Fuzzy Multi Objective Project Scheduling Under Inflationary Conditions

Author

Listed:
  • Fatemeh Azimi

    (Departmentof Mathematics, Qazvin Branch Islamic Azad University, Qazvin, Iran)

  • Fatemeh Fathallahi

    (Faculty of Industrial Engineering K.N. Toosi University of Technology, Tehran, Iran)

Abstract

Project scheduling is a major area of project management and planning. Due to the increasing prices of goods in most countries during the project and lack of information related to each parameters and variables, using fuzzy sets under inflationary condition can be efficient. In this paper, fuzzy project scheduling when project’s revenues and costs are increased by different inflationary rate is considered. The duration of each project’s activity is assumed as a fuzzy number. Two objectives of the problem are to minimize the project duration and to maximize the net present value of the project. The nonlinear multi-objective model will be solved by one of the multi- objective decision making methods named LP-Metric method and Frank-Wolf algorithm as one of the nonlinear programming procedure. The solving approach will be explained in a numerical example and the computational results will be reported.

Suggested Citation

  • Fatemeh Azimi & Fatemeh Fathallahi, 2016. "Fuzzy Multi Objective Project Scheduling Under Inflationary Conditions," ECONOMIC COMPUTATION AND ECONOMIC CYBERNETICS STUDIES AND RESEARCH, Faculty of Economic Cybernetics, Statistics and Informatics, vol. 50(3), pages 337-350.
  • Handle: RePEc:cys:ecocyb:v:50:y:2016:i:3:p:337-350
    as

    Download full text from publisher

    File URL: ftp://www.eadr.ro/RePEc/cys/ecocyb_pdf/ecocyb3_2016p337-350.pdf
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Jolayemi, J. K. & Oluleye, A. E., 1993. "Scheduling of projects under the condition of inflation," Omega, Elsevier, vol. 21(4), pages 481-487, July.
    2. Sobel, Matthew J. & Szmerekovsky, Joseph G. & Tilson, Vera, 2009. "Scheduling projects with stochastic activity duration to maximize expected net present value," European Journal of Operational Research, Elsevier, vol. 198(3), pages 697-705, November.
    3. Herroelen, Willy & Leus, Roel, 2005. "Project scheduling under uncertainty: Survey and research potentials," European Journal of Operational Research, Elsevier, vol. 165(2), pages 289-306, September.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Yangyang Liang & Nanfang Cui & Tian Wang & Erik Demeulemeester, 2019. "Robust resource-constrained max-NPV project scheduling with stochastic activity duration," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 41(1), pages 219-254, March.
    2. Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
    3. Kerkhove, L.-P. & Vanhoucke, M., 2017. "Optimised scheduling for weather sensitive offshore construction projects," Omega, Elsevier, vol. 66(PA), pages 58-78.
    4. Illana Bendavid & Boaz Golany, 2009. "Setting gates for activities in the stochastic project scheduling problem through the cross entropy methodology," Annals of Operations Research, Springer, vol. 172(1), pages 259-276, November.
    5. Öncü Hazir & Gündüz Ulusoy, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," Post-Print hal-02898162, HAL.
    6. Illana Bendavid & Boaz Golany, 2011. "Predetermined intervals for start times of activities in the stochastic project scheduling problem," Annals of Operations Research, Springer, vol. 186(1), pages 429-442, June.
    7. Illana Bendavid & Boaz Golany, 2011. "Setting gates for activities in the stochastic project scheduling problem through the cross entropy methodology," Annals of Operations Research, Springer, vol. 189(1), pages 25-42, September.
    8. Magni, Carlo Alberto, 2015. "Investment, financing and the role of ROA and WACC in value creation," European Journal of Operational Research, Elsevier, vol. 244(3), pages 855-866.
    9. Zaraket, Fadi A. & Olleik, Majd & Yassine, Ali A., 2014. "Skill-based framework for optimal software project selection and resource allocation," European Journal of Operational Research, Elsevier, vol. 234(1), pages 308-318.
    10. Hartmann, Sönke & Briskorn, Dirk, 2022. "An updated survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 297(1), pages 1-14.
    11. Altekin, F. Tevhide & Bukchin, Yossi, 2022. "A multi-objective optimization approach for exploring the cost and makespan trade-off in additive manufacturing," European Journal of Operational Research, Elsevier, vol. 301(1), pages 235-253.
    12. Xiong, Jian & Leus, Roel & Yang, Zhenyu & Abbass, Hussein A., 2016. "Evolutionary multi-objective resource allocation and scheduling in the Chinese navigation satellite system project," European Journal of Operational Research, Elsevier, vol. 251(2), pages 662-675.
    13. Shichang Xiao & Shudong Sun & Jionghua (Judy) Jin, 2017. "Surrogate Measures for the Robust Scheduling of Stochastic Job Shop Scheduling Problems," Energies, MDPI, vol. 10(4), pages 1-26, April.
    14. He, Yukang & Jia, Tao & Zheng, Weibo, 2023. "Tabu search for dedicated resource-constrained multiproject scheduling to minimise the maximal cash flow gap under uncertainty," European Journal of Operational Research, Elsevier, vol. 310(1), pages 34-52.
    15. Servranckx, Tom & Vanhoucke, Mario, 2019. "Strategies for project scheduling with alternative subgraphs under uncertainty: similar and dissimilar sets of schedules," European Journal of Operational Research, Elsevier, vol. 279(1), pages 38-53.
    16. Nicolas Zufferey & Olivier Labarthe & David Schindl, 2012. "Heuristics for a project management problem with incompatibility and assignment costs," Computational Optimization and Applications, Springer, vol. 51(3), pages 1231-1252, April.
    17. Gutjahr, Walter J., 2015. "Bi-Objective Multi-Mode Project Scheduling Under Risk Aversion," European Journal of Operational Research, Elsevier, vol. 246(2), pages 421-434.
    18. Morteza Davari & Erik Demeulemeester, 2019. "The proactive and reactive resource-constrained project scheduling problem," Journal of Scheduling, Springer, vol. 22(2), pages 211-237, April.
    19. Moukrim, Aziz & Quilliot, Alain & Toussaint, Hélène, 2015. "An effective branch-and-price algorithm for the Preemptive Resource Constrained Project Scheduling Problem based on minimal Interval Order Enumeration," European Journal of Operational Research, Elsevier, vol. 244(2), pages 360-368.
    20. Da Lu & Fatma Gzara, 2015. "The robust crew pairing problem: model and solution methodology," Journal of Global Optimization, Springer, vol. 62(1), pages 29-54, May.

    More about this item

    Keywords

    Fuzzy sets; Inflation; Project scheduling; Makespan; NPV.;
    All these keywords.

    JEL classification:

    • C44 - Mathematical and Quantitative Methods - - Econometric and Statistical Methods: Special Topics - - - Operations Research; Statistical Decision Theory
    • E31 - Macroeconomics and Monetary Economics - - Prices, Business Fluctuations, and Cycles - - - Price Level; Inflation; Deflation
    • E40 - Macroeconomics and Monetary Economics - - Money and Interest Rates - - - General

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:cys:ecocyb:v:50:y:2016:i:3:p:337-350. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Corina Saman (email available below). General contact details of provider: https://edirc.repec.org/data/feasero.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.