Integration of routing into a resource-constrained project scheduling problem
Author
Abstract
Suggested Citation
DOI: 10.1007/s13675-018-0104-z
Download full text from publisher
As the access to this document is restricted, you may want to search for a different version of it.
References listed on IDEAS
- Kreter, Stefan & Rieck, Julia & Zimmermann, Jürgen, 2016. "Models and solution procedures for the resource-constrained project scheduling problem with general temporal constraints and calendars," European Journal of Operational Research, Elsevier, vol. 251(2), pages 387-403.
- A. Alan B. Pritsker & Lawrence J. Waiters & Philip M. Wolfe, 1969. "Multiproject Scheduling with Limited Resources: A Zero-One Programming Approach," Management Science, INFORMS, vol. 16(1), pages 93-108, September.
- Peter Brucker & Sigrid Knust & Duncan Roper & Yakov Zinder, 2000. "Scheduling UET task systems with concurrency on two parallel identical processors," Mathematical Methods of Operations Research, Springer;Gesellschaft für Operations Research (GOR);Nederlands Genootschap voor Besliskunde (NGB), vol. 52(3), pages 369-387, December.
- Kolisch, R. & Padman, R., 2001.
"An integrated survey of deterministic project scheduling,"
Omega, Elsevier, vol. 29(3), pages 249-272, June.
- Kolisch, Rainer & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 8114, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
- Krüger, Doreen & Scholl, Armin, 2009.
"A heuristic solution framework for the resource constrained (multi-)project scheduling problem with sequence-dependent transfer times,"
European Journal of Operational Research, Elsevier, vol. 197(2), pages 492-508, September.
- Doreen Krüger & Armin Scholl, 2007. "A heuristic solution framework for the resource constrained (multi-)project scheduling problem with sequence-dependent transfer times," Jena Research Papers in Business and Economics - Working and Discussion Papers (Expired!) 16/2007, Friedrich-Schiller-University Jena, School of Economics and Business Administration.
- Cordeau, Jean-François & Laporte, Gilbert, 2003. "A tabu search heuristic for the static multi-vehicle dial-a-ride problem," Transportation Research Part B: Methodological, Elsevier, vol. 37(6), pages 579-594, July.
- Peter J. M. van Laarhoven & Emile H. L. Aarts & Jan Karel Lenstra, 1992. "Job Shop Scheduling by Simulated Annealing," Operations Research, INFORMS, vol. 40(1), pages 113-125, February.
- Eugeniusz Nowicki & Czeslaw Smutnicki, 1996. "A Fast Taboo Search Algorithm for the Job Shop Problem," Management Science, INFORMS, vol. 42(6), pages 797-813, June.
- Beasley, JE, 1983. "Route first--Cluster second methods for vehicle routing," Omega, Elsevier, vol. 11(4), pages 403-408.
- Lacomme, Philippe & Larabi, Mohand & Tchernev, Nikolay, 2013. "Job-shop based framework for simultaneous scheduling of machines and automated guided vehicles," International Journal of Production Economics, Elsevier, vol. 143(1), pages 24-34.
- Caumond, A. & Lacomme, P. & Moukrim, A. & Tchernev, N., 2009. "An MILP for scheduling problems in an FMS with one vehicle," European Journal of Operational Research, Elsevier, vol. 199(3), pages 706-722, December.
- Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
- Brucker, Peter & Drexl, Andreas & Mohring, Rolf & Neumann, Klaus & Pesch, Erwin, 1999. "Resource-constrained project scheduling: Notation, classification, models, and methods," European Journal of Operational Research, Elsevier, vol. 112(1), pages 3-41, January.
- Jens Poppenborg & Sigrid Knust, 2016. "A flow-based tabu search algorithm for the RCPSP with transfer times," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 38(2), pages 305-334, March.
- Zhi-Long Chen, 2010. "Integrated Production and Outbound Distribution Scheduling: Review and Extensions," Operations Research, INFORMS, vol. 58(1), pages 130-148, February.
- Philippe Lacomme & Christian Prins & Wahiba Ramdane-Cherif, 2004. "Competitive Memetic Algorithms for Arc Routing Problems," Annals of Operations Research, Springer, vol. 131(1), pages 159-185, October.
Citations
Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
Cited by:
- Hartmann, Sönke & Briskorn, Dirk, 2022. "An updated survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 297(1), pages 1-14.
- Berterottière, Lucas & Dauzère-Pérès, Stéphane & Yugma, Claude, 2024. "Flexible job-shop scheduling with transportation resources," European Journal of Operational Research, Elsevier, vol. 312(3), pages 890-909.
- de Castro Pena, Guilherme & Santos, Andréa Cynthia & Prins, Christian, 2023. "Solving the integrated multi-period scheduling routing problem for cleaning debris in the aftermath of disasters," European Journal of Operational Research, Elsevier, vol. 306(1), pages 156-172.
Most related items
These are the items that most often cite the same works as this one and are cited by the same works as this one.- Hartmann, Sönke & Briskorn, Dirk, 2022. "An updated survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 297(1), pages 1-14.
- Gómez Sánchez, Mariam & Lalla-Ruiz, Eduardo & Fernández Gil, Alejandro & Castro, Carlos & Voß, Stefan, 2023. "Resource-constrained multi-project scheduling problem: A survey," European Journal of Operational Research, Elsevier, vol. 309(3), pages 958-976.
- Jens Poppenborg & Sigrid Knust, 2016. "A flow-based tabu search algorithm for the RCPSP with transfer times," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 38(2), pages 305-334, March.
- Kellenbrink, Carolin & Helber, Stefan, 2015.
"Scheduling resource-constrained projects with a flexible project structure,"
European Journal of Operational Research, Elsevier, vol. 246(2), pages 379-391.
- Kellenbrink, Carolin & Helber, Stefan, 2013. "Scheduling resource-constrained projects with a flexible project structure," Hannover Economic Papers (HEP) dp-511, Leibniz Universität Hannover, Wirtschaftswissenschaftliche Fakultät.
- André Schnabel & Carolin Kellenbrink & Stefan Helber, 2018.
"Profit-oriented scheduling of resource-constrained projects with flexible capacity constraints,"
Business Research, Springer;German Academic Association for Business Research, vol. 11(2), pages 329-356, September.
- Schnabel, André & Kellenbrink, Carolin & Helber, Stefan, 2017. "Profit-oriented scheduling of resource-constrained projects with flexible capacity constraints," Hannover Economic Papers (HEP) dp-593, Leibniz Universität Hannover, Wirtschaftswissenschaftliche Fakultät.
- Berterottière, Lucas & Dauzère-Pérès, Stéphane & Yugma, Claude, 2024. "Flexible job-shop scheduling with transportation resources," European Journal of Operational Research, Elsevier, vol. 312(3), pages 890-909.
- Park, Jongyoon & Han, Jinil & Lee, Kyungsik, 2022. "Integer Optimization Model and Algorithm for the Stem Cell Culturing Problem," Omega, Elsevier, vol. 108(C).
- Xiong, Jian & Leus, Roel & Yang, Zhenyu & Abbass, Hussein A., 2016. "Evolutionary multi-objective resource allocation and scheduling in the Chinese navigation satellite system project," European Journal of Operational Research, Elsevier, vol. 251(2), pages 662-675.
- Moukrim, Aziz & Quilliot, Alain & Toussaint, Hélène, 2015. "An effective branch-and-price algorithm for the Preemptive Resource Constrained Project Scheduling Problem based on minimal Interval Order Enumeration," European Journal of Operational Research, Elsevier, vol. 244(2), pages 360-368.
- F. Perez & T. Gomez, 2016. "Multiobjective project portfolio selection with fuzzy constraints," Annals of Operations Research, Springer, vol. 245(1), pages 7-29, October.
- Naber, Anulark & Kolisch, Rainer, 2014. "MIP models for resource-constrained project scheduling with flexible resource profiles," European Journal of Operational Research, Elsevier, vol. 239(2), pages 335-348.
- Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
- Krüger, Doreen & Scholl, Armin, 2009.
"A heuristic solution framework for the resource constrained (multi-)project scheduling problem with sequence-dependent transfer times,"
European Journal of Operational Research, Elsevier, vol. 197(2), pages 492-508, September.
- Doreen Krüger & Armin Scholl, 2007. "A heuristic solution framework for the resource constrained (multi-)project scheduling problem with sequence-dependent transfer times," Jena Research Papers in Business and Economics - Working and Discussion Papers (Expired!) 16/2007, Friedrich-Schiller-University Jena, School of Economics and Business Administration.
- He, Zhengwen & Liu, Renjing & Jia, Tao, 2012. "Metaheuristics for multi-mode capital-constrained project payment scheduling," European Journal of Operational Research, Elsevier, vol. 223(3), pages 605-613.
- Yang-Kuei Lin & Chin Soon Chong, 2017. "Fast GA-based project scheduling for computing resources allocation in a cloud manufacturing system," Journal of Intelligent Manufacturing, Springer, vol. 28(5), pages 1189-1201, June.
- Arash Amirteimoori & Reza Kia, 2023. "Concurrent scheduling of jobs and AGVs in a flexible job shop system: a parallel hybrid PSO-GA meta-heuristic," Flexible Services and Manufacturing Journal, Springer, vol. 35(3), pages 727-753, September.
- Gonzalo Muñoz & Daniel Espinoza & Marcos Goycoolea & Eduardo Moreno & Maurice Queyranne & Orlando Rivera Letelier, 2018. "A study of the Bienstock–Zuckerberg algorithm: applications in mining and resource constrained project scheduling," Computational Optimization and Applications, Springer, vol. 69(2), pages 501-534, March.
- Vanhoucke, Mario & Coelho, José, 2016. "An approach using SAT solvers for the RCPSP with logical constraints," European Journal of Operational Research, Elsevier, vol. 249(2), pages 577-591.
- Brachmann, Robert & Kolisch, Rainer, 2021. "The impact of flexibility on engineer-to-order production planning," International Journal of Production Economics, Elsevier, vol. 239(C).
- Xabier A. Martin & Rosa Herrero & Angel A. Juan & Javier Panadero, 2024. "An Agile Adaptive Biased-Randomized Discrete-Event Heuristic for the Resource-Constrained Project Scheduling Problem," Mathematics, MDPI, vol. 12(12), pages 1-21, June.
More about this item
Keywords
Routing; Scheduling; RCPSP;All these keywords.
Statistics
Access and download statisticsCorrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:spr:eurjco:v:7:y:2019:i:4:d:10.1007_s13675-018-0104-z. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Sonal Shukla or Springer Nature Abstracting and Indexing (email available below). General contact details of provider: http://www.springer.com .
Please note that corrections may take a couple of weeks to filter through the various RePEc services.