On path correlation and PERT bias

Author

Listed:
  • Banerjee, Arunava
  • Paul, Anand

Abstract

Most studies of project time estimation assume that (a) activity times are mutually independent random variables; many also assume that (b) path completion times are mutually independent. In this paper, we subject the impact of both these assumptions to close scrutiny. Using tools from multivariate analysis, we make a theoretical study of the direction of the error in the classical PERT method of estimating mean project completion time when correlation is ignored. We also investigate the effect of activity dependence on the normality of path length via simulation.

Suggested Citation

  • Banerjee, Arunava & Paul, Anand, 2008. "On path correlation and PERT bias," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1208-1216, September.
  • Handle: RePEc:eee:ejores:v:189:y:2008:i:3:p:1208-1216
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0377-2217(07)00594-2
    Download Restriction: Full text for ScienceDirect subscribers only
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Bajis Dodin, 1985. "Bounding the Project Completion Time Distribution in PERT Networks," Operations Research, INFORMS, vol. 33(4), pages 862-881, August.
    2. Kenneth R. MacCrimmon & Charles A. Ryavec, 1964. "An Analytical Study of the PERT Assumptions," Operations Research, INFORMS, vol. 12(1), pages 16-37, February.
    3. Larry J. Ringer, 1971. "A Statistical Theory for Pert in Which Completion Times of Activities are Inter-Dependent," Management Science, INFORMS, vol. 17(11), pages 717-723, July.
    4. Genaro Gutierrez & Anand Paul, 2000. "Analysis of the Effects of Uncertainty, Risk-Pooling, and Subcontracting Mechanisms on Project Performance," Operations Research, INFORMS, vol. 48(6), pages 927-938, December.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Zhichao Zheng & Karthik Natarajan & Chung-Piaw Teo, 2016. "Least Squares Approximation to the Distribution of Project Completion Times with Gaussian Uncertainty," Operations Research, INFORMS, vol. 64(6), pages 1406-1421, December.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Tetsuo Iida, 2000. "Computing bounds on project duration distributions for stochastic PERT networks," Naval Research Logistics (NRL), John Wiley & Sons, vol. 47(7), pages 559-580, October.
    2. Xuan Vinh Doan & Karthik Natarajan, 2012. "On the Complexity of Nonoverlapping Multivariate Marginal Bounds for Probabilistic Combinatorial Optimization Problems," Operations Research, INFORMS, vol. 60(1), pages 138-149, February.
    3. Kamburowski, J., 1997. "New validations of PERT times," Omega, Elsevier, vol. 25(3), pages 323-328, June.
    4. Pérez, José García & Martín, María del Mar López & García, Catalina García & Sánchez Granero, Miguel Ángel, 2016. "Project management under uncertainty beyond beta: The generalized bicubic distribution," Operations Research Perspectives, Elsevier, vol. 3(C), pages 67-76.
    5. Badinelli, Ralph D., 1996. "Approximating probability density functions and their convolutions using orthogonal polynomials," European Journal of Operational Research, Elsevier, vol. 95(1), pages 211-230, November.
    6. Samaddar, Subhashish, 2001. "The effect of setup time reduction on its variance," Omega, Elsevier, vol. 29(3), pages 243-247, June.
    7. Junguang Zhang & Dan Wan, 2021. "Determination of early warning time window for bottleneck resource buffer," Annals of Operations Research, Springer, vol. 300(1), pages 289-305, May.
    8. Martens, Annelies & Vanhoucke, Mario, 2019. "The impact of applying effort to reduce activity variability on the project time and cost performance," European Journal of Operational Research, Elsevier, vol. 277(2), pages 442-453.
    9. Williams, Terry, 1999. "Towards realism in network simulation," Omega, Elsevier, vol. 27(3), pages 305-314, June.
    10. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2022. "Using Earned Value Management and Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 297(2), pages 451-466.
    11. Huang, Ding-Hsiang & Huang, Cheng-Fu & Lin, Yi-Kuei, 2020. "Exact project reliability for a multi-state project network subject to time and budget constraints," Reliability Engineering and System Safety, Elsevier, vol. 195(C).
    12. Williams, Terry, 1995. "A classified bibliography of recent research relating to project risk management," European Journal of Operational Research, Elsevier, vol. 85(1), pages 18-38, August.
    13. Jiao Wang & Kai Yang & Ruiqing Zhao, 2017. "The impact of decision criteria on deadline-based incentive contracts in project management," Journal of Intelligent Manufacturing, Springer, vol. 28(3), pages 643-655, March.
    14. Luz Stella Cardona-Meza & Gerard Olivar-Tost, 2017. "Modeling and Simulation of Project Management through the PMBOK® Standard Using Complex Networks," Complexity, Hindawi, vol. 2017, pages 1-12, December.
    15. Schmidt, Craig W. & Grossmann, Ignacio E., 2000. "The exact overall time distribution of a project with uncertain task durations," European Journal of Operational Research, Elsevier, vol. 126(3), pages 614-636, November.
    16. Li, Xiaobo & Natarajan, Karthik & Teo, Chung-Piaw & Zheng, Zhichao, 2014. "Distributionally robust mixed integer linear programs: Persistency models with applications," European Journal of Operational Research, Elsevier, vol. 233(3), pages 459-473.
    17. Brucker, Peter & Drexl, Andreas & Mohring, Rolf & Neumann, Klaus & Pesch, Erwin, 1999. "Resource-constrained project scheduling: Notation, classification, models, and methods," European Journal of Operational Research, Elsevier, vol. 112(1), pages 3-41, January.
    18. García Pérez, J., 1998. "El método de subasta como complemento al PERT clásico," Estudios de Economia Aplicada, Estudios de Economia Aplicada, vol. 10, pages 71-88, Diciembre.
    19. Hajdu M. & Isaac S., 2016. "Sixty years of project planning: history and future," Organization, Technology and Management in Construction, Sciendo, vol. 8(1), pages 1499-1510, December.
    20. Van de Vonder, Stijn & Demeulemeester, Erik & Herroelen, Willy & Leus, Roel, 2005. "The use of buffers in project management: The trade-off between stability and makespan," International Journal of Production Economics, Elsevier, vol. 97(2), pages 227-240, August.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:ejores:v:189:y:2008:i:3:p:1208-1216. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/eor .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.