IDEAS home Printed from https://ideas.repec.org/a/gam/jsusta/v14y2022i22p14927-d969890.html
   My bibliography  Save this article

Detection and In-Depth Analysis of Causes of Delay in Construction Projects: Synergy between Machine Learning and Expert Knowledge

Author

Listed:
  • Marija Z. Ivanović

    (Department of Construction Project Management, Faculty of Civil Engineering, University of Belgrade, 11000 Belgrade, Serbia)

  • Đorđe Nedeljković

    (Department of Construction Project Management, Faculty of Civil Engineering, University of Belgrade, 11000 Belgrade, Serbia)

  • Zoran Stojadinović

    (Department of Construction Project Management, Faculty of Civil Engineering, University of Belgrade, 11000 Belgrade, Serbia)

  • Dejan Marinković

    (Department of Construction Project Management, Faculty of Civil Engineering, University of Belgrade, 11000 Belgrade, Serbia)

  • Nenad Ivanišević

    (Department of Construction Project Management, Faculty of Civil Engineering, University of Belgrade, 11000 Belgrade, Serbia)

  • Nevena Simić

    (Department of Construction Project Management, Faculty of Civil Engineering, University of Belgrade, 11000 Belgrade, Serbia)

Abstract

Due to numerous reasons, construction projects often fail to achieve the planned duration. Detecting causes of delays (CoD) is the first step in eliminating or mitigating potential delays in future projects. The goal of research is unbiased CoD detection at a single project level, with the ultimate goal to discover the root causes of delay. The existing approach is based on expert knowledge which is used to create CoD lists for projects in general or groups of similar projects. When applied to a single project, it is burdened with bias, as shown on a case project returning low Spearman Rank correlation values. This research introduces a Delay Root causes Extraction and Analysis Model—DREAM. The proposed model combines expert knowledge, machine learning techniques, and Minutes of Meetings (MoM) as an unutilized extensive source of information. In the first phase, DREAM outputs a CoD list based on occurring frequency in MoM with satisfactory recall values, significantly reducing expert-induced subjectivism. In the second phase, enabled by MoM dates, DREAM adds another dimension to delay analysis—temporal CoD distribution. By analyzing corresponding informative charts, experts can understand the nature of delays and discover the root CoD, allowing intelligent decision making on future projects.

Suggested Citation

  • Marija Z. Ivanović & Đorđe Nedeljković & Zoran Stojadinović & Dejan Marinković & Nenad Ivanišević & Nevena Simić, 2022. "Detection and In-Depth Analysis of Causes of Delay in Construction Projects: Synergy between Machine Learning and Expert Knowledge," Sustainability, MDPI, vol. 14(22), pages 1-23, November.
  • Handle: RePEc:gam:jsusta:v:14:y:2022:i:22:p:14927-:d:969890
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/2071-1050/14/22/14927/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/2071-1050/14/22/14927/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Taleb, Nassim Nicholas, 2007. "Black Swans and the Domains of Statistics," The American Statistician, American Statistical Association, vol. 61, pages 198-200, August.
    2. Nikolić, Ana & Roumboutsos, Athena & Stanković, Jelena Ćirilović & Mladenović, Goran, 2020. "Has the latest global financial crisis changed the way road public-private partnerships are funded? A comparison of Europe and Latin America," Utilities Policy, Elsevier, vol. 64(C).
    3. Zaher Mundher Yaseen & Zainab Hasan Ali & Sinan Q. Salih & Nadhir Al-Ansari, 2020. "Prediction of Risk Delay in Construction Projects Using a Hybrid Artificial Intelligence Model," Sustainability, MDPI, vol. 12(4), pages 1-14, February.
    4. Peter Kaming & Paul Olomolaiye & Gary Holt & Frank Harris, 1997. "Factors influencing construction time and cost overruns on high-rise projects in Indonesia," Construction Management and Economics, Taylor & Francis Journals, vol. 15(1), pages 83-94.
    5. Paul Parsons & Kamran Sedig, 2014. "Adjustable properties of visual representations: Improving the quality of human-information interaction," Journal of the Association for Information Science & Technology, Association for Information Science & Technology, vol. 65(3), pages 455-482, March.
    6. Edwin Thomas Banobi & Wooyong Jung, 2019. "Causes and Mitigation Strategies of Delay in Power Construction Projects: Gaps between Owners and Contractors in Successful and Unsuccessful Projects," Sustainability, MDPI, vol. 11(21), pages 1-16, October.
    7. Su Jin Choi & So Won Choi & Jong Hyun Kim & Eul-Bum Lee, 2021. "AI and Text-Mining Applications for Analyzing Contractor’s Risk in Invitation to Bid (ITB) and Contracts for Engineering Procurement and Construction (EPC) Projects," Energies, MDPI, vol. 14(15), pages 1-28, July.
    8. Alessandra Montenegro & Marina Dobrota & Marija Todorovic & Teodora Slavinski & Vladimir Obradovic, 2021. "Impact of Construction Project Managers’ Emotional Intelligence on Project Success," Sustainability, MDPI, vol. 13(19), pages 1-18, September.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Al-Bataineh Fuad & Khatatbeh Ahmed Ali & Alzubi Yazan, 2024. "Unsupervised machine learning for identifying key risk factors contributing to construction delays," Organization, Technology and Management in Construction, Sciendo, vol. 16(1), pages 170-185.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Carlos Araújo-Rey & Miguel A. Sebastián, 2021. "An Approach to the Analysis of Causes of Delays in Industrial Construction Projects through Planning and Statistical Computing," Sustainability, MDPI, vol. 13(7), pages 1-21, April.
    2. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2018. "Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project," Sustainability, MDPI, vol. 10(12), pages 1-18, December.
    3. Parrini, Alessandro, 2013. "Importance Sampling for Portfolio Credit Risk in Factor Copula Models," MPRA Paper 103745, University Library of Munich, Germany.
    4. Child, K. & Desta, G. & Douthwaite, B. & Haileslassie, Amare & van Rooyen, A. & Tamene, L. & Uhlenbrook, Stefan, 2021. "Impact tracking: a practitioner-developed approach to scaling agricultural innovation in Ethiopia," IWMI Books, Reports H050789, International Water Management Institute.
    5. Hendry, David F. & Mizon, Grayham E., 2014. "Unpredictability in economic analysis, econometric modeling and forecasting," Journal of Econometrics, Elsevier, vol. 182(1), pages 186-195.
    6. Safi Ullah & Muhammad Siddiq & Deng Xiaopeng & Sun Jun & Diana R. Anbar & Chiemela Victor Amaechi & Muhammad Waqas Ashraf, 2025. "Identifying the Most Effective Delaying Factors Using FCEM-AHP: A Case Study of Pakistan’s Construction Industry," Journal of the Knowledge Economy, Springer;Portland International Center for Management of Engineering and Technology (PICMET), vol. 16(3), pages 13589-13623, September.
    7. Taleb, Nassim Nicholas, 2009. "Errors, robustness, and the fourth quadrant," International Journal of Forecasting, Elsevier, vol. 25(4), pages 744-759, October.
    8. Christopher Crawford, G. & McKelvey, Bill & Lichtenstein, Benyamin B., 2014. "The empirical reality of entrepreneurship: How power law distributed outcomes call for new theory and method," Journal of Business Venturing Insights, Elsevier, vol. 1, pages 3-7.
    9. Ori Plonsky & Yefim Roth & Ido Erev, 2021. "Underweighting of rare events in social interactions and its implications to the design of voluntary health applications," Judgment and Decision Making, Society for Judgment and Decision Making, vol. 16(2), pages 267-289, March.
    10. Schotter, Andreas P.J. & Buchel, Olha & Vashchilko (Lukoianova), Tatiana, 2018. "Interactive visualization for research contextualization in international business," Journal of World Business, Elsevier, vol. 53(3), pages 356-372.
    11. Khalid Alshehhi & Ali Cheaitou & Hamad Rashid, 2025. "Investigating risk elements and critical success factors for AI procurement projects in the public sector: a qualitative approach based on UAE public organisations," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 16(2), pages 446-467, February.
    12. Kristina Galjanić & Ivan Marović & Tomaš Hanak, 2023. "Performance Measurement Framework for Prediction and Management of Construction Investments," Sustainability, MDPI, vol. 15(18), pages 1-20, September.
    13. Boda Liu & Bin Yang & Jianzhuang Xiao & Dayu Zhu & Binghan Zhang & Zhichen Wang & Miaosi Dong, 2021. "Review of Optimization Dynamically Applied in the Construction and the Application Potential of ICT," Sustainability, MDPI, vol. 13(10), pages 1-18, May.
    14. Araz Taeihagh, 2017. "Network-centric policy design," Policy Sciences, Springer;Society of Policy Sciences, vol. 50(2), pages 317-338, June.
    15. repec:ces:ifodic:v:10:y:2012:i:1:p:03-08 is not listed on IDEAS
    16. repec:zbw:rwimat:062 is not listed on IDEAS
    17. So-Won Choi & Eul-Bum Lee, 2022. "Contractor’s Risk Analysis of Engineering Procurement and Construction (EPC) Contracts Using Ontological Semantic Model and Bi-Long Short-Term Memory (LSTM) Technology," Sustainability, MDPI, vol. 14(11), pages 1-32, June.
    18. Shagun Tyagi & Ashulekha Gupta & Nabila Ansari, 2024. "Adoption and perception of banking customers towards green mode of banking: a demonstration of structural equation modelling," Journal of Financial Services Marketing, Palgrave Macmillan, vol. 29(3), pages 826-842, September.
    19. repec:cup:judgdm:v:16:y:2021:i:2:p:267-289 is not listed on IDEAS
    20. Miranda Sarmento, J.J. & Renneboog, Luc, 2017. "Cost overruns in public sector investment projects," Other publications TiSEM 51799a3e-4c78-4dbd-b330-b, Tilburg University, School of Economics and Management.
    21. Min-Ji Park & Eul-Bum Lee & Seung-Yeab Lee & Jong-Hyun Kim, 2021. "A Digitalized Design Risk Analysis Tool with Machine-Learning Algorithm for EPC Contractor’s Technical Specifications Assessment on Bidding," Energies, MDPI, vol. 14(18), pages 1-31, September.
    22. Nur Fatin Syazwani Abu Bakar* & Syuhaida Ismail & Rohayah Che Amat & Serdar Durdyev, 2018. "Sustainable Construction in Malaysian Mixed Development Projects: The Barriers and Critical Success Factors," The Journal of Social Sciences Research, Academic Research Publishing Group, pages 885-892:6.
    23. repec:ces:ifodic:v:10:y:2012:i:1:p:18174973 is not listed on IDEAS
    24. Alan Gaignebet & Vincent Chapurlat & Gregory Zacharewicz & Victor Richet & Robert Plana, 2021. "A Model Based System Commissioning Approach for Nuclear Facilities," Sustainability, MDPI, vol. 13(19), pages 1-21, September.

    More about this item

    Keywords

    ;
    ;
    ;
    ;
    ;
    ;

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jsusta:v:14:y:2022:i:22:p:14927-:d:969890. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.