Multiproject Resources Allocation Model under Fuzzy Random Environment and Its Application to Industrial Equipment Installation Engineering
Author
Abstract
Suggested Citation
DOI: 10.1155/2013/818731
Download full text from publisher
References listed on IDEAS
- Xu, Jiuping & Yan, Fang & Li, Steven, 2011. "Vehicle routing optimization with soft time windows in a fuzzy random environment," Transportation Research Part E: Logistics and Transportation Review, Elsevier, vol. 47(6), pages 1075-1091.
- Brucker, Peter & Drexl, Andreas & Mohring, Rolf & Neumann, Klaus & Pesch, Erwin, 1999. "Resource-constrained project scheduling: Notation, classification, models, and methods," European Journal of Operational Research, Elsevier, vol. 112(1), pages 3-41, January.
- Golenko-Ginzburg, Dimitri & Gonik, Aharon, 1997. "Stochastic network project scheduling with non-consumable limited resources," International Journal of Production Economics, Elsevier, vol. 48(1), pages 29-37, January.
- H. Zhang & C. M. Tam, 2003. "Fuzzy decision-making for dynamic resource allocation," Construction Management and Economics, Taylor & Francis Journals, vol. 21(1), pages 31-41.
- Golenko-Ginzburg, Dimitri & Gonik, Aharon, 1998. "A heuristic for network project scheduling with random activity durations depending on the resource allocation," International Journal of Production Economics, Elsevier, vol. 55(2), pages 149-162, July.
- Tao Zhang & Tiesong Hu & Yue Zheng & Xuning Guo, 2012. "An Improved Particle Swarm Optimization for Solving Bilevel Multiobjective Programming Problem," Journal of Applied Mathematics, Hindawi, vol. 2012, pages 1-13, April.
- Omar Ben-Ayed & Charles E. Blair, 1990. "Computational Difficulties of Bilevel Linear Programming," Operations Research, INFORMS, vol. 38(3), pages 556-560, June.
- Yang, Kum-Khiong & Sum, Chee-Chuong, 1997. "An evaluation of due date, resource allocation, project release, and activity scheduling rules in a multiproject environment," European Journal of Operational Research, Elsevier, vol. 103(1), pages 139-154, November.
- Mori, Masao & Tseng, Ching Chih, 1997. "A genetic algorithm for multi-mode resource constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 100(1), pages 134-141, July.
- Tao Zhang & Tiesong Hu & Yue Zheng & Xuning Guo, 2012. "An Improved Particle Swarm Optimization for Solving Bilevel Multiobjective Programming Problem," Journal of Applied Mathematics, John Wiley & Sons, vol. 2012(1).
Most related items
These are the items that most often cite the same works as this one and are cited by the same works as this one.- Xiong, Jian & Leus, Roel & Yang, Zhenyu & Abbass, Hussein A., 2016. "Evolutionary multi-objective resource allocation and scheduling in the Chinese navigation satellite system project," European Journal of Operational Research, Elsevier, vol. 251(2), pages 662-675.
- Jianxue Wang & Jianming Lu & Zhaohong Bie & Shutang You & Xiaoyu Cao, 2014. "Long‐Term Maintenance Scheduling of Smart Distribution System through a PSO‐TS Algorithm," Journal of Applied Mathematics, John Wiley & Sons, vol. 2014(1).
- V. Van Peteghem & M. Vanhoucke, 2009. "Using Resource Scarceness Characteristics to Solve the Multi-Mode Resource-Constrained Project Scheduling Problem," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 09/595, Ghent University, Faculty of Economics and Business Administration.
- Rabbani, M. & Fatemi Ghomi, S.M.T. & Jolai, F. & Lahiji, N.S., 2007. "A new heuristic for resource-constrained project scheduling in stochastic networks using critical chain concept," European Journal of Operational Research, Elsevier, vol. 176(2), pages 794-808, January.
- Krüger, Doreen & Scholl, Armin, 2009. "A heuristic solution framework for the resource constrained (multi-)project scheduling problem with sequence-dependent transfer times," European Journal of Operational Research, Elsevier, vol. 197(2), pages 492-508, September.
- Siqian Shen & J. Cole Smith & Shabbir Ahmed, 2010. "Expectation and Chance-Constrained Models and Algorithms for Insuring Critical Paths," Management Science, INFORMS, vol. 56(10), pages 1794-1814, October.
- Peteghem, Vincent Van & Vanhoucke, Mario, 2010. "A genetic algorithm for the preemptive and non-preemptive multi-mode resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 201(2), pages 409-418, March.
- Weglarz, Jan & Józefowska, Joanna & Mika, Marek & Waligóra, Grzegorz, 2011. "Project scheduling with finite or infinite number of activity processing modes - A survey," European Journal of Operational Research, Elsevier, vol. 208(3), pages 177-205, February.
- Ming-Ta Yang & An Liu, 2013. "Applying Hybrid PSO to Optimize Directional Overcurrent Relay Coordination in Variable Network Topologies," Journal of Applied Mathematics, John Wiley & Sons, vol. 2013(1).
- Van Peteghem, Vincent & Vanhoucke, Mario, 2014.
"An experimental investigation of metaheuristics for the multi-mode resource-constrained project scheduling problem on new dataset instances,"
European Journal of Operational Research, Elsevier, vol. 235(1), pages 62-72.
- V. Van Peteghem & M. Vanhoucke, 2011. "An Experimental Investigation of Metaheuristics for the Multi-Mode Resource-Constrained Project Scheduling Problem on New Dataset Instances," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 11/758, Ghent University, Faculty of Economics and Business Administration.
- Öncü Hazir & Gündüz Ulusoy, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," Post-Print hal-02898162, HAL.
- Browning, Tyson R. & Yassine, Ali A., 2010. "Resource-constrained multi-project scheduling: Priority rule performance revisited," International Journal of Production Economics, Elsevier, vol. 126(2), pages 212-228, August.
- Golenko-Ginzburg, Dimitri & Gonik, Aharon & Laslo, Zohar, 2003. "Resource constrained scheduling simulation model for alternative stochastic network projects," Mathematics and Computers in Simulation (MATCOM), Elsevier, vol. 63(2), pages 105-117.
- Coelho, José & Vanhoucke, Mario, 2011.
"Multi-mode resource-constrained project scheduling using RCPSP and SAT solvers,"
European Journal of Operational Research, Elsevier, vol. 213(1), pages 73-82, August.
- J. Coelho & M. Vanhoucke, 2009. "Multi-mode resource constrained pro ject scheduling using RCPSP and SAT solvers," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 09/614, Ghent University, Faculty of Economics and Business Administration.
- Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
- T Wauters & K Verbeeck & G Vanden Berghe & P De Causmaecker, 2011. "Learning agents for the multi-mode project scheduling problem," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 62(2), pages 281-290, February.
- Azaron, Amir & Tavakkoli-Moghaddam, Reza, 2007. "Multi-objective time-cost trade-off in dynamic PERT networks using an interactive approach," European Journal of Operational Research, Elsevier, vol. 180(3), pages 1186-1200, August.
- Herroelen, Willy & Leus, Roel, 2005. "Project scheduling under uncertainty: Survey and research potentials," European Journal of Operational Research, Elsevier, vol. 165(2), pages 289-306, September.
- Kolisch, R. & Padman, R., 2001.
"An integrated survey of deterministic project scheduling,"
Omega, Elsevier, vol. 29(3), pages 249-272, June.
- Kolisch, Rainer & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 8114, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
- Tseng, Lin-Yu & Chen, Shih-Chieh, 2006. "A hybrid metaheuristic for the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 175(2), pages 707-721, December.
Corrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:wly:jnljam:v:2013:y:2013:i:1:n:818731. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Wiley Content Delivery (email available below). General contact details of provider: https://onlinelibrary.wiley.com/journal/4185 .
Please note that corrections may take a couple of weeks to filter through the various RePEc services.
Printed from https://ideas.repec.org/a/wly/jnljam/v2013y2013i1n818731.html