A Novel Method of Developing Construction Projects Schedule under Rework Scenarios

Author

Listed:
  • Guofeng Ma

    (Department of Construction Management and Real Estate, TongJi University, Shanghai 200092, China)

  • Shan Jiang

    (Department of Construction Management and Real Estate, TongJi University, Shanghai 200092, China)

  • Tiancheng Zhu

    (Department of Construction Management and Real Estate, TongJi University, Shanghai 200092, China)

  • Jianyao Jia

    (Department of Construction Management and Real Estate, TongJi University, Shanghai 200092, China)

Abstract

Construction projects have faced serious schedule delays caused by rework risks. However, it appears that traditional methods are of limited value in developing applicable project schedules. This study presents an analysis on construction projects schedule development under rework scenarios by a novel method named the improved critical chain design structure matrix (CCDSM). Research data are collected from a real estate development project in China. As a result, predictions of project completion duration and probability have been made. A reliable schedule considering information interactions has been developed and visualized. Rework impact areas of activities have been examined to quantitatively record the impact on project duration. To meet different demands, the method generates two more schedules setting different rework buffers. Furthermore, these activities have the potential of causing rework and have been quantified based on the calculation of two criticalities, providing an identification of rework-intensive works that should be payed close importance to, which have not be realized by previous methods. The results proved the feasibility and effectiveness of this method in developing a schedule for construction projects disturbed by rework, helping practitioners adopt measures to avoid rework-caused schedule delays and achieve sustainable development of such projects.

Suggested Citation

  • Guofeng Ma & Shan Jiang & Tiancheng Zhu & Jianyao Jia, 2019. "A Novel Method of Developing Construction Projects Schedule under Rework Scenarios," Sustainability, MDPI, vol. 11(20), pages 1-25, October.
  • Handle: RePEc:gam:jsusta:v:11:y:2019:i:20:p:5710-:d:276948
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/2071-1050/11/20/5710/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/2071-1050/11/20/5710/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Tukel, Oya I. & Rom, Walter O. & Eksioglu, Sandra Duni, 2006. "An investigation of buffer sizing techniques in critical chain scheduling," European Journal of Operational Research, Elsevier, vol. 172(2), pages 401-416, July.
    2. Eppinger, Steven D. & Browning, Tyson R., 2012. "Design Structure Matrix Methods and Applications," MIT Press Books, The MIT Press, edition 1, volume 1, number 0262017520, April.
    3. Zhang, Junguang & Song, Xiwei & Díaz, Estrella, 2016. "Project buffer sizing of a critical chain based on comprehensive resource tightness," European Journal of Operational Research, Elsevier, vol. 248(1), pages 174-182.
    4. Tim Taylor & David N. Ford, 2006. "Tipping point failure and robustness in single development projects," System Dynamics Review, System Dynamics Society, vol. 22(1), pages 51-71, March.
    5. Martin Taggart & Lauri Koskela & John Rooke, 2014. "The role of the supply chain in the elimination and reduction of construction rework and defects: an action research approach," Construction Management and Economics, Taylor & Francis Journals, vol. 32(7-8), pages 829-842, August.
    6. Peter Love & Heng Li, 2000. "Quantifying the causes and costs of rework in construction," Construction Management and Economics, Taylor & Francis Journals, vol. 18(4), pages 479-490.
    7. Tyson R. Browning, 1999. "Sources of schedule risk in complex system development," Systems Engineering, John Wiley & Sons, vol. 2(3), pages 129-142.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Guofeng Ma & Jianyao Jia & Tiancheng Zhu & Shan Jiang, 2019. "A Critical Design Structure Method for Project Schedule Development under Rework Risks," Sustainability, MDPI, vol. 11(24), pages 1-20, December.
    2. Junguang Zhang & Xiwei Song & Hongyu Chen & Ruixia (Sandy) Shi, 2016. "Determination of critical chain project buffer based on information flow interactions," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 67(9), pages 1146-1157, September.
    3. Junguang Zhang & Dan Wan, 2021. "Determination of early warning time window for bottleneck resource buffer," Annals of Operations Research, Springer, vol. 300(1), pages 289-305, May.
    4. Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
    5. She, Bingling & Chen, Bo & Hall, Nicholas G., 2021. "Buffer sizing in critical chain project management by network decomposition," Omega, Elsevier, vol. 102(C).
    6. Xuejun Hu & Jianjiang Wang & Kaijun Leng, 2019. "The Interaction Between Critical Chain Sequencing, Buffer Sizing, and Reactive Actions in a CC/BM Framework," Asia-Pacific Journal of Operational Research (APJOR), World Scientific Publishing Co. Pte. Ltd., vol. 36(03), pages 1-22, June.
    7. Mohammadreza Sharifi Ghazvini & Vahidreza Ghezavati & Sadigh Raissi & Ahmad Makui, 2017. "An Integrated Efficiency–Risk Approach in Sustainable Project Control," Sustainability, MDPI, vol. 9(9), pages 1-20, September.
    8. Junguang Zhang & Xiwei Song & Estrella Díaz, 2017. "Critical chain project buffer sizing based on resource constraints," International Journal of Production Research, Taylor & Francis Journals, vol. 55(3), pages 671-683, February.
    9. Asadabadi, Mehdi Rajabi & Zwikael, Ofer, 2021. "Integrating risk into estimations of project activities' time and cost: A stratified approach," European Journal of Operational Research, Elsevier, vol. 291(2), pages 482-490.
    10. Zhang, Junguang & Song, Xiwei & Díaz, Estrella, 2016. "Project buffer sizing of a critical chain based on comprehensive resource tightness," European Journal of Operational Research, Elsevier, vol. 248(1), pages 174-182.
    11. Öncü Hazir & Gündüz Ulusoy, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," Post-Print hal-02898162, HAL.
    12. Xuejun Hu & Erik Demeulemeester & Nanfang Cui & Jianjiang Wang & Wendi Tian, 2017. "Improved critical chain buffer management framework considering resource costs and schedule stability," Flexible Services and Manufacturing Journal, Springer, vol. 29(2), pages 159-183, June.
    13. Wendi Tian & Erik Demeulemeester, 2014. "Railway scheduling reduces the expected project makespan over roadrunner scheduling in a multi-mode project scheduling environment," Annals of Operations Research, Springer, vol. 213(1), pages 271-291, February.
    14. Uwe Beyer & Oliver Ullrich, 2022. "Organizational Complexity as a Contributing Factor to Underperformance," Businesses, MDPI, vol. 2(1), pages 1-15, March.
    15. Morgan Dwyer & Bruce Cameron & Zoe Szajnfarber, 2015. "A Framework for Studying Cost Growth on Complex Acquisition Programs," Systems Engineering, John Wiley & Sons, vol. 18(6), pages 568-583, November.
    16. Félicia Saïah & Diego Vega & Harwin de Vries & Joakim Kembro, 2023. "Process modularity, supply chain responsiveness, and moderators: The Médecins Sans Frontières response to the Covid‐19 pandemic," Production and Operations Management, Production and Operations Management Society, vol. 32(5), pages 1490-1511, May.
    17. Hosang Hyun & Hyunsoo Kim & Hyun-Soo Lee & Moonseo Park & Jeonghoon Lee, 2020. "Integrated Design Process for Modular Construction Projects to Reduce Rework," Sustainability, MDPI, vol. 12(2), pages 1-19, January.
    18. Raphael N. Milion & Thaís da C. L. Alves & José Carlos Paliari & Luisa H. B. Liboni, 2021. "CBA-Based Evaluation Method of the Impact of Defects in Residential Buildings: Assessing Risks towards Making Sustainable Decisions on Continuous Improvement Activities," Sustainability, MDPI, vol. 13(12), pages 1-20, June.
    19. Alencastro, João & Fuertes, Alba & de Wilde, Pieter, 2018. "The relationship between quality defects and the thermal performance of buildings," Renewable and Sustainable Energy Reviews, Elsevier, vol. 81(P1), pages 883-894.
    20. Liu, Zhixue & Ding, Ronggui & Wang, Lei & Song, Rui & Song, Xinyi, 2023. "Cooperation in an uncertain environment: The impact of stakeholders' concerted action on collaborative innovation projects risk management," Technological Forecasting and Social Change, Elsevier, vol. 196(C).

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jsusta:v:11:y:2019:i:20:p:5710-:d:276948. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.