Project scheduling under resource and mode identity constraints: Model, complexity, methods, and application
Author
Abstract
Suggested Citation
Download full text from publisher
As the access to this document is restricted, you may want to search for a different version of it.
References listed on IDEAS
- Patterson, James H. & Brian Talbot, F. & Slowinski, Roman & Weglarz, Jan, 1990. "Computational experience with a backtracking algorithm for solving a general class of precedence and resource-constrained scheduling problems," European Journal of Operational Research, Elsevier, vol. 49(1), pages 68-79, November.
- de Werra, D., 1985. "An introduction to timetabling," European Journal of Operational Research, Elsevier, vol. 19(2), pages 151-162, February.
- A. Alan B. Pritsker & Lawrence J. Waiters & Philip M. Wolfe, 1969. "Multiproject Scheduling with Limited Resources: A Zero-One Programming Approach," Management Science, INFORMS, vol. 16(1), pages 93-108, September.
- Schirmer, Andreas, 1996. "New insights on the complexity of resource-constrained project scheduling: A case of single-mode scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 390, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Schirmer, Andreas, 1995. "A guide to complexity theory in operations research," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 381, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- F. Brian Talbot, 1982. "Resource-Constrained Project Scheduling with Time-Resource Tradeoffs: The Nonpreemptive Case," Management Science, INFORMS, vol. 28(10), pages 1197-1210, October.
- Edward W. Davis & James H. Patterson, 1975. "A Comparison of Heuristic and Optimum Solutions in Resource-Constrained Project Scheduling," Management Science, INFORMS, vol. 21(8), pages 944-955, April.
- Erik Demeulemeester & Willy Herroelen, 1992. "A Branch-and-Bound Procedure for the Multiple Resource-Constrained Project Scheduling Problem," Management Science, INFORMS, vol. 38(12), pages 1803-1818, December.
- Dale F. Cooper, 1976. "Heuristics for Scheduling Resource-Constrained Projects: An Experimental Investigation," Management Science, INFORMS, vol. 22(11), pages 1186-1194, July.
- Drexl, Andreas & Juretzka, Jan & Salewski, Frank, 1993. "Academic course scheduling under workload and changeover constraints," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 337, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- D. Abramson, 1991. "Constructing School Timetables Using Simulated Annealing: Sequential and Parallel Algorithms," Management Science, INFORMS, vol. 37(1), pages 98-113, January.
- Salewski, Frank & Schirmer, Andreas & Drexl, Andreas, 1996. "Project Scheduling under Resource and Mode Identity Constraints. Part II: An Application to Audit-Staff Scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 388, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Rainer Kolisch & Arno Sprecher & Andreas Drexl, 1995. "Characterization and Generation of a General Class of Resource-Constrained Project Scheduling Problems," Management Science, INFORMS, vol. 41(10), pages 1693-1703, October.
- Boctor, Fayer F., 1990. "Some efficient multi-heuristic procedures for resource-constrained project scheduling," European Journal of Operational Research, Elsevier, vol. 49(1), pages 3-13, November.
- Salewski, Frank & Schirmer, Andreas & Drexl, Andreas, 1996. "Project Scheduling under Resource and Mode Identity Constraints. Part I: Model, Complexity Status, and Methods," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 387, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- I. Kurtulus & E. W. Davis, 1982. "Multi-Project Scheduling: Categorization of Heuristic Rules Performance," Management Science, INFORMS, vol. 28(2), pages 161-172, February.
- Dodin, Bajis & Huang Chan, K., 1991. "Application of production scheduling methods to external and internal audit scheduling," European Journal of Operational Research, Elsevier, vol. 52(3), pages 267-279, June.
- F. Brian Talbot & James H. Patterson, 1978. "An Efficient Integer Programming Algorithm with Network Cuts for Solving Resource-Constrained Scheduling Problems," Management Science, INFORMS, vol. 24(11), pages 1163-1174, July.
- Andreas Drexl, 1991. "Scheduling of Project Networks by Job Assignment," Management Science, INFORMS, vol. 37(12), pages 1590-1602, December.
- Schirmer, Andreas, 1996. "New insights on the complexity of resource-constrained project scheduling: Two cases of multi-mode scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 391, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- James H. Patterson, 1984. "A Comparison of Exact Approaches for Solving the Multiple Constrained Resource, Project Scheduling Problem," Management Science, INFORMS, vol. 30(7), pages 854-867, July.
Citations
Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
Cited by:
- Drexl, Andreas & Frahm, Johannes & Salewski, Frank, 1997. "Audit-staff scheduling by column generation," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 464, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Jorgensen, Trond & Wallace, Stein W., 2000. "Improving project cost estimation by taking into account managerial flexibility," European Journal of Operational Research, Elsevier, vol. 127(2), pages 239-251, December.
- Coelho, José & Vanhoucke, Mario, 2011.
"Multi-mode resource-constrained project scheduling using RCPSP and SAT solvers,"
European Journal of Operational Research, Elsevier, vol. 213(1), pages 73-82, August.
- J. Coelho & M. Vanhoucke, 2009. "Multi-mode resource constrained pro ject scheduling using RCPSP and SAT solvers," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 09/614, Ghent University, Faculty of Economics and Business Administration.
- Kellenbrink, Carolin & Helber, Stefan, 2015.
"Scheduling resource-constrained projects with a flexible project structure,"
European Journal of Operational Research, Elsevier, vol. 246(2), pages 379-391.
- Kellenbrink, Carolin & Helber, Stefan, 2013. "Scheduling resource-constrained projects with a flexible project structure," Hannover Economic Papers (HEP) dp-511, Leibniz Universität Hannover, Wirtschaftswissenschaftliche Fakultät.
- Florian Mischek & Nysret Musliu, 2021. "A local search framework for industrial test laboratory scheduling," Annals of Operations Research, Springer, vol. 302(2), pages 533-562, July.
- Brucker, Peter & Drexl, Andreas & Mohring, Rolf & Neumann, Klaus & Pesch, Erwin, 1999. "Resource-constrained project scheduling: Notation, classification, models, and methods," European Journal of Operational Research, Elsevier, vol. 112(1), pages 3-41, January.
- Weglarz, Jan & Józefowska, Joanna & Mika, Marek & Waligóra, Grzegorz, 2011. "Project scheduling with finite or infinite number of activity processing modes - A survey," European Journal of Operational Research, Elsevier, vol. 208(3), pages 177-205, February.
- Schirmer, Andreas & Riesenberg, Sven, 1997. "Parameterized heuristics for project scheduling: Biased random sampling methods," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 456, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Tiwari, Vikram & Patterson, James H. & Mabert, Vincent A., 2009. "Scheduling projects with heterogeneous resources to meet time and quality objectives," European Journal of Operational Research, Elsevier, vol. 193(3), pages 780-790, March.
- Schirmer, Andreas & Riesenberg, Sven, 1998. "Class-based control schemes for parameterized project scheduling heuristics," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 471, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Dolgui, Alexandre & Kovalev, Sergey & Kovalyov, Mikhail Y. & Malyutin, Sergey & Soukhal, Ameur, 2018. "Optimal workforce assignment to operations of a paced assembly line," European Journal of Operational Research, Elsevier, vol. 264(1), pages 200-211.
- Hartmann, Sönke & Briskorn, Dirk, 2008. "A survey of variants and extensions of the resource-constrained project scheduling problem," Working Paper Series 02/2008, Hamburg School of Business Administration (HSBA).
- Schirmer, Andreas & Potzahr, Kathrin, 2001. "Lehrgangsplanung für die Ausbildung von Verkehrsflugzeugführern: Ergebnisse einer Studie bei Lufthansa Flight Training," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 538, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Karen Puttkammer & Rainer Kleber & Tobias Schulz & Karl Inderfurth, 2011. "Simultane Maschinenbelegungs- und Personaleinsatzplanung in KMUs anhand eines Fallbeispiels aus der Druckereibranche," FEMM Working Papers 110010, Otto-von-Guericke University Magdeburg, Faculty of Economics and Management.
- Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
- Wang, Xiong & Ferreira, Fernando A.F. & Chang, Ching-Ter, 2022. "Multi-objective competency-based approach to project scheduling and staff assignment: Case study of an internal audit project," Socio-Economic Planning Sciences, Elsevier, vol. 81(C).
- Florian Mischek & Nysret Musliu & Andrea Schaerf, 2023. "Local search approaches for the test laboratory scheduling problem with variable task grouping," Journal of Scheduling, Springer, vol. 26(5), pages 457-477, October.
- Čapek, R. & Šůcha, P. & Hanzálek, Z., 2012. "Production scheduling with alternative process plans," European Journal of Operational Research, Elsevier, vol. 217(2), pages 300-311.
- Mohammad Rostami & Morteza Bagherpour, 2020. "A lagrangian relaxation algorithm for facility location of resource-constrained decentralized multi-project scheduling problems," Operational Research, Springer, vol. 20(2), pages 857-897, June.
- Bersch, Christopher V. & Akkerman, Renzo & Kolisch, Rainer, 2021. "Strategic planning of new product introductions: Integrated planning of products and modules in the automotive industry," Omega, Elsevier, vol. 105(C).
- Adrian Zimmermann & Norbert Trautmann, 2018. "A list-scheduling heuristic for the short-term planning of assessment centers," Journal of Scheduling, Springer, vol. 21(2), pages 131-142, April.
Most related items
These are the items that most often cite the same works as this one and are cited by the same works as this one.- Salewski, Frank & Schirmer, Andreas & Drexl, Andreas, 1996. "Project Scheduling under Resource and Mode Identity Constraints. Part I: Model, Complexity Status, and Methods," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 387, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Schirmer, Andreas & Riesenberg, Sven, 1997. "Parameterized heuristics for project scheduling: Biased random sampling methods," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 456, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Kolisch, R. & Padman, R., 2001.
"An integrated survey of deterministic project scheduling,"
Omega, Elsevier, vol. 29(3), pages 249-272, June.
- Kolisch, Rainer & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 8114, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
- Kolisch, Rainer, 1996. "Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation," European Journal of Operational Research, Elsevier, vol. 90(2), pages 320-333, April.
- Kolisch, Rainer, 1994. "Serial and parallel resource-constrained projekt scheduling methodes revisited: Theory and computation," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 344, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Brucker, Peter & Drexl, Andreas & Mohring, Rolf & Neumann, Klaus & Pesch, Erwin, 1999. "Resource-constrained project scheduling: Notation, classification, models, and methods," European Journal of Operational Research, Elsevier, vol. 112(1), pages 3-41, January.
- Kolisch, Rainer & Sprecher, Arno & Drexl, Andreas, 1992. "Characterization and generation of a general class of resource-constrained project scheduling problems: Easy and hard instances," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 301, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Aristide Mingozzi & Vittorio Maniezzo & Salvatore Ricciardelli & Lucio Bianco, 1998. "An Exact Algorithm for the Resource-Constrained Project Scheduling Problem Based on a New Mathematical Formulation," Management Science, INFORMS, vol. 44(5), pages 714-729, May.
- Schirmer, Andreas & Riesenberg, Sven, 1998. "Class-based control schemes for parameterized project scheduling heuristics," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 471, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Kolisch, Rainer & Drexl, Andreas, 1994. "Hybrid biased random sampling for multiple resourse-constrained project scheduling problems," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 354, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Yang, Kum-Khiong, 1998. "A comparison of dispatching rules for executing a resource-constrained project with estimated activity durations," Omega, Elsevier, vol. 26(6), pages 729-738, December.
- Jan Böttcher & Andreas Drexl & Rainer Kolisch & Frank Salewski, 1999. "Project Scheduling Under Partially Renewable Resource Constraints," Management Science, INFORMS, vol. 45(4), pages 543-559, April.
- Salewski, Frank & Schirmer, Andreas & Drexl, Andreas, 1996. "Project Scheduling under Resource and Mode Identity Constraints. Part II: An Application to Audit-Staff Scheduling," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 388, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Sprecher, Arno, 1996. "Solving the RCPSP efficiently at modest memory requirements," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 425, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Böttcher, Jan & Drexl, Andreas & Kolisch, Rainer & Salewski, Frank, 1996. "Project scheduling under partially renewable resource constraints," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 398, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Kolisch, Rainer, 1994. "Efficient priority rules for the resource-constrained project scheduling problem," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 350, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Drexl, Andreas & Kolisch, Rainer & Sprecher, Arno, 1995. "Neuere Entwicklungen in der computergestützten Projektplanung," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 379, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
- Browning, Tyson R. & Yassine, Ali A., 2010. "Resource-constrained multi-project scheduling: Priority rule performance revisited," International Journal of Production Economics, Elsevier, vol. 126(2), pages 212-228, August.
- Rainer Kolisch & Andreas Drexl, 1996. "Adaptive search for solving hard project scheduling problems," Naval Research Logistics (NRL), John Wiley & Sons, vol. 43(1), pages 23-40, February.
- Sprecher, Arno & Drexl, Andreas, 1998. "Multi-mode resource-constrained project scheduling by a simple, general and powerful sequencing algorithm," European Journal of Operational Research, Elsevier, vol. 107(2), pages 431-450, June.
Corrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:ejores:v:102:y:1997:i:1:p:88-110. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/eor .
Please note that corrections may take a couple of weeks to filter through the various RePEc services.