A New Model for Solving Time-Cost-Quality Trade-Off Problems in Construction

Author

Listed:
  • Fang Fu
  • Tao Zhang

Abstract

A poor quality affects project makespan and its total costs negatively, but it can be recovered by repair works during construction. We construct a new non-linear programming model based on the classic multi-mode resource constrained project scheduling problem considering repair works. In order to obtain satisfactory quality without a high increase of project cost, the objective is to minimize total quality cost which consists of the prevention cost and failure cost according to Quality-Cost Analysis. A binary dependent normal distribution function is adopted to describe the activity quality; Cumulative quality is defined to determine whether to initiate repair works, according to the different relationships among activity qualities, namely, the coordinative and precedence relationship. Furthermore, a shuffled frog-leaping algorithm is developed to solve this discrete trade-off problem based on an adaptive serial schedule generation scheme and adjusted activity list. In the program of the algorithm, the frog-leaping progress combines the crossover operator of genetic algorithm and a permutation-based local search. Finally, an example of a construction project for a framed railway overpass is provided to examine the algorithm performance, and it assist in decision making to search for the appropriate makespan and quality threshold with minimal cost.

Suggested Citation

  • Fang Fu & Tao Zhang, 2016. "A New Model for Solving Time-Cost-Quality Trade-Off Problems in Construction," PLOS ONE, Public Library of Science, vol. 11(12), pages 1-15, December.
  • Handle: RePEc:plo:pone00:0167142
    DOI: 10.1371/journal.pone.0167142
    as

    Download full text from publisher

    File URL: https://journals.plos.org/plosone/article?id=10.1371/journal.pone.0167142
    Download Restriction: no

    File URL: https://journals.plos.org/plosone/article/file?id=10.1371/journal.pone.0167142&type=printable
    Download Restriction: no

    File URL: https://libkey.io/10.1371/journal.pone.0167142?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Hong Zhang & Heng Li, 2010. "Multi-objective particle swarm optimization for construction time-cost tradeoff problems," Construction Management and Economics, Taylor & Francis Journals, vol. 28(1), pages 75-88.
    2. Azadeh, A. & Maleki Shoja, B. & Ghanei, S. & Sheikhalishahi, M., 2015. "A multi-objective optimization problem for multi-state series-parallel systems: A two-stage flow-shop manufacturing system," Reliability Engineering and System Safety, Elsevier, vol. 136(C), pages 62-74.
    3. Tiwari, Vikram & Patterson, James H. & Mabert, Vincent A., 2009. "Scheduling projects with heterogeneous resources to meet time and quality objectives," European Journal of Operational Research, Elsevier, vol. 193(3), pages 780-790, March.
    4. Babu, A. J. G. & Suresh, Nalina, 1996. "Project management with time, cost, and quality considerations," European Journal of Operational Research, Elsevier, vol. 88(2), pages 320-327, January.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Öncü Hazir & Gündüz Ulusoy, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," Post-Print hal-02898162, HAL.
    2. Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
    3. Kosztyán, Zsolt T. & Pribojszki-Németh, Anikó & Szalkai, István, 2019. "Hybrid multimode resource-constrained maintenance project scheduling problem," Operations Research Perspectives, Elsevier, vol. 6(C).
    4. Mehrnoosh Zohrehvandi & Shakib Zohrehvandi & Mohammad Khalilzadeh & Maghsoud Amiri & Fariborz Jolai & Edmundas Kazimieras Zavadskas & Jurgita Antucheviciene, 2024. "A Multi-Objective Mathematical Programming Model for Project-Scheduling Optimization Considering Customer Satisfaction in Construction Projects," Mathematics, MDPI, vol. 12(2), pages 1-15, January.
    5. Paraskevopoulos, Dimitris C. & Laporte, Gilbert & Repoussis, Panagiotis P. & Tarantilis, Christos D., 2017. "Resource constrained routing and scheduling: Review and research prospects," European Journal of Operational Research, Elsevier, vol. 263(3), pages 737-754.
    6. Jeunet, Jully & Bou Orm, Mayassa, 2020. "Optimizing temporary work and overtime in the Time Cost Quality Trade-off Problem," European Journal of Operational Research, Elsevier, vol. 284(2), pages 743-761.
    7. C-C Chang & R-S Chen, 2007. "Project advancement and its applications to multi-air-route quality budget allocation," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 58(8), pages 1008-1020, August.
    8. Guanyi Liu & Xuemei Li & Khalid Mehmood Alam, 2023. "Multiple objective immune wolf colony algorithm for solving time-cost-quality trade-off problem," PLOS ONE, Public Library of Science, vol. 18(2), pages 1-29, February.
    9. Qingfeng Meng & Zhen Li & Jianguo Du & Huimin Liu & Xiang Ding, 2019. "Negotiation for Time Optimization in Construction Projects with Competitive and Social Welfare Preferences," Complexity, Hindawi, vol. 2019, pages 1-13, January.
    10. Zsolt T. Kosztyán & István Szalkai, 2020. "Multimode resource-constrained project scheduling in flexible projects," Journal of Global Optimization, Springer, vol. 76(1), pages 211-241, January.
    11. Kerkhove, L.P. & Vanhoucke, M., 2016. "Incentive contract design for projects: The owner׳s perspective," Omega, Elsevier, vol. 62(C), pages 93-114.
    12. Luise-Sophie Hoffmann & Carolin Kellenbrink & Stefan Helber, 2020. "Simultaneous structuring and scheduling of multiple projects with flexible project structures," Journal of Business Economics, Springer, vol. 90(5), pages 679-711, June.
    13. Brucker, Peter & Qu, Rong & Burke, Edmund, 2011. "Personnel scheduling: Models and complexity," European Journal of Operational Research, Elsevier, vol. 210(3), pages 467-473, May.
    14. Lin, Yi-Kuei & Huang, Ding-Hsiang, 2020. "Reliability analysis for a hybrid flow shop with due date consideration," Reliability Engineering and System Safety, Elsevier, vol. 199(C).
    15. Perrone, G. & Roma, P. & Lo Nigro, G., 2010. "Designing multi-attribute auctions for engineering services procurement in new product development in the automotive context," International Journal of Production Economics, Elsevier, vol. 124(1), pages 20-31, March.
    16. Kellenbrink, Carolin & Helber, Stefan, 2015. "Scheduling resource-constrained projects with a flexible project structure," European Journal of Operational Research, Elsevier, vol. 246(2), pages 379-391.
    17. Asadabadi, Mehdi Rajabi & Zwikael, Ofer, 2021. "Integrating risk into estimations of project activities' time and cost: A stratified approach," European Journal of Operational Research, Elsevier, vol. 291(2), pages 482-490.
    18. Weglarz, Jan & Józefowska, Joanna & Mika, Marek & Waligóra, Grzegorz, 2011. "Project scheduling with finite or infinite number of activity processing modes - A survey," European Journal of Operational Research, Elsevier, vol. 208(3), pages 177-205, February.
    19. Osama Mohamed ElSahly & Salma Ahmed & Akmal Abdelfatah, 2023. "Systematic Review of the Time-Cost Optimization Models in Construction Management," Sustainability, MDPI, vol. 15(6), pages 1-20, March.
    20. De Bruecker, Philippe & Van den Bergh, Jorne & Beliën, Jeroen & Demeulemeester, Erik, 2015. "Workforce planning incorporating skills: State of the art," European Journal of Operational Research, Elsevier, vol. 243(1), pages 1-16.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:plo:pone00:0167142. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: plosone (email available below). General contact details of provider: https://journals.plos.org/plosone/ .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.