A Project Risk Management Methodology Based on Probabilistic and Non-probabilistic Approach: A Study on Transmission Line Installation Projects

Author

Listed:
  • Shwetank Parihar
  • Chandan Bhar
  • Nishit Kumar Srivastava

Abstract

The article deals with the project risk analysis for electrical transmission line installation projects, where both probabilistic decision tree (DT) and non-probabilistic analytical hierarchy process (AHP) methods are used simultaneously on the same risks. The study gives the complete analysis for each risk type and finally they are analyzed by both AHP and DT; both of these techniques are selected for project’s risk minimization while designing the risk mitigation plan. A model is generated for minimizing the project risk and the risks selected after being analyzed through AHP and DT are then treated with this model for risk mitigation. Overall the study minimizes project risk by a three-step procedure, that is, AHP, DT, and finally through the risk minimization model for electrical transmission line installation projects.

Suggested Citation

  • Shwetank Parihar & Chandan Bhar & Nishit Kumar Srivastava, 2015. "A Project Risk Management Methodology Based on Probabilistic and Non-probabilistic Approach: A Study on Transmission Line Installation Projects," Jindal Journal of Business Research, , vol. 4(1-2), pages 27-45, June.
  • Handle: RePEc:sae:jjlobr:v:4:y:2015:i:1-2:p:27-45
    DOI: 10.1177/2278682116655662
    as

    Download full text from publisher

    File URL: https://journals.sagepub.com/doi/10.1177/2278682116655662
    Download Restriction: no

    File URL: https://libkey.io/10.1177/2278682116655662?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Tavares, L. Valadares & Antunes Ferreira, J. A. & Silva Coelho, J., 1998. "On the optimal management of project risk," European Journal of Operational Research, Elsevier, vol. 107(2), pages 451-469, June.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Servranckx, Tom & Vanhoucke, Mario, 2019. "Strategies for project scheduling with alternative subgraphs under uncertainty: similar and dissimilar sets of schedules," European Journal of Operational Research, Elsevier, vol. 279(1), pages 38-53.
    2. Janusz Kulejewski & Nabi Ibadov & Jerzy Rosłon & Jacek Zawistowski, 2021. "Cash Flow Optimization for Renewable Energy Construction Projects with a New Approach to Critical Chain Scheduling," Energies, MDPI, vol. 14(18), pages 1-15, September.
    3. Herroelen, Willy & Leus, Roel, 2004. "The construction of stable project baseline schedules," European Journal of Operational Research, Elsevier, vol. 156(3), pages 550-565, August.
    4. Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
    5. Van de Vonder, Stijn & Demeulemeester, Erik & Herroelen, Willy & Leus, Roel, 2005. "The use of buffers in project management: The trade-off between stability and makespan," International Journal of Production Economics, Elsevier, vol. 97(2), pages 227-240, August.
    6. Herroelen, Willy & Leus, Roel, 2005. "Project scheduling under uncertainty: Survey and research potentials," European Journal of Operational Research, Elsevier, vol. 165(2), pages 289-306, September.
    7. HazIr, Öncü & Haouari, Mohamed & Erel, Erdal, 2010. "Robust scheduling and robustness measures for the discrete time/cost trade-off problem," European Journal of Operational Research, Elsevier, vol. 207(2), pages 633-643, December.
    8. Wiesemann, Wolfram & Kuhn, Daniel & Rustem, Berç, 2010. "Maximizing the net present value of a project under uncertainty," European Journal of Operational Research, Elsevier, vol. 202(2), pages 356-367, April.
    9. KIlIç, Murat & Ulusoy, Gündüz & Serifoglu, Funda Sivrikaya, 2008. "A bi-objective genetic algorithm approach to risk mitigation in project scheduling," International Journal of Production Economics, Elsevier, vol. 112(1), pages 202-216, March.
    10. Bruni, M.E. & Di Puglia Pugliese, L. & Beraldi, P. & Guerriero, F., 2017. "An adjustable robust optimization model for the resource-constrained project scheduling problem with uncertain activity durations," Omega, Elsevier, vol. 71(C), pages 66-84.
    11. Said, Samer S. & Haouari, Mohamed, 2015. "A hybrid simulation-optimization approach for the robust Discrete Time/Cost Trade-off Problem," Applied Mathematics and Computation, Elsevier, vol. 259(C), pages 628-636.
    12. Öncü Hazir & Gündüz Ulusoy, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," Post-Print hal-02898162, HAL.
    13. Creemers, Stefan, 2018. "Maximizing the expected net present value of a project with phase-type distributed activity durations: An efficient globally optimal solution procedure," European Journal of Operational Research, Elsevier, vol. 267(1), pages 16-22.
    14. Dang, Jr-Fong & Hong, I-Hsuan, 2013. "The equilibrium quantity and production strategy in a fuzzy random decision environment: Game approach and case study in glass substrates industries," International Journal of Production Economics, Elsevier, vol. 145(2), pages 724-732.
    15. Jorgensen, Trond & Wallace, Stein W., 2000. "Improving project cost estimation by taking into account managerial flexibility," European Journal of Operational Research, Elsevier, vol. 127(2), pages 239-251, December.
    16. Tavares, L. V., 2002. "A review of the contribution of Operational Research to Project Management," European Journal of Operational Research, Elsevier, vol. 136(1), pages 1-18, January.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:sae:jjlobr:v:4:y:2015:i:1-2:p:27-45. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: SAGE Publications (email available below). General contact details of provider: .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.