 13(12), pages 1-22, June.
  • Handle: RePEc:gam:jsusta:v:13:y:2021:i:12:p:6958-:d:578809
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/2071-1050/13/12/6958/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/2071-1050/13/12/6958/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Pei Dang & Zhanwen Niu & Shang Gao & Lei Hou & Guomin Zhang, 2020. "Critical Factors Influencing the Sustainable Construction Capability in Prefabrication of Chinese Construction Enterprises," Sustainability, MDPI, vol. 12(21), pages 1-21, October.
    2. Ahsan Nawaz & Ahsan Waqar & Syyed Adnan Raheel Shah & Muhammad Sajid & Muhammad Irslan Khalid, 2019. "An Innovative Framework for Risk Management in Construction Projects in Developing Countries: Evidence from Pakistan," Risks, MDPI, vol. 7(1), pages 1-10, February.
    3. Panagiotis K. Marhavilas & Michael G. Tegas & Georgios K. Koulinas & Dimitrios E. Koulouriotis, 2020. "A Joint Stochastic/Deterministic Process with Multi-Objective Decision Making Risk-Assessment Framework for Sustainable Constructions Engineering Projects—A Case Study," Sustainability, MDPI, vol. 12(10), pages 1-21, May.
    4. Myung-Hun Kim & Eul-Bum Lee & Han-Suk Choi, 2019. "A Forecast and Mitigation Model of Construction Performance by Assessing Detailed Engineering Maturity at Key Milestones for Offshore EPC Mega-Projects," Sustainability, MDPI, vol. 11(5), pages 1-21, February.
    5. Slagmulder, Regine & Devoldere, Bart, 2018. "Transforming under deep uncertainty: A strategic perspective on risk management," Business Horizons, Elsevier, vol. 61(5), pages 733-743.
    6. Agnieszka Leśniak & Filip Janowiec, 2019. "Risk Assessment of Additional Works in Railway Construction Investments Using the Bayes Network," Sustainability, MDPI, vol. 11(19), pages 1-15, September.
    7. Merkourios Papanikolaou & Yiannis Xenidis, 2020. "Risk-Informed Performance Assessment of Construction Projects," Sustainability, MDPI, vol. 12(13), pages 1-20, July.
    8. G.K. Koulinas & O.E. Demesouka & P.K. Marhavilas & A.P. Vavatsikos & D.E. Koulouriotis, 2019. "Risk Assessment Using Fuzzy TOPSIS and PRAT for Sustainable Engineering Projects," Sustainability, MDPI, vol. 11(3), pages 1-15, January.
    9. Yujing Yang & Wenzhe Tang & Wenxin Shen & Tengfei Wang, 2019. "Enhancing Risk Management by Partnering in International EPC Projects: Perspective from Evolutionary Game in Chinese Construction Companies," Sustainability, MDPI, vol. 11(19), pages 1-16, September.
    10. Murat Gunduz & Hesham Ahmed Elsherbeny, 2020. "Construction Contract Administration Performance Assessment Tool by Using a Fuzzy Structural Equation Model," Sustainability, MDPI, vol. 12(2), pages 1-21, January.
    11. Sulfiah Dwi Astarini & Christiono Utomo, 2020. "Performance-Based Building Design of High-Rise Residential Buildings in Indonesia," Sustainability, MDPI, vol. 12(17), pages 1-17, August.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Huihua Chen & Hujun Li & Yige Wang & Baoquan Cheng, 2020. "A Comprehensive Assessment Approach for Water-Soil Environmental Risk during Railway Construction in Ecological Fragile Region Based on AHP and MEA," Sustainability, MDPI, vol. 12(19), pages 1-17, September.
    2. Fotis Kitsios & Elpiniki Chatzidimitriou & Maria Kamariotou, 2023. "The ISO/IEC 27001 Information Security Management Standard: How to Extract Value from Data in the IT Sector," Sustainability, MDPI, vol. 15(7), pages 1-17, March.
    3. Carlos Araújo-Rey & Miguel A. Sebastián, 2021. "An Approach to the Analysis of Causes of Delays in Industrial Construction Projects through Planning and Statistical Computing," Sustainability, MDPI, vol. 13(7), pages 1-21, April.
    4. Ahsan Nawaz & Xing Su & Qaiser Mohi Ud Din & Muhammad Irslan Khalid & Muhammad Bilal & Syyed Adnan Raheel Shah, 2020. "Identification of the H&S (Health and Safety Factors) Involved in Infrastructure Projects in Developing Countries-A Sequential Mixed Method Approach of OLMT-Project," IJERPH, MDPI, vol. 17(2), pages 1-18, January.
    5. Suleyman Enes Hacibektasoglu & Bulent Mertoglu & Hakan Tozan, 2021. "Application of a Novel Hybrid f-SC Risk Analysis Method in the Paint Industry," Sustainability, MDPI, vol. 13(24), pages 1-23, December.
    6. Agnieszka Bekisz & Magdalena Kowacka & Michał Kruszyński & Dominika Dudziak-Gajowiak & Grzegorz Debita, 2022. "Risk Management Using Network Thinking Methodology on the Example of Rail Transport," Energies, MDPI, vol. 15(14), pages 1-19, July.
    7. Maria Iglesias-Mendoza & Akilu Yunusa-Kaltungo & Sara Hadleigh-Dunn & Ashraf Labib, 2021. "Learning How to Learn from Disasters through a Comparative Dichotomy Analysis: Grenfell Tower and Hurricane Katrina Case Studies," Sustainability, MDPI, vol. 13(4), pages 1-18, February.
    8. Ji, Chenyi & Su, Xing & Qin, Zhongfu & Nawaz, Ahsan, 2022. "Probability Analysis of Construction Risk based on Noisy-or Gate Bayesian Networks," Reliability Engineering and System Safety, Elsevier, vol. 217(C).
    9. Nicholas Thom & Andrew Dawson, 2019. "Sustainable Road Design: Promoting Recycling and Non-Conventional Materials," Sustainability, MDPI, vol. 11(21), pages 1-12, November.
    10. Mohammad Ajmal Nikjow & Li Liang & Xijing Qi & Samad Sepasgozar, 2021. "Engineering Procurement Construction in the Context of Belt and Road Infrastructure Projects in West Asia: A SWOT Analysis," JRFM, MDPI, vol. 14(3), pages 1-17, February.
    11. Yulia Vertakova & Inga Vselenskaya & Vladimir Plotnikov, 2021. "Mergers and Acquisitions Risk Modeling," JRFM, MDPI, vol. 14(9), pages 1-24, September.
    12. Truong Dang Hoang Nhat Nguyen & Hyosoo Moon & Yonghan Ahn, 2022. "Critical Review of Trends in Modular Integrated Construction Research with a Focus on Sustainability," Sustainability, MDPI, vol. 14(19), pages 1-23, September.
    13. Hsu-Shih Shih & I-Fei Chen & Nolberto Munier & Zena Alcide, 2023. "Investigating Risk-Constraint Nexus of Construction Projects in Caribbean Small Island Developing States," SAGE Open, , vol. 13(1), pages 21582440231, March.
    14. Sulfiah Dwi Astarini & Christiono Utomo & Ayu Fatimah Sari & M Arif Rohman & Nugroho Priyo Negoro, 2020. "The Influence of Performance-Based Building Design on the Strategy of Retail Property in Indonesia," Sustainability, MDPI, vol. 12(21), pages 1-15, October.
    15. Jarosław Górecki & Manuel Díaz-Madroñero, 2020. "Who Risks and Wins?—Simulated Cost Variance in Sustainable Construction Projects," Sustainability, MDPI, vol. 12(8), pages 1-31, April.
    16. Skiba, Marta & Mrówczyńska, Maria & Sztubecka, Małgorzata & Bazan-Krzywoszańska, Anna & Kazak, Jan K. & Leśniak, Agnieszka & Janowiec, Filip, 2021. "Probability estimation of the city’s energy efficiency improvement as a result of using the phase change materials in heating networks," Energy, Elsevier, vol. 228(C).
    17. Ole Jonny Klakegg & Julien Pollack & Lynn Crawford, 2020. "Preparing for Successful Collaborative Contracts," Sustainability, MDPI, vol. 13(1), pages 1-18, December.
    18. Jiabao Jing & Xiaomei Deng & Rashid Maqbool & Yahya Rashid & Saleha Ashfaq, 2020. "Default Behaviors of Contractors under Surety Bond in Construction Industry Based on Evolutionary Game Model," Sustainability, MDPI, vol. 12(21), pages 1-28, November.
    19. Chenxi Li & Jingyao Wu & Zenglei Xi & Weiqiang Zhang, 2021. "Farmers’ Satisfaction with Land Expropriation System Reform: A Case Study in China," Land, MDPI, vol. 10(12), pages 1-16, December.
    20. Forliano, Canio & Ferraris, Alberto & Bivona, Enzo & Couturier, Jerome, 2022. "Pouring new wine into old bottles: A dynamic perspective of the interplay among environmental dynamism, capabilities development, and performance," Journal of Business Research, Elsevier, vol. 142(C), pages 448-463.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jsusta:v:13:y:2021:i:12:p:6958-:d:578809. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.