Early Highway Construction Cost Estimation: Selection of Key Cost Drivers

Author

Listed:
  • Nevena Simić

    (Faculty of Civil Engineering, University of Belgrade, 11000 Belgrade, Serbia)

  • Nenad Ivanišević

    (Faculty of Civil Engineering, University of Belgrade, 11000 Belgrade, Serbia)

  • Đorđe Nedeljković

    (Faculty of Civil Engineering, University of Belgrade, 11000 Belgrade, Serbia)

  • Aleksandar Senić

    (Faculty of Civil Engineering, University of Belgrade, 11000 Belgrade, Serbia)

  • Zoran Stojadinović

    (Faculty of Civil Engineering, University of Belgrade, 11000 Belgrade, Serbia)

  • Marija Ivanović

    (Faculty of Civil Engineering, University of Belgrade, 11000 Belgrade, Serbia)

Abstract

Cost estimates in the early stages of project development are essential for making the right decisions, but they are a huge challenge and risk for owners and potential contractors due to limited information about the characteristics of a future highway project. Whereas previous studies were mainly focused on achieving the highest possible estimation accuracy, this paper aims to propose cost-estimation models that can provide satisfactory accuracy with the least possible effort and to compare the perspectives of owners and contractors as the key stakeholders on projects. To determine cost drivers (CDs) that have a high influence on highway-construction costs and require low effort for their establishment, a questionnaire survey was conducted. Based on the key stakeholders’ perceptions and collected data set, cost-estimation models were developed using multiple-regression analysis, artificial neural networks, and XGBoost. The results show that reasonable cost-estimation accuracy can be achieved with relatively low effort for three CDs for the owners’ perspective and five CDs for the contractors’ perspective. Additional inclusion of input CDs in models does not necessarily imply an increase in accuracy. Also, the questionnaire results show that owners are more concerned about environmental issues, whereas contractors are more concerned about the possible changes in resource prices (especially after recent high increases caused by COVID-19 and the Russia–Ukraine war). These findings can help owners and potential contractors in intelligent decision-making in the early stages of future highway-construction projects.

Suggested Citation

  • Nevena Simić & Nenad Ivanišević & Đorđe Nedeljković & Aleksandar Senić & Zoran Stojadinović & Marija Ivanović, 2023. "Early Highway Construction Cost Estimation: Selection of Key Cost Drivers," Sustainability, MDPI, vol. 15(6), pages 1-20, March.
  • Handle: RePEc:gam:jsusta:v:15:y:2023:i:6:p:5584-:d:1104249
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/2071-1050/15/6/5584/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/2071-1050/15/6/5584/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Odeck, James, 2004. "Cost overruns in road construction--what are their sizes and determinants?," Transport Policy, Elsevier, vol. 11(1), pages 43-53, January.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Chantal C. Cantarelli & Bert van Wee & Eric J. E. Molin & Bent Flyvbjerg, 2013. "Different Cost Performance: Different Determinants? The Case of Cost Overruns in Dutch Transportation Infrastructure Projects," Papers 1307.2179, arXiv.org, revised Jan 2015.
    2. Cantarelli, C.C. & Flyvbjerg, B. & Buhl, S.L., 2012. "Geographical variation in project cost performance: the Netherlands versus worldwide," Journal of Transport Geography, Elsevier, vol. 24(C), pages 324-331.
    3. Herve Kabanda & Alex Romard & Fuze Yurtsever & Anjali Wadhera & Joshua Andrews & Craig Merrett, 2021. "Construction Time Estimation Function for Canadian Utility Scale Power Plants," Energies, MDPI, vol. 14(17), pages 1-16, August.
    4. Holz-Rau, Christian & Scheiner, Joachim, 2011. "Safety and travel time in cost-benefit analysis: A sensitivity analysis for North Rhine-Westphalia," Transport Policy, Elsevier, vol. 18(2), pages 336-346, March.
    5. Love, Peter E.D. & Ika, Lavagnon A. & Ahiaga-Dagbui, Dominic D., 2019. "On de-bunking ‘fake news’ in a post truth era: Why does the Planning Fallacy explanation for cost overruns fall short?," Transportation Research Part A: Policy and Practice, Elsevier, vol. 126(C), pages 397-408.
    6. Hugo Priemus & Bert van Wee (ed.), 2013. "International Handbook on Mega-Projects," Books, Edward Elgar Publishing, number 14791.
    7. Dahl, Roy Endré & Lorentzen, Sindre & Oglend, Atle & Osmundsen, Petter, 2017. "Pro-cyclical petroleum investments and cost overruns in Norway," Energy Policy, Elsevier, vol. 100(C), pages 68-78.
    8. Adriana Gómez-Cabrera & Amalia Sanz-Benlloch & Laura Montalban-Domingo & Jose Luis Ponz-Tienda & Eugenio Pellicer, 2020. "Identification of Factors Affecting the Performance of Rural Road Projects in Colombia," Sustainability, MDPI, vol. 12(18), pages 1-18, September.
    9. Minhyuk Jung & Shira You & Seokho Chi & Ilhan Yu & Bon-Gang Hwang, 2018. "The Relationship between Unbilled Accounts Receivable and Financial Performance of Construction Contractors," Sustainability, MDPI, vol. 10(8), pages 1-14, July.
    10. Chantal C. Cantarelli & Bent Flyvbjerg, 2013. "Mega-projects’ cost performance and lock-in: problems and solutions," Chapters, in: Hugo Priemus & Bert van Wee (ed.), International Handbook on Mega-Projects, chapter 15, pages 333-355, Edward Elgar Publishing.
    11. Edyta Plebankiewicz & Damian Wieczorek, 2020. "Prediction of Cost Overrun Risk in Construction Projects," Sustainability, MDPI, vol. 12(22), pages 1-15, November.
    12. Petr Halámek & Radka Matuszková & Michal Radimský, 2021. "Modernisation of Regional Roads Evaluated Using Ex-Post CBA," Sustainability, MDPI, vol. 13(4), pages 1-20, February.
    13. Cantarelli, C.C. & Molin, E.J.E. & van Wee, B. & Flyvbjerg, B., 2012. "Characteristics of cost overruns for Dutch transport infrastructure projects and the importance of the decision to build and project phases," Transport Policy, Elsevier, vol. 22(C), pages 49-56.
    14. Verweij, Stefan & van Meerkerk, Ingmar & Korthagen, Iris A., 2015. "Reasons for contract changes in implementing Dutch transportation infrastructure projects: An empirical exploration," Transport Policy, Elsevier, vol. 37(C), pages 195-202.
    15. Love, Peter E.D. & Zhou, Jingyang & Edwards, David J. & Irani, Zahir & Sing, Chun-Pong, 2017. "Off the rails: The cost performance of infrastructure rail projects," Transportation Research Part A: Policy and Practice, Elsevier, vol. 99(C), pages 14-29.
    16. Chong, Uven & Hopkins, Omar, 2016. "An international experience on the evolution of road costs during the project life cycle," Transport Policy, Elsevier, vol. 48(C), pages 60-66.
    17. Agnieszka Huterska, 2017. "Public-Private Partnership in Building Sustainable Development of the Kuyavian-Pomeranian Voivodship," European Journal of Interdisciplinary Studies Articles, Revistia Research and Publishing, vol. 3, September.
    18. Petter Osmundsen & Kristin Helen Roll, 2016. "Rig Rates and Drilling Speed: Reinforcing Effects," CESifo Working Paper Series 5895, CESifo.
    19. Abeysekara, Baudhi & Perera, Piyaruwan & Chhipi Shrestha, Gyan Kumar & Gunaruwan, Lalithasiri & Kumarage, Amal & Sadiq, Rehan & Hewage, Kasun, 2021. "Improving the capital deployment efficiency: An infrastructure investment planning process in transportation project," Research in Transportation Economics, Elsevier, vol. 88(C).
    20. Steen Lichtenberg, 2016. "Successful Control of Major Project Budgets," Administrative Sciences, MDPI, vol. 6(3), pages 1-14, July.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jsusta:v:15:y:2023:i:6:p:5584-:d:1104249. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.