Project Evaluation and Selection with Task Failures

Author

Listed:
  • Wenhui Zhao
  • Nicholas G. Hall
  • Zhixin Liu

Abstract

We consider a company that schedules the tasks of its projects to maximize their expected net present value (ENPV) when tasks may fail. The failure of any task terminates the project immediately. We show that for projects with certain decreasing failure rates, the ENPV optimization problem can be solved using a linear program. The main focus of our work is on how constant task failure rates contribute to decreasing project risk as tasks are completed. Under constant task failure rate, earlier completion of a task improves its probability of success and the risk profile of the project. However, it may also accelerate costs, which worsen discounted cash flow. We show the equivalence of cash flow discount rate and failure rate. Further, if task failures are independent, then the failure rates are additive. We develop a model that (a) recognizes the reduction in project risk when a task is completed, (b) implements this risk reduction into the ENPV calculation, and (c) permits optimization of the ENPV through sequencing and timing decisions for the tasks. We design an algorithm to solve the problem optimally. This enables us to validate the contributions of our work using two computational studies. The first study demonstrates a significant increase in maximum project ENPV from improved project scheduling. The second study demonstrates a significant increase in total project portfolio value as a result of better informed project selection. Our work motivates companies to develop more precise information about the failure risks of their project tasks.

Suggested Citation

  • Wenhui Zhao & Nicholas G. Hall & Zhixin Liu, 2020. "Project Evaluation and Selection with Task Failures," Production and Operations Management, Production and Operations Management Society, vol. 29(2), pages 428-446, February.
  • Handle: RePEc:bla:popmgt:v:29:y:2020:i:2:p:428-446
    DOI: 10.1111/poms.13107
    as

    Download full text from publisher

    File URL: https://doi.org/10.1111/poms.13107
    Download Restriction: no

    File URL: https://libkey.io/10.1111/poms.13107?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Jonathan F. Bard, 1985. "Parallel Funding of R&D Tasks with Probabilistic Outcomes," Management Science, INFORMS, vol. 31(7), pages 814-828, July.
    2. A. H. Russell, 1970. "Cash Flows in Networks," Management Science, INFORMS, vol. 16(5), pages 357-373, January.
    3. Robert A. Russell, 1986. "A Comparison of Heuristics for Scheduling Projects with Cash Flows and Resource Restrictions," Management Science, INFORMS, vol. 32(10), pages 1291-1300, October.
    4. Stephen Stollmack & Carl M. Harris, 1974. "Failure-Rate Analysis Applied to Recidivism Data," Operations Research, INFORMS, vol. 22(6), pages 1192-1205, December.
    5. Yorgos Goletsis & John Psarras & Jesus-Emmanuel Samouilidis, 2003. "Project Ranking in the Armenian Energy Sector Using a Multicriteria Method for Groups," Annals of Operations Research, Springer, vol. 120(1), pages 135-157, April.
    6. Oral, Muhittin & Kettani, Ossama & Cinar, Unver, 2001. "Project evaluation and selection in a network of collaboration: A consensual disaggregation multi-criterion approach," European Journal of Operational Research, Elsevier, vol. 130(2), pages 332-346, April.
    7. B. De Reyck & Y. Grushka-Cockayne & R. Leus, 2007. "A New Challenge in Project Scheduling. The Incorporation of Activity Failures," Review of Business and Economic Literature, KU Leuven, Faculty of Economics and Business (FEB), Review of Business and Economic Literature, vol. 0(3), pages 410-435.
    8. Nelson, Craig A., 1986. "A scoring model for flexible manufacturing systems project selection," European Journal of Operational Research, Elsevier, vol. 24(3), pages 346-359, March.
    9. Baozhuang Niu & Kanglin Chen & Xin Fang & Xiaohang Yue & Xin Wang, 2019. "Technology Specifications and Production Timing in a Co‐Opetitive Supply Chain," Production and Operations Management, Production and Operations Management Society, vol. 28(8), pages 1990-2007, August.
    10. Herroelen, Willy S. & Gallens, Els, 1993. "Computational experience with an optimal procedure for the scheduling of activities to maximize the net present value of projects," European Journal of Operational Research, Elsevier, vol. 65(2), pages 274-277, March.
    11. Yaozhong Wu & Karthik Ramachandran & Vish Krishnan, 2014. "Managing Cost Salience and Procrastination in Projects: Compensation and Team Composition," Production and Operations Management, Production and Operations Management Society, vol. 23(8), pages 1299-1311, August.
    12. Richard C. Grinold, 1972. "The payment scheduling problem," Naval Research Logistics Quarterly, John Wiley & Sons, vol. 19(1), pages 123-136, March.
    13. Christos Ellinas, 2019. "The Domino Effect: An Empirical Exposition of Systemic Risk Across Project Networks," Production and Operations Management, Production and Operations Management Society, vol. 28(1), pages 63-81, January.
    14. Elmaghraby, Salah E. & Herroelen, Willy S., 1990. "The scheduling of activities to maximize the net present value of projects," European Journal of Operational Research, Elsevier, vol. 49(1), pages 35-49, November.
    15. Wiesemann, Wolfram & Kuhn, Daniel & Rustem, Berç, 2010. "Maximizing the net present value of a project under uncertainty," European Journal of Operational Research, Elsevier, vol. 202(2), pages 356-367, April.
    16. Janne Kettunen & Ahti Salo, 2017. "Estimation of Downside Risks in Project Portfolio Selection," Production and Operations Management, Production and Operations Management Society, vol. 26(10), pages 1839-1853, October.
    17. Nicholas G. Hall & Marc E. Posner, 2001. "Generating Experimental Data for Computational Testing with Machine Scheduling Applications," Operations Research, INFORMS, vol. 49(6), pages 854-865, December.
    18. Rainer Kolisch & Konrad Meyer, 2006. "Selection and Scheduling of Pharmaceutical Research Projects," International Series in Operations Research & Management Science, in: Joanna Józefowska & Jan Weglarz (ed.), Perspectives in Modern Project Scheduling, chapter 0, pages 321-344, Springer.
    19. Stefan Creemers & Bert De Reyck & Roel Leus, 2015. "Project planning with alternative technologies in uncertain environments," Post-Print hal-01563008, HAL.
    20. C. Perry & I. D. Greig, 1975. "Estimating the Mean and Variance of Subjective Distributions in PERT and Decision Analysis," Management Science, INFORMS, vol. 21(12), pages 1477-1480, August.
    21. Xuejun Hu & Nanfang Cui & Erik Demeulemeester, 2015. "Effective expediting to improve project due date and cost performance through buffer management," International Journal of Production Research, Taylor & Francis Journals, vol. 53(5), pages 1460-1471, March.
    22. Creemers, Stefan & De Reyck, Bert & Leus, Roel, 2015. "Project planning with alternative technologies in uncertain environments," European Journal of Operational Research, Elsevier, vol. 242(2), pages 465-476.
    23. Baozhuang Niu & Jiawei Li & Jie Zhang & Hsing Kenneth Cheng & Yinliang (Ricky) Tan, 2019. "Strategic Analysis of Dual Sourcing and Dual Channel with an Unreliable Alternative Supplier," Production and Operations Management, Production and Operations Management Society, vol. 28(3), pages 570-587, March.
    24. Sobel, Matthew J. & Szmerekovsky, Joseph G. & Tilson, Vera, 2009. "Scheduling projects with stochastic activity duration to maximize expected net present value," European Journal of Operational Research, Elsevier, vol. 198(3), pages 697-705, November.
    25. Herroelen, Willy S. & Van Dommelen, Patrick & Demeulemeester, Erik L., 1997. "Project network models with discounted cash flows a guided tour through recent developments," European Journal of Operational Research, Elsevier, vol. 100(1), pages 97-121, July.
    26. Christoph Schwindt & Jürgen Zimmermann, 2001. "A steepest ascent approach to maximizing the net present value of projects," Mathematical Methods of Operations Research, Springer;Gesellschaft für Operations Research (GOR);Nederlands Genootschap voor Besliskunde (NGB), vol. 53(3), pages 435-450, July.
    27. Oya Icmeli & S. Selcuk Erenguc, 1996. "A Branch and Bound Procedure for the Resource Constrained Project Scheduling Problem with Discounted Cash Flows," Management Science, INFORMS, vol. 42(10), pages 1395-1408, October.
    28. Mario Vanhoucke & Erik Demeulemeester & Willy Herroelen, 2001. "On Maximizing the Net Present Value of a Project Under Renewable Resource Constraints," Management Science, INFORMS, vol. 47(8), pages 1113-1121, August.
    29. Green, Rodney H. & Doyle, John R. & Cook, Wade D., 1996. "Preference voting and project ranking using DEA and cross-evaluation," European Journal of Operational Research, Elsevier, vol. 90(3), pages 461-472, May.
    30. Nicky J. Welton & Howard H. Z. Thom, 2015. "Value of Information," Medical Decision Making, , vol. 35(5), pages 564-566, July.
    31. Anant Mishra & Sidhartha R. Das & James J. Murray, 2016. "Risk, Process Maturity, and Project Performance: An Empirical Analysis of US Federal Government Technology Projects," Production and Operations Management, Production and Operations Management Society, vol. 25(2), pages 210-232, February.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Hongbo Li & Rui Chen & Xianchao Zhang, 2022. "Uncertain Public R&D Project Portfolio Selection Considering Sectoral Balancing and Project Failure," Sustainability, MDPI, vol. 14(23), pages 1-13, November.
    2. She, Bingling & Chen, Bo & Hall, Nicholas G., 2021. "Buffer sizing in critical chain project management by network decomposition," Omega, Elsevier, vol. 102(C).
    3. Aditya Vedantam & Ananth Iyer, 2021. "Capacity Investment under Bayesian Information Updates at Reporting Periods: Model and Application," Production and Operations Management, Production and Operations Management Society, vol. 30(8), pages 2707-2725, August.
    4. Maciej Nowak & Tadeusz Trzaskalik, 2022. "A trade-off multiobjective dynamic programming procedure and its application to project portfolio selection," Annals of Operations Research, Springer, vol. 311(2), pages 1155-1181, April.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Mika, Marek & Waligora, Grzegorz & Weglarz, Jan, 2005. "Simulated annealing and tabu search for multi-mode resource-constrained project scheduling with positive discounted cash flows and different payment models," European Journal of Operational Research, Elsevier, vol. 164(3), pages 639-668, August.
    2. He, Zhengwen & Wang, Nengmin & Jia, Tao & Xu, Yu, 2009. "Simulated annealing and tabu search for multi-mode project payment scheduling," European Journal of Operational Research, Elsevier, vol. 198(3), pages 688-696, November.
    3. Creemers, Stefan, 2018. "Maximizing the expected net present value of a project with phase-type distributed activity durations: An efficient globally optimal solution procedure," European Journal of Operational Research, Elsevier, vol. 267(1), pages 16-22.
    4. Joseph G. Szmerekovsky & George L. Vairaktarakis, 2006. "Maximizing project cash availability," Naval Research Logistics (NRL), John Wiley & Sons, vol. 53(4), pages 272-284, June.
    5. Peymankar, Mahboobeh & Davari, Morteza & Ranjbar, Mohammad, 2021. "Maximizing the expected net present value in a project with uncertain cash flows," European Journal of Operational Research, Elsevier, vol. 294(2), pages 442-452.
    6. M. Vanhoucke, 2006. "An efficient hybrid search algorithm for various optimization problems," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 06/365, Ghent University, Faculty of Economics and Business Administration.
    7. Kolisch, R. & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Omega, Elsevier, vol. 29(3), pages 249-272, June.
    8. Vanhoucke, Mario & Demeulemeester, Erik & Herroelen, Willy, 2003. "Progress payments in project scheduling problems," European Journal of Operational Research, Elsevier, vol. 148(3), pages 604-620, August.
    9. Mario Vanhoucke & Erik Demeulemeester & Willy Herroelen, 2001. "On Maximizing the Net Present Value of a Project Under Renewable Resource Constraints," Management Science, INFORMS, vol. 47(8), pages 1113-1121, August.
    10. Hermans, Ben & Leus, Roel & Looy, Bart Van, 2023. "Deciding on scheduling, secrecy, and patenting during the new product development process: The relevance of project planning models," Omega, Elsevier, vol. 116(C).
    11. Etgar, Ran & Gelbard, Roy & Cohen, Yuval, 2017. "Optimizing version release dates of research and development long-term processes," European Journal of Operational Research, Elsevier, vol. 259(2), pages 642-653.
    12. Nursel Kavlak & Gündüz Ulusoy & Funda Sivrikaya Şerifoğlu & Ş. İlker Birbil, 2009. "Client‐contractor bargaining on net present value in project scheduling with limited resources," Naval Research Logistics (NRL), John Wiley & Sons, vol. 56(2), pages 93-112, March.
    13. Yangyang Liang & Nanfang Cui & Tian Wang & Erik Demeulemeester, 2019. "Robust resource-constrained max-NPV project scheduling with stochastic activity duration," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 41(1), pages 219-254, March.
    14. De Reyck, Bert & Herroelen, willy, 1998. "A branch-and-bound procedure for the resource-constrained project scheduling problem with generalized precedence relations," European Journal of Operational Research, Elsevier, vol. 111(1), pages 152-174, November.
    15. Thomas Schmitt & Bruce Faaland, 2004. "Scheduling recurrent construction," Naval Research Logistics (NRL), John Wiley & Sons, vol. 51(8), pages 1102-1128, December.
    16. Creemers, Stefan, 2018. "Moments and distribution of the net present value of a serial project," European Journal of Operational Research, Elsevier, vol. 267(3), pages 835-848.
    17. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    18. Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
    19. He, Zhengwen & Xu, Yu, 2008. "Multi-mode project payment scheduling problems with bonus-penalty structure," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1191-1207, September.
    20. Brucker, Peter & Drexl, Andreas & Mohring, Rolf & Neumann, Klaus & Pesch, Erwin, 1999. "Resource-constrained project scheduling: Notation, classification, models, and methods," European Journal of Operational Research, Elsevier, vol. 112(1), pages 3-41, January.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:bla:popmgt:v:29:y:2020:i:2:p:428-446. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Wiley Content Delivery (email available below). General contact details of provider: http://onlinelibrary.wiley.com/journal/10.1111/(ISSN)1937-5956 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.