Integrated stochastic optimization of stope design and long-term underground mine production scheduling

Author

Listed:
  • Furtado e Faria, Matheus
  • Dimitrakopoulos, Roussos
  • Lopes Pinto, Cláudio Lúcio

Abstract

In the commonly used underground mine planning framework, mine design is first established and is the main input for the subsequent long-term mine production scheduling optimization. This sequential optimization approach cannot, therefore, capture the synergies between the involved planning steps, generating solutions that depart substantially from a global optimum. In addition, traditional underground mine planning methods for stope design and life-of-mine production scheduling are deterministic and are based on a single estimated orebody model. As a result, the uncertainty and variability in grades and material types are not incorporated into the optimization process, resulting in designs that misrepresent all high-, medium- and low-grade stoping volumes and production schedules with misleading forecasts. A two-stage stochastic integer program (SIP) for integrated optimization of stope and development network designs and an underground mine production scheduling are proposed for the sublevel open stoping mining method under grade uncertainty and variability, quantified by a set of geostatistical simulations of the mineral deposit considered. Assuming a mine is accessed through a shaft, the model defines a schedule of levels and stopes, which aims to maximize the discounted revenues, minimize development costs, and manage the risk of not meeting production targets, while satisfying geotechnical constraints. The practical aspects of the proposed method are presented through an application at an underground gold mine. A comparison with the stepwise framework, where the stope design is input to a subsequent optimization of the production schedule, shows that the proposed approach provides a physically different design and production schedule with an 11% higher net present value (NPV) and a life-of-mine that is two years shorter, affirming the advantages of the integrated optimization process.

Suggested Citation

  • Furtado e Faria, Matheus & Dimitrakopoulos, Roussos & Lopes Pinto, Cláudio Lúcio, 2022. "Integrated stochastic optimization of stope design and long-term underground mine production scheduling," Resources Policy, Elsevier, vol. 78(C).
  • Handle: RePEc:eee:jrpoli:v:78:y:2022:i:c:s0301420722003622
    DOI: 10.1016/j.resourpol.2022.102918
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0301420722003622
    Download Restriction: Full text for ScienceDirect subscribers only

    File URL: https://libkey.io/10.1016/j.resourpol.2022.102918?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Christopher Alford & Marcus Brazil & David H. Lee, 2007. "Optimisation in Underground Mining," International Series in Operations Research & Management Science, in: Andres Weintraub & Carlos Romero & Trond Bjørndal & Rafael Epstein & Jaime Miranda (ed.), Handbook Of Operations Research In Natural Resources, chapter 0, pages 561-577, Springer.
    2. Dónal O’Sullivan & Alexandra Newman, 2014. "Extraction and Backfill Scheduling in a Complex Underground Mine," Interfaces, INFORMS, vol. 44(2), pages 204-221, April.
    3. W. Matthew Carlyle & B. Curtis Eaves, 2001. "Underground Planning at Stillwater Mining Company," Interfaces, INFORMS, vol. 31(4), pages 50-60, August.
    4. Mark Kuchta & Alexandra Newman & Erkan Topal, 2004. "Implementing a Production Schedule at LKAB's Kiruna Mine," Interfaces, INFORMS, vol. 34(2), pages 124-134, April.
    5. Montiel, Luis & Dimitrakopoulos, Roussos, 2015. "Optimizing mining complexes with multiple processing and transportation alternatives: An uncertainty-based approach," European Journal of Operational Research, Elsevier, vol. 247(1), pages 166-178.
    6. Luis Montiel & Roussos Dimitrakopoulos, 2017. "A heuristic approach for the stochastic optimization of mine production schedules," Journal of Heuristics, Springer, vol. 23(5), pages 397-415, October.
    7. Sotoudeh, Farzad & Nehring, Micah & Kizil, Mehmet & Knights, Peter & Mousavi, Amin, 2020. "Production scheduling optimisation for sublevel stoping mines using mathematical programming: A review of literature and future directions," Resources Policy, Elsevier, vol. 68(C).
    8. Foroughi, Sorayya & Hamidi, Jafar Khademi & Monjezi, Masoud & Nehring, Micah, 2019. "The integrated optimization of underground stope layout designing and production scheduling incorporating a non-dominated sorting genetic algorithm (NSGA-II)," Resources Policy, Elsevier, vol. 63(C), pages 1-1.
    9. Nesbitt, Peter & Blake, Lewis R. & Lamas, Patricio & Goycoolea, Marcos & Pagnoncelli, Bernardo K. & Newman, Alexandra & Brickey, Andrea, 2021. "Underground mine scheduling under uncertainty," European Journal of Operational Research, Elsevier, vol. 294(1), pages 340-352.
    10. Nhleko, AS & Tholana, T. & Neingo, PN, 2018. "A review of underground stope boundary optimization algorithms," Resources Policy, Elsevier, vol. 56(C), pages 59-69.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Chimunhu, Prosper & Topal, Erkan & Ajak, Ajak Duany & Asad, Waqar, 2022. "A review of machine learning applications for underground mine planning and scheduling," Resources Policy, Elsevier, vol. 77(C).
    2. Lorenzo Reus & Mathias Belbèze & Hans Feddersen & Enrique Rubio, 2018. "Extraction Planning Under Capacity Uncertainty at the Chuquicamata Underground Mine," Interfaces, INFORMS, vol. 48(6), pages 543-555, November.
    3. Akshay Chowdu & Peter Nesbitt & Andrea Brickey & Alexandra M. Newman, 2022. "Operations Research in Underground Mine Planning: A Review," Interfaces, INFORMS, vol. 52(2), pages 109-132, March.
    4. Barry King & Alexandra Newman, 2018. "Optimizing the Cutoff Grade for an Operational Underground Mine," Interfaces, INFORMS, vol. 48(4), pages 357-371, August.
    5. Siyu Tu & Mingtao Jia & Liguan Wang & Shuzhao Feng & Shuang Huang, 2022. "A Multi-Equipment Task Assignment Model for the Horizontal Stripe Pre-Cut Mining Method," Sustainability, MDPI, vol. 14(24), pages 1-18, December.
    6. Rafael Epstein & Marcel Goic & Andrés Weintraub & Jaime Catalán & Pablo Santibáñez & Rodolfo Urrutia & Raúl Cancino & Sergio Gaete & Augusto Aguayo & Felipe Caro, 2012. "Optimizing Long-Term Production Plans in Underground and Open-Pit Copper Mines," Operations Research, INFORMS, vol. 60(1), pages 4-17, February.
    7. Gonzalo Muñoz & Daniel Espinoza & Marcos Goycoolea & Eduardo Moreno & Maurice Queyranne & Orlando Rivera Letelier, 2018. "A study of the Bienstock–Zuckerberg algorithm: applications in mining and resource constrained project scheduling," Computational Optimization and Applications, Springer, vol. 69(2), pages 501-534, March.
    8. Nesbitt, Peter & Blake, Lewis R. & Lamas, Patricio & Goycoolea, Marcos & Pagnoncelli, Bernardo K. & Newman, Alexandra & Brickey, Andrea, 2021. "Underground mine scheduling under uncertainty," European Journal of Operational Research, Elsevier, vol. 294(1), pages 340-352.
    9. Del Castillo, M. Fernanda & Dimitrakopoulos, Roussos, 2019. "Dynamically optimizing the strategic plan of mining complexes under supply uncertainty," Resources Policy, Elsevier, vol. 60(C), pages 83-93.
    10. Foroughi, Sorayya & Hamidi, Jafar Khademi & Monjezi, Masoud & Nehring, Micah, 2019. "The integrated optimization of underground stope layout designing and production scheduling incorporating a non-dominated sorting genetic algorithm (NSGA-II)," Resources Policy, Elsevier, vol. 63(C), pages 1-1.
    11. Yifei Zhao & Jianhong Chen & Shan Yang & Yi Chen, 2022. "Mining Plan Optimization of Multi-Metal Underground Mine Based on Adaptive Hybrid Mutation PSO Algorithm," Mathematics, MDPI, vol. 10(14), pages 1-20, July.
    12. Sotoudeh, Farzad & Nehring, Micah & Kizil, Mehmet & Knights, Peter & Mousavi, Amin, 2020. "Production scheduling optimisation for sublevel stoping mines using mathematical programming: A review of literature and future directions," Resources Policy, Elsevier, vol. 68(C).
    13. Mousavi, Amin & Sellers, Ewan, 2019. "Optimisation of production planning for an innovative hybrid underground mining method," Resources Policy, Elsevier, vol. 62(C), pages 184-192.
    14. Ashish Kumar & Roussos Dimitrakopoulos & Marco Maulen, 2020. "Adaptive self-learning mechanisms for updating short-term production decisions in an industrial mining complex," Journal of Intelligent Manufacturing, Springer, vol. 31(7), pages 1795-1811, October.
    15. O’Sullivan, Dónal & Newman, Alexandra, 2015. "Optimization-based heuristics for underground mine scheduling," European Journal of Operational Research, Elsevier, vol. 241(1), pages 248-259.
    16. Chung, Joyce & Asad, Mohammad Waqar Ali & Topal, Erkan, 2022. "Timing of transition from open-pit to underground mining: A simultaneous optimisation model for open-pit and underground mine production schedules," Resources Policy, Elsevier, vol. 77(C).
    17. Friedrich-Wilhelm Wellmer & Roland W. Scholz, 2018. "What Is the Optimal and Sustainable Lifetime of a Mine?," Sustainability, MDPI, vol. 10(2), pages 1-22, February.
    18. King, Barry & Goycoolea, Marcos & Newman, A., 2017. "Optimizing the open pit-to-underground mining transition," European Journal of Operational Research, Elsevier, vol. 257(1), pages 297-309.
    19. Esmaeili, Ahmadreza & Hamidi, Jafar Khademi & Mousavi, Amin, 2023. "Determination of sublevel stoping layout using a network flow algorithm and the MRMR classification system," Resources Policy, Elsevier, vol. 80(C).
    20. Mark Kuchta & Alexandra Newman & Erkan Topal, 2004. "Implementing a Production Schedule at LKAB's Kiruna Mine," Interfaces, INFORMS, vol. 34(2), pages 124-134, April.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:jrpoli:v:78:y:2022:i:c:s0301420722003622. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/inca/30467 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.