Cost and time control of construction projects: inhibiting factors and mitigating measures in practice
Author
Abstract
Suggested Citation
DOI: 10.1080/01446191003674519
Download full text from publisher
As the access to this document is restricted, you may want to search for a different version of it.
Citations
Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
Cited by:
- Kareem Mohammad Mahmoud Mostafa & Dr. Ayman Hamdy Nassar, 2018. "Using Artificial Neural Networks to Model Cost Overruns in Real Estate Projects," International Journal of Research and Scientific Innovation, International Journal of Research and Scientific Innovation (IJRSI), vol. 5(10), pages 72-86, October.
- Shenzhe Jiang & Junjie Xia & Jiajun Xu & Jianye Yan, 2023. "A theory of National Development Bank: long-term investment and the agency problem," Economic Theory, Springer;Society for the Advancement of Economic Theory (SAET), vol. 76(3), pages 995-1024, October.
- repec:eur:ejfejr:4 is not listed on IDEAS
- Byung-Yun Son & Eul-Bum Lee, 2019. "Using Text Mining to Estimate Schedule Delay Risk of 13 Offshore Oil and Gas EPC Case Studies During the Bidding Process," Energies, MDPI, vol. 12(10), pages 1-25, May.
- Zakari Mustapha & Benjamin Boahene Akomah & Samuel Kwame Ansah, 2023. "Construction Projects Success: Time, Cost, Quality and Safety," International Journal of Research and Innovation in Social Science, International Journal of Research and Innovation in Social Science (IJRISS), vol. 7(9), pages 680-688, September.
- Nyoni, Thabani, 2019. "Cost overrun factors in construction industry: a case of Zimbabwe," MPRA Paper 96788, University Library of Munich, Germany.
- Atle Oglend & Petter Osmundsen & Sindre Lorentzen, 2016.
"Cost Overrun at the Norwegian Continental Shelf: The Element of Surprise,"
CESifo Working Paper Series
5886, CESifo.
- Øglend, Atle & Osmundsen, Petter & Lorentzen, Sindre, 2016. "Cost Overrun at the Norwegian Continental Shelf: The element of surprise," UiS Working Papers in Economics and Finance 2016/3, University of Stavanger.
- Francisco Pinheiro Catalão & Carlos Oliveira Cruz & Joaquim Miranda Sarmento, 2023. "The entanglement of time and cost deviations in public projects," Annals of Public and Cooperative Economics, Wiley Blackwell, vol. 94(1), pages 241-272, March.
- Shahab Shoar & Nicholas Chileshe, 2021. "Exploring the Causes of Design Changes in Building Construction Projects: An Interpretive Structural Modeling Approach," Sustainability, MDPI, vol. 13(17), pages 1-23, August.
- Giuliano Marella & Valentina Antoniucci, 2019. "Time Overrun in Public Works—Evidence from North-East Italy," Sustainability, MDPI, vol. 11(24), pages 1-17, December.
- Osmundsen, Petter & Roll, Kristin Helen, 2016.
"Rig rates and drilling speed: reinforcing effects,"
UiS Working Papers in Economics and Finance
2016/4, University of Stavanger.
- Petter Osmundsen & Kristin Helen Roll, 2016. "Rig Rates and Drilling Speed: Reinforcing Effects," CESifo Working Paper Series 5895, CESifo.
- Temitope Seun Omotayo & Bankole Awuzie & Valerie Kenechukwu Obi & Saheed Ajayi & Lovelin Ifeoma Obi & Oluyomi Osobajo & Adekunle Oke, 2022. "The System Dynamics Analysis of Cost Overrun Causations in UK Rail Projects in a COVID-19 Epidemic Era," SAGE Open, , vol. 12(2), pages 21582440221, May.
- Patrick Uwineza & Jean de Dieu Dushimimana, 2022. "Project Management Practices And Effectiveness Of Private Radio Station’S Projects A Case Of Selected Projects Of Energy Radio, In Musanze District, Rwanda (2017-2020)," Working papers 2022-42-08, Voice of Research.
- Hemanta Doloi & Anil Sawhney & K.C. Iyer, 2012. "Structural equation model for investigating factors affecting delay in Indian construction projects," Construction Management and Economics, Taylor & Francis Journals, vol. 30(10), pages 869-884, October.
- Myung-Hun Kim & Eul-Bum Lee & Han-Suk Choi, 2019. "A Forecast and Mitigation Model of Construction Performance by Assessing Detailed Engineering Maturity at Key Milestones for Offshore EPC Mega-Projects," Sustainability, MDPI, vol. 11(5), pages 1-21, February.
- repec:eur:ejfejr:49 is not listed on IDEAS
- Jin Woo Won & Wooyong Jung & Seung Heon Han & Sungmin Yun & Bonsang Koo, 2019. "What Enables a High-Risk Project to Yield High Return from a Construction Contractor’s Perspective?," Sustainability, MDPI, vol. 11(21), pages 1-17, October.
More about this item
Keywords
Cost control; interview; practice; project control; project management;All these keywords.
Statistics
Access and download statisticsCorrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:taf:conmgt:v:28:y:2010:i:5:p:509-526. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
We have no bibliographic references for this item. You can help adding them by using this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Longhurst (email available below). General contact details of provider: http://www.tandfonline.com/RCME20 .
Please note that corrections may take a couple of weeks to filter through the various RePEc services.