A Survey on Integration of Optimization and Project Management Tools for Sustainable Construction Scheduling

Author

Listed:
  • Borna Dasović

    (Faculty of Civil Engineering, Transportation Engineering and Architecture, University of Maribor, Smetanova ulica 17, 2000 Maribor, Slovenia)

  • Mario Galić

    (Faculty of Civil Engineering and Architecture Osijek, Josip Juraj Strossmayer University of Osijek, Ulica Vladimira Preloga 3, 31000 Osijek, Croatia)

  • Uroš Klanšek

    (Faculty of Civil Engineering, Transportation Engineering and Architecture, University of Maribor, Smetanova ulica 17, 2000 Maribor, Slovenia)

Abstract

Construction scheduling, in practice, commonly relies on the usage of commercial project management tools (PMT) without specific optimization features. To obtain optimal schedules, planners often need to develop separate optimization models with special tools, which, however, demand further processing and editing of optimization results by PMT into forms expected for project management. In this regard, separation of optimization and PMT also requires considerable additional work for complete and harmonized updating of schedules during construction execution. Mentioned drawbacks and lack of available time may take to deficient construction scheduling during the implementation phase resulting in poor or even insufficient realization of project goals. Therefore, this paper presents an achievements survey on the integration of optimization and PMT that allow sustainable construction scheduling, particularly in terms of continuous optimal time and resource allocation throughout the project life cycle. Such work has not yet been comprehensively done up to now and the present contribution intends to fill a literature gap in the aforesaid area. Following a brief introduction, the optimization platform for construction scheduling is given in the article. Focusing on construction scheduling, an in-depth achievements survey on the integration of heuristics methods, mathematical programming and special solving methods with conventional PMT as well as optimization-based building information modeling (BIM) tools is then performed and findings are reported. The paper ends with conclusions and recommendations for further research.

Suggested Citation

  • Borna Dasović & Mario Galić & Uroš Klanšek, 2020. "A Survey on Integration of Optimization and Project Management Tools for Sustainable Construction Scheduling," Sustainability, MDPI, vol. 12(8), pages 1-18, April.
  • Handle: RePEc:gam:jsusta:v:12:y:2020:i:8:p:3405-:d:348695
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/2071-1050/12/8/3405/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/2071-1050/12/8/3405/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. WoonSeong Jeong & Soowon Chang & JeongWook Son & June-Seong Yi, 2016. "BIM-Integrated Construction Operation Simulation for Just-In-Time Production Management," Sustainability, MDPI, vol. 8(11), pages 1-25, October.
    2. Lihua He & Lianying Zhang, 2013. "Dynamic priority rule-based forward-backward heuristic algorithm for resource levelling problem in construction project," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 64(8), pages 1106-1117, August.
    3. Aidin Delgoshaei & Timon Rabczuk & Ahad Ali & Mohd Khairol Anuar Ariffin, 2017. "An applicable method for modifying over-allocated multi-mode resource constraint schedules in the presence of preemptive resources," Annals of Operations Research, Springer, vol. 259(1), pages 85-117, December.
    4. Nashwan Dawood & Eknarin Sriprasert, 2006. "Construction scheduling using multi-constraint and genetic algorithms approach," Construction Management and Economics, Taylor & Francis Journals, vol. 24(1), pages 19-30.
    5. Servranckx, Tom & Vanhoucke, Mario, 2019. "A tabu search procedure for the resource-constrained project scheduling problem with alternative subgraphs," European Journal of Operational Research, Elsevier, vol. 273(3), pages 841-860.
    6. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    7. Konstantinos Anagnostopoulos & Georgios Koulinas, 2010. "A simulated annealing hyperheuristic for construction resource levelling," Construction Management and Economics, Taylor & Francis Journals, vol. 28(2), pages 163-175.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Orlando Lima & Gabriela Fernandes & Anabela Tereso, 2023. "Benefits of Adopting Innovation and Sustainability Practices in Project Management within the SME Context," Sustainability, MDPI, vol. 15(18), pages 1-20, September.
    2. Borna Dasović & Uroš Klanšek, 2021. "Integration of Mixed-Integer Nonlinear Program and Project Management Tool to Support Sustainable Cost-Optimal Construction Scheduling," Sustainability, MDPI, vol. 13(21), pages 1-20, November.
    3. YeEun Jang & JeongWook Son & June-Seong Yi, 2021. "Classifying the Level of Bid Price Volatility Based on Machine Learning with Parameters from Bid Documents as Risk Factors," Sustainability, MDPI, vol. 13(7), pages 1-18, April.
    4. Borna Dasović & Uroš Klanšek, 2022. "A Review of Energy-Efficient and Sustainable Construction Scheduling Supported with Optimization Tools," Energies, MDPI, vol. 15(7), pages 1-17, March.
    5. Mateusz Trzeciak & Izabela Jonek-Kowalska, 2021. "Monitoring and Control in Program Management as Effectiveness Drivers in Polish Energy Sector. Diagnosis and Directions of Improvement," Energies, MDPI, vol. 14(15), pages 1-25, July.
    6. Kyunghwan Kim, 2020. "Generalized Resource-Constrained Critical Path Method to Improve Sustainability in Construction Project Scheduling," Sustainability, MDPI, vol. 12(21), pages 1-19, October.
    7. Michał Tomczak & Piotr Jaśkowski, 2021. "Preferences of Construction Managers Regarding the Quality and Optimization Criteria of Project Schedules," Sustainability, MDPI, vol. 13(2), pages 1-22, January.
    8. Wei He & Wenjing Li & Wei Wang, 2021. "Developing a Resource Allocation Approach for Resource-Constrained Construction Operation under Multi-Objective Operation," Sustainability, MDPI, vol. 13(13), pages 1-22, June.
    9. Čeněk Jarský & Miloslava Popenková & Jozef Gašparík & Patrik Šťastný, 2022. "On Use of Construction Technology Designs for Expert Opinions," Sustainability, MDPI, vol. 14(9), pages 1-12, May.
    10. Chia-Nan Wang & Nhat-Luong Nhieu & Trang Thi Thu Tran, 2021. "Stochastic Chebyshev Goal Programming Mixed Integer Linear Model for Sustainable Global Production Planning," Mathematics, MDPI, vol. 9(5), pages 1-22, February.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Hongbo Li & Linwen Zheng & Hanyu Zhu, 2023. "Resource leveling in projects with flexible structures," Annals of Operations Research, Springer, vol. 321(1), pages 311-342, February.
    2. Pejman Peykani & Jafar Gheidar-Kheljani & Sheida Shahabadi & Seyyed Hassan Ghodsypour & Mojtaba Nouri, 2023. "A two-phase resource-constrained project scheduling approach for design and development of complex product systems," Operational Research, Springer, vol. 23(1), pages 1-25, March.
    3. Hartmann, Sönke & Briskorn, Dirk, 2022. "An updated survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 297(1), pages 1-14.
    4. Borna Dasović & Uroš Klanšek, 2021. "Integration of Mixed-Integer Nonlinear Program and Project Management Tool to Support Sustainable Cost-Optimal Construction Scheduling," Sustainability, MDPI, vol. 13(21), pages 1-20, November.
    5. Estévez-Fernández, Arantza, 2012. "A game theoretical approach to sharing penalties and rewards in projects," European Journal of Operational Research, Elsevier, vol. 216(3), pages 647-657.
    6. Xiong, Jian & Leus, Roel & Yang, Zhenyu & Abbass, Hussein A., 2016. "Evolutionary multi-objective resource allocation and scheduling in the Chinese navigation satellite system project," European Journal of Operational Research, Elsevier, vol. 251(2), pages 662-675.
    7. Servranckx, Tom & Vanhoucke, Mario, 2019. "Strategies for project scheduling with alternative subgraphs under uncertainty: similar and dissimilar sets of schedules," European Journal of Operational Research, Elsevier, vol. 279(1), pages 38-53.
    8. Vega-Velázquez, Miguel Ángel & García-Nájera, Abel & Cervantes, Humberto, 2018. "A survey on the Software Project Scheduling Problem," International Journal of Production Economics, Elsevier, vol. 202(C), pages 145-161.
    9. Zezhou Wu & Changhong Chen & Yuzhu Cai & Chen Lu & Hao Wang & Tao Yu, 2019. "BIM-Based Visualization Research in the Construction Industry: A Network Analysis," IJERPH, MDPI, vol. 16(18), pages 1-13, September.
    10. Paraskevopoulos, Dimitris C. & Laporte, Gilbert & Repoussis, Panagiotis P. & Tarantilis, Christos D., 2017. "Resource constrained routing and scheduling: Review and research prospects," European Journal of Operational Research, Elsevier, vol. 263(3), pages 737-754.
    11. Ferreira, Cristiane & Figueira, Gonçalo & Amorim, Pedro, 2021. "Scheduling Human-Robot Teams in collaborative working cells," International Journal of Production Economics, Elsevier, vol. 235(C).
    12. Jeunet, Jully & Bou Orm, Mayassa, 2020. "Optimizing temporary work and overtime in the Time Cost Quality Trade-off Problem," European Journal of Operational Research, Elsevier, vol. 284(2), pages 743-761.
    13. Murat Gunduz & Ayman Fahmi Naser, 2017. "Cost Based Value Stream Mapping as a Sustainable Construction Tool for Underground Pipeline Construction Projects," Sustainability, MDPI, vol. 9(12), pages 1-20, November.
    14. Borna Dasović & Uroš Klanšek, 2022. "A Review of Energy-Efficient and Sustainable Construction Scheduling Supported with Optimization Tools," Energies, MDPI, vol. 15(7), pages 1-17, March.
    15. Korytkowski, Przemyslaw & Malachowski, Bartlomiej, 2019. "Competence-based estimation of activity duration in IT projects," European Journal of Operational Research, Elsevier, vol. 275(2), pages 708-720.
    16. Yang-Kuei Lin & Chin Soon Chong, 2017. "Fast GA-based project scheduling for computing resources allocation in a cloud manufacturing system," Journal of Intelligent Manufacturing, Springer, vol. 28(5), pages 1189-1201, June.
    17. Billaut, Jean-Charles & Della Croce, Federico & Grosso, Andrea, 2015. "A single machine scheduling problem with two-dimensional vector packing constraints," European Journal of Operational Research, Elsevier, vol. 243(1), pages 75-81.
    18. Benita, Francisco & López-Ramos, Francisco & Nasini, Stefano, 2019. "A bi-level programming approach for global investment strategies with financial intermediation," European Journal of Operational Research, Elsevier, vol. 274(1), pages 375-390.
    19. Boda Liu & Bin Yang & Jianzhuang Xiao & Dayu Zhu & Binghan Zhang & Zhichen Wang & Miaosi Dong, 2021. "Review of Optimization Dynamically Applied in the Construction and the Application Potential of ICT," Sustainability, MDPI, vol. 13(10), pages 1-18, May.
    20. Gonzalo Muñoz & Daniel Espinoza & Marcos Goycoolea & Eduardo Moreno & Maurice Queyranne & Orlando Rivera Letelier, 2018. "A study of the Bienstock–Zuckerberg algorithm: applications in mining and resource constrained project scheduling," Computational Optimization and Applications, Springer, vol. 69(2), pages 501-534, March.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jsusta:v:12:y:2020:i:8:p:3405-:d:348695. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.