Rescheduling Plan Optimization of Underground Mine Haulage Equipment Based on Random Breakdown Simulation

Author

Listed:
  • Ning Li

    (School of Resource and Environment Engineering, Wuhan University of Technology, Wuhan 430070, China
    Hubei Key Laboratory of Mineral Resources Processing and Environment, Wuhan 430070, China)

  • Shuzhao Feng

    (School of Resource and Environment Engineering, Wuhan University of Technology, Wuhan 430070, China)

  • Tao Lei

    (School of Resource and Environment Engineering, Wuhan University of Technology, Wuhan 430070, China
    Hubei Key Laboratory of Mineral Resources Processing and Environment, Wuhan 430070, China)

  • Haiwang Ye

    (School of Resource and Environment Engineering, Wuhan University of Technology, Wuhan 430070, China)

  • Qizhou Wang

    (School of Resource and Environment Engineering, Wuhan University of Technology, Wuhan 430070, China)

  • Liguan Wang

    (School of Resource and Safety Engineering, Central South University, Changsha 410083, China)

  • Mingtao Jia

    (School of Resource and Safety Engineering, Central South University, Changsha 410083, China)

Abstract

Due to production space and operating environment requirements, mine production equipment often breaks down, seriously affecting the mine’s production schedule. To ensure the smooth completion of the haulage operation plan under abnormal conditions, a model of the haulage equipment rescheduling plan based on the random simulation of equipment breakdowns is established in this paper. The model aims to accomplish both the maximum completion rate of the original mining plan and the minimum fluctuation of the ore grade during the rescheduling period. This model is optimized by improving the wolf colony algorithm and changing the location update formula of the individuals in the wolf colony. Then, the optimal model solution can be used to optimize the rescheduling of the haulage plan by considering equipment breakdowns. The application of the proposed method in an underground mine revealed that the completion rate of the mine’s daily mining plan reached 83.40% without increasing the amount of equipment, while the ore quality remained stable. Moreover, the improved optimization algorithm converged quickly and was characterized by high robustness.

Suggested Citation

  • Ning Li & Shuzhao Feng & Tao Lei & Haiwang Ye & Qizhou Wang & Liguan Wang & Mingtao Jia, 2022. "Rescheduling Plan Optimization of Underground Mine Haulage Equipment Based on Random Breakdown Simulation," Sustainability, MDPI, vol. 14(6), pages 1-18, March.
  • Handle: RePEc:gam:jsusta:v:14:y:2022:i:6:p:3448-:d:771820
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/2071-1050/14/6/3448/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/2071-1050/14/6/3448/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Al-Hinai, Nasr & ElMekkawy, T.Y., 2011. "Robust and stable flexible job shop scheduling with random machine breakdowns using a hybrid genetic algorithm," International Journal of Production Economics, Elsevier, vol. 132(2), pages 279-291, August.
    2. Foroughi, Sorayya & Hamidi, Jafar Khademi & Monjezi, Masoud & Nehring, Micah, 2019. "The integrated optimization of underground stope layout designing and production scheduling incorporating a non-dominated sorting genetic algorithm (NSGA-II)," Resources Policy, Elsevier, vol. 63(C), pages 1-1.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Dževdet Halilović & Miloš Gligorić & Zoran Gligorić & Dragan Pamučar, 2023. "An Underground Mine Ore Pass System Optimization via Fuzzy 0–1 Linear Programming with Novel Torricelli–Simpson Ranking Function," Mathematics, MDPI, vol. 11(13), pages 1-35, June.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Shichang Xiao & Zigao Wu & Hongyan Dui, 2022. "Resilience-Based Surrogate Robustness Measure and Optimization Method for Robust Job-Shop Scheduling," Mathematics, MDPI, vol. 10(21), pages 1-22, October.
    2. Jose L. Andrade-Pineda & David Canca & Pedro L. Gonzalez-R & M. Calle, 2020. "Scheduling a dual-resource flexible job shop with makespan and due date-related criteria," Annals of Operations Research, Springer, vol. 291(1), pages 5-35, August.
    3. Zigao Wu & Shaohua Yu & Tiancheng Li, 2019. "A Meta-Model-Based Multi-Objective Evolutionary Approach to Robust Job Shop Scheduling," Mathematics, MDPI, vol. 7(6), pages 1-19, June.
    4. Esmaeili, Ahmadreza & Hamidi, Jafar Khademi & Mousavi, Amin, 2023. "Determination of sublevel stoping layout using a network flow algorithm and the MRMR classification system," Resources Policy, Elsevier, vol. 80(C).
    5. Constantin Waubert de Puiseau & Richard Meyes & Tobias Meisen, 2022. "On reliability of reinforcement learning based production scheduling systems: a comparative survey," Journal of Intelligent Manufacturing, Springer, vol. 33(4), pages 911-927, April.
    6. Zhang, Rui & Song, Shiji & Wu, Cheng, 2013. "A hybrid artificial bee colony algorithm for the job shop scheduling problem," International Journal of Production Economics, Elsevier, vol. 141(1), pages 167-178.
    7. Iwona Paprocka & Bożena Skołud, 2017. "A hybrid multi-objective immune algorithm for predictive and reactive scheduling," Journal of Scheduling, Springer, vol. 20(2), pages 165-182, April.
    8. Zhang, Rui & Chang, Pei-Chann & Wu, Cheng, 2013. "A hybrid genetic algorithm for the job shop scheduling problem with practical considerations for manufacturing costs: Investigations motivated by vehicle production," International Journal of Production Economics, Elsevier, vol. 145(1), pages 38-52.
    9. Yiyi Xu & M’hammed Sahnoun & Fouad Ben Abdelaziz & David Baudry, 2022. "A simulated multi-objective model for flexible job shop transportation scheduling," Annals of Operations Research, Springer, vol. 311(2), pages 899-920, April.
    10. Che, Ada & Feng, Jianguang & Chen, Haoxun & Chu, Chengbin, 2015. "Robust optimization for the cyclic hoist scheduling problem," European Journal of Operational Research, Elsevier, vol. 240(3), pages 627-636.
    11. Shichang Xiao & Shudong Sun & Jionghua (Judy) Jin, 2017. "Surrogate Measures for the Robust Scheduling of Stochastic Job Shop Scheduling Problems," Energies, MDPI, vol. 10(4), pages 1-26, April.
    12. Akshay Chowdu & Peter Nesbitt & Andrea Brickey & Alexandra M. Newman, 2022. "Operations Research in Underground Mine Planning: A Review," Interfaces, INFORMS, vol. 52(2), pages 109-132, March.
    13. Cheng, T.C.E. & Wu, Chin-Chia & Chen, Juei-Chao & Wu, Wen-Hsiang & Cheng, Shuenn-Ren, 2013. "Two-machine flowshop scheduling with a truncated learning function to minimize the makespan," International Journal of Production Economics, Elsevier, vol. 141(1), pages 79-86.
    14. Furtado e Faria, Matheus & Dimitrakopoulos, Roussos & Lopes Pinto, Cláudio Lúcio, 2022. "Integrated stochastic optimization of stope design and long-term underground mine production scheduling," Resources Policy, Elsevier, vol. 78(C).
    15. Siyu Tu & Mingtao Jia & Liguan Wang & Shuzhao Feng & Shuang Huang, 2022. "A Multi-Equipment Task Assignment Model for the Horizontal Stripe Pre-Cut Mining Method," Sustainability, MDPI, vol. 14(24), pages 1-18, December.
    16. Li, Guo & Li, Na & Sambandam, Narayanasamy & Sethi, Suresh P. & Zhang, Faping, 2018. "Flow shop scheduling with jobs arriving at different times," International Journal of Production Economics, Elsevier, vol. 206(C), pages 250-260.
    17. Sotoudeh, Farzad & Nehring, Micah & Kizil, Mehmet & Knights, Peter & Mousavi, Amin, 2020. "Production scheduling optimisation for sublevel stoping mines using mathematical programming: A review of literature and future directions," Resources Policy, Elsevier, vol. 68(C).
    18. Xiong, Jian & Xing, Li-ning & Chen, Ying-wu, 2013. "Robust scheduling for multi-objective flexible job-shop problems with random machine breakdowns," International Journal of Production Economics, Elsevier, vol. 141(1), pages 112-126.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jsusta:v:14:y:2022:i:6:p:3448-:d:771820. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.