Application of the DEMATEL method for quantitative analysis of risk factors for railway investments in Poland

Author

Listed:
  • Jan Kowalski
  • Marzena Lendo-Siwicka
  • Zdzisław Skutnik
  • Dorota Mirosław-Świątek

Abstract

The paper presents the results of research on the influence of risk factors on the implementation of railway investments in Poland (build stage) and deals with a detailed diagnosis of relation between factors. The application of DEcision MAking Trial and Evaluation Laboratory (DEMATEL) method for the analyses allowed to develop a cause-and-effect model of key factors and analyse the importance of the factors. Eleven factors identified in eariel studies as the most important risk factors were examined. It was found that the factors: errors in the preparation of tender documents (10.38%), errors in project documentation (10.02%), improperly estimated time of completion of the investment by the Employer (9.82%), internal regulations of PKP Polskie Koleje Państwowe S.A. (Polish State Railways) not coordinated with the provisions of contracts (9.51%) have the highest degree of importance. Factors: too many external institutions involved in the investment process and internal regulations of PKP Polskie Koleje Państwowe S.A. (Polish State Railways) not coordinated with the provisions of contracts, have the greatest net impact on the other factors. The relations between the factors and factors importance are valuable knowledge for engineers, enabling the project to be implemented according to the planned schedule and investment cost.

Suggested Citation

  • Jan Kowalski & Marzena Lendo-Siwicka & Zdzisław Skutnik & Dorota Mirosław-Świątek, 2024. "Application of the DEMATEL method for quantitative analysis of risk factors for railway investments in Poland," PLOS ONE, Public Library of Science, vol. 19(5), pages 1-20, May.
  • Handle: RePEc:plo:pone00:0303606
    DOI: 10.1371/journal.pone.0303606
    as

    Download full text from publisher

    File URL: https://journals.plos.org/plosone/article?id=10.1371/journal.pone.0303606
    Download Restriction: no

    File URL: https://journals.plos.org/plosone/article/file?id=10.1371/journal.pone.0303606&type=printable
    Download Restriction: no

    File URL: https://libkey.io/10.1371/journal.pone.0303606?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Hua Dong & Kun Yang, 2021. "Application of the entropy-DEMATEL-VIKOR multicriteria decision-making method in public charging infrastructure," PLOS ONE, Public Library of Science, vol. 16(10), pages 1-25, October.
    2. Arshi Shakeel Faridi & Sameh Monir El-Sayegh, 2006. "Significant factors causing delay in the UAE construction industry," Construction Management and Economics, Taylor & Francis Journals, vol. 24(11), pages 1167-1176.
    3. Agnieszka Leśniak & Filip Janowiec, 2019. "Risk Assessment of Additional Works in Railway Construction Investments Using the Bayes Network," Sustainability, MDPI, vol. 11(19), pages 1-15, September.
    4. Bijan Khazai & Mirjam Merz & Carola Schulz & Dietmar Borst, 2013. "An integrated indicator framework for spatial assessment of industrial and social vulnerability to indirect disaster losses," Natural Hazards: Journal of the International Society for the Prevention and Mitigation of Natural Hazards, Springer;International Society for the Prevention and Mitigation of Natural Hazards, vol. 67(2), pages 145-167, June.
    5. Peng Wang & Qiang Wei & Guotang Zhao & Jingchun Wang & Yang Yin, 2022. "Safety Risk Identification Method for Railway Construction in Complex and Dangerous Areas," Sustainability, MDPI, vol. 14(21), pages 1-14, October.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2018. "Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project," Sustainability, MDPI, vol. 10(12), pages 1-18, December.
    2. Agnieszka Bekisz & Magdalena Kowacka & Michał Kruszyński & Dominika Dudziak-Gajowiak & Grzegorz Debita, 2022. "Risk Management Using Network Thinking Methodology on the Example of Rail Transport," Energies, MDPI, vol. 15(14), pages 1-19, July.
    3. Jieun Ryu & Eun Joo Yoon & Chan Park & Dong Kun Lee & Seong Woo Jeon, 2017. "A Flood Risk Assessment Model for Companies and Criteria for Governmental Decision-Making to Minimize Hazards," Sustainability, MDPI, vol. 9(11), pages 1-26, November.
    4. R. Jayaraman, 2021. "An Empirical Study of Delays in Large Engineering Projects: An Indian Experience," Jindal Journal of Business Research, , vol. 10(1), pages 49-76, June.
    5. Achintya Ghatak & Adarsh Garg, 2022. "Power transmission project: a framework to align project success with organization goal," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 13(4), pages 1817-1833, August.
    6. Huihua Chen & Hujun Li & Yige Wang & Baoquan Cheng, 2020. "A Comprehensive Assessment Approach for Water-Soil Environmental Risk during Railway Construction in Ecological Fragile Region Based on AHP and MEA," Sustainability, MDPI, vol. 12(19), pages 1-17, September.
    7. Dr. Mwenda, Mary Nyawira & Dr. Otieno- Omutoko Lillian & Prof. Christopher Gakuu, 2021. "The Nexus between Project Monitoring and Evaluation and Quality of Residential Buildings in Nairobi County, Kenya," International Journal of Research and Innovation in Social Science, International Journal of Research and Innovation in Social Science (IJRISS), vol. 5(1), pages 354-362, January.
    8. Ihsan Issa Ahmad Hosani & Fikri T. Dweiri & Udechukwu Ojiako, 0. "A study of cost overruns in complex multi-stakeholder road projects in the United Arab Emirates," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 0, pages 1-10.
    9. Chengsi Li & Shu Zhang & Weijie Ling & Liquan Zhao & Younghwan Pan, 2024. "Enhancing User Experience in Electric Vehicle Charging Applications (EVCA): A Comprehensive Analysis in the Chinese Context," Journal of the Knowledge Economy, Springer;Portland International Center for Management of Engineering and Technology (PICMET), vol. 15(4), pages 18495-18530, December.
    10. Hui-Ping Tserng & I-Cheng Cho & Chun-Hung Chen & Yu-Fan Liu, 2021. "Developing a Risk Management Process for Infrastructure Projects Using IDEF0," Sustainability, MDPI, vol. 13(12), pages 1-22, June.
    11. Goutom K. Pall & Adrian J. Bridge & Jason Gray & Martin Skitmore, 2019. "Causes of Delay in Power Transmission Projects: An Empirical Study," Energies, MDPI, vol. 13(1), pages 1-29, December.
    12. Ihsan Issa Ahmad Hosani & Fikri T. Dweiri & Udechukwu Ojiako, 2020. "A study of cost overruns in complex multi-stakeholder road projects in the United Arab Emirates," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 11(6), pages 1250-1259, December.
    13. Min-Yuan Cheng & Shu-Hua Yeh & Woei-Chyi Chang, 2020. "Multi-Criteria Decision Making of Contractor Selection in Mass Rapid Transit Station Development Using Bayesian Fuzzy Prospect Model," Sustainability, MDPI, vol. 12(11), pages 1-32, June.
    14. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2019. "Materials Challenges in Reconstruction of Historical Projects: A Case Study of the Old Riwaq Project," Sustainability, MDPI, vol. 11(17), pages 1-19, August.
    15. Edyta Plebankiewicz & Wiesław Meszek & Krzysztof Zima & Damian Wieczorek, 2019. "Probabilistic and Fuzzy Approaches for Estimating the Life Cycle Costs of Buildings under Conditions of Exposure to Risk," Sustainability, MDPI, vol. 12(1), pages 1-15, December.
    16. Faham Tahmasebinia & Vicheth Song, 2022. "Significant Factors Causing Delay in the Cambodian Construction Industry," Sustainability, MDPI, vol. 14(6), pages 1-24, March.
    17. Mirjam Merz & Michael Hiete & Tina Comes & Frank Schultmann, 2013. "A composite indicator model to assess natural disaster risks in industry on a spatial level," Journal of Risk Research, Taylor & Francis Journals, vol. 16(9), pages 1077-1099, October.
    18. Hemanta Doloi & Anil Sawhney & K.C. Iyer, 2012. "Structural equation model for investigating factors affecting delay in Indian construction projects," Construction Management and Economics, Taylor & Francis Journals, vol. 30(10), pages 869-884, October.
    19. Murat Gunduz & Hamza M. A. Lutfi, 2021. "Go/No-Go Decision Model for Owners Using Exhaustive CHAID and QUEST Decision Tree Algorithms," Sustainability, MDPI, vol. 13(2), pages 1-24, January.
    20. Saini Yang & Shuai He & Juan Du & Xiaohua Sun, 2015. "Screening of social vulnerability to natural hazards in China," Natural Hazards: Journal of the International Society for the Prevention and Mitigation of Natural Hazards, Springer;International Society for the Prevention and Mitigation of Natural Hazards, vol. 76(1), pages 1-18, March.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:plo:pone00:0303606. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: plosone (email available below). General contact details of provider: https://journals.plos.org/plosone/ .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.