A computer application for a bus body assembly line using Genetic Algorithms
Author
Abstract
Suggested Citation
DOI: 10.1016/j.ijpe.2012.06.026
Download full text from publisher
As the access to this document is restricted, you may want to search for a different version of it.
References listed on IDEAS
- Giard, Vincent & Jeunet, Jully, 2010. "Optimal sequencing of mixed models with sequence-dependent setups and utility workers on an assembly line," International Journal of Production Economics, Elsevier, vol. 123(2), pages 290-300, February.
- repec:dau:papers:123456789/2861 is not listed on IDEAS
- Böttcher, Jan & Drexl, A. & Kolisch, R. & Salewski, F., 1999. "Project scheduling under partially renewable resource constraints," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 345, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
- Kolisch, Rainer, 1996. "Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation," European Journal of Operational Research, Elsevier, vol. 90(2), pages 320-333, April.
- Lova, Antonio & Tormos, Pilar & Cervantes, Mariamar & Barber, Federico, 2009. "An efficient hybrid genetic algorithm for scheduling projects with resource constraints and multiple execution modes," International Journal of Production Economics, Elsevier, vol. 117(2), pages 302-316, February.
- Gonçalves, J.F. & Mendes, J.J.M. & Resende, M.G.C., 2008. "A genetic algorithm for the resource constrained multi-project scheduling problem," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1171-1190, September.
- Hartmann, Sonke & Kolisch, Rainer, 2000. "Experimental evaluation of state-of-the-art heuristics for the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 127(2), pages 394-407, December.
- Christofides, Nicos & Alvarez-Valdes, R. & Tamarit, J. M., 1987. "Project scheduling with resource constraints: A branch and bound approach," European Journal of Operational Research, Elsevier, vol. 29(3), pages 262-273, June.
- Hartmann, Sönke & Kolisch, R., 2000. "Experimental evaluation of state-of-the-art heuristics for the resource-constrained project scheduling problem," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 11180, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
- Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
- Antonio Lova & Pilar Tormos, 2001. "Analysis of Scheduling Schemes and Heuristic Rules Performance in Resource-Constrained Multiproject Scheduling," Annals of Operations Research, Springer, vol. 102(1), pages 263-286, February.
- Ding, Fong-Yuen & Zhu, Jin & Sun, Hui, 2006. "Comparing two weighted approaches for sequencing mixed-model assembly lines with multiple objectives," International Journal of Production Economics, Elsevier, vol. 102(1), pages 108-131, July.
- Browning, Tyson R. & Yassine, Ali A., 2010. "Resource-constrained multi-project scheduling: Priority rule performance revisited," International Journal of Production Economics, Elsevier, vol. 126(2), pages 212-228, August.
- Drezet, L.-E. & Billaut, J.-C., 2008. "A project scheduling problem with labour constraints and time-dependent activities requirements," International Journal of Production Economics, Elsevier, vol. 112(1), pages 217-225, March.
- Boysen, Nils & Fliedner, Malte & Scholl, Armin, 2009.
"Sequencing mixed-model assembly lines: Survey, classification and model critique,"
European Journal of Operational Research, Elsevier, vol. 192(2), pages 349-373, January.
- Nils Boysen & Malte Fliedner & Armin Scholl, 2007. "Sequencing mixed-model assembly lines: Survey, classification and model critique," Jena Research Papers in Business and Economics - Working and Discussion Papers (Expired!) 02/2007, Friedrich-Schiller-University Jena, School of Economics and Business Administration.
- Alvarez-Valdes, R. & Crespo, E. & Tamarit, J.M. & Villa, F., 2008. "GRASP and path relinking for project scheduling under partially renewable resources," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1153-1170, September.
- Jan Böttcher & Andreas Drexl & Rainer Kolisch & Frank Salewski, 1999. "Project Scheduling Under Partially Renewable Resource Constraints," Management Science, INFORMS, vol. 45(4), pages 543-559, April.
- Vo[ss], Stefan & Witt, Andreas, 2007. "Hybrid flow shop scheduling as a multi-mode multi-project scheduling problem with batching requirements: A real-world application," International Journal of Production Economics, Elsevier, vol. 105(2), pages 445-458, February.
- Lambrechts, Olivier & Demeulemeester, Erik & Herroelen, Willy, 2008. "A tabu search procedure for developing robust predictive project schedules," International Journal of Production Economics, Elsevier, vol. 111(2), pages 493-508, February.
- Heilmann, Roland, 2003. "A branch-and-bound procedure for the multi-mode resource-constrained project scheduling problem with minimum and maximum time lags," European Journal of Operational Research, Elsevier, vol. 144(2), pages 348-365, January.
- Elloumi, Sonda & Fortemps, Philippe, 2010. "A hybrid rank-based evolutionary algorithm applied to multi-mode resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 205(1), pages 31-41, August.
- Jin, Mingzhou & Luo, Yi & Eksioglu, Sandra D., 2008. "Integration of production sequencing and outbound logistics in the automotive industry," International Journal of Production Economics, Elsevier, vol. 113(2), pages 766-774, June.
- Mohanty, R. P. & Siddiq, M. K., 1989. "Multiple projects -- Multiple resources constrained scheduling: A multiobjective analysis," Engineering Costs and Production Economics, Elsevier, vol. 18(1), pages 83-92, October.
- Banaszak, Z.A. & Zaremba, M.B. & Muszynski, W., 2009. "Constraint programming for project-driven manufacturing," International Journal of Production Economics, Elsevier, vol. 120(2), pages 463-475, August.
- Gagne, Caroline & Gravel, Marc & Price, Wilson L., 2006. "Solving real car sequencing problems with ant colony optimization," European Journal of Operational Research, Elsevier, vol. 174(3), pages 1427-1448, November.
Citations
Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
Cited by:
- Piran, Fabio Antonio Sartori & Lacerda, Daniel Pacheco & Camargo, Luis Felipe Riehs & Viero, Carlos Frederico & Dresch, Aline & Cauchick-Miguel, Paulo Augusto, 2016. "Product modularization and effects on efficiency: An analysis of a bus manufacturer using data envelopment analysis (DEA)," International Journal of Production Economics, Elsevier, vol. 182(C), pages 1-13.
- Barbosa, Luziane Machado & Lacerda, Daniel Pacheco & Piran, Fabio Antonio Sartori & Dresch, Aline, 2017. "Exploratory analysis of the variables prevailing on the effects of product modularization on production volume and efficiency," International Journal of Production Economics, Elsevier, vol. 193(C), pages 677-690.
Most related items
These are the items that most often cite the same works as this one and are cited by the same works as this one.- Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
- Hartmann, Sönke & Briskorn, Dirk, 2008. "A survey of variants and extensions of the resource-constrained project scheduling problem," Working Paper Series 02/2008, Hamburg School of Business Administration (HSBA).
- Weglarz, Jan & Józefowska, Joanna & Mika, Marek & Waligóra, Grzegorz, 2011. "Project scheduling with finite or infinite number of activity processing modes - A survey," European Journal of Operational Research, Elsevier, vol. 208(3), pages 177-205, February.
- Abdollah Arasteh, 2020. "Considering Project Management Activities for Engineering Design Groups," SN Operations Research Forum, Springer, vol. 1(4), pages 1-29, December.
- Kolisch, R. & Padman, R., 2001.
"An integrated survey of deterministic project scheduling,"
Omega, Elsevier, vol. 29(3), pages 249-272, June.
- Kolisch, Rainer & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 8114, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
- Browning, Tyson R. & Yassine, Ali A., 2010. "Resource-constrained multi-project scheduling: Priority rule performance revisited," International Journal of Production Economics, Elsevier, vol. 126(2), pages 212-228, August.
- Chen, Jiaqiong & Askin, Ronald G., 2009. "Project selection, scheduling and resource allocation with time dependent returns," European Journal of Operational Research, Elsevier, vol. 193(1), pages 23-34, February.
- Feifei Li & Zhe Xu, 2018. "A multi-agent system for distributed multi-project scheduling with two-stage decomposition," PLOS ONE, Public Library of Science, vol. 13(10), pages 1-24, October.
- He, Naihui & Zhang, David Z. & Yuce, Baris, 2022. "Integrated multi-project planning and scheduling - a multiagent approach," European Journal of Operational Research, Elsevier, vol. 302(2), pages 688-699.
- Bredael, Dries & Vanhoucke, Mario, 2023. "Multi-project scheduling: A benchmark analysis of metaheuristic algorithms on various optimisation criteria and due dates," European Journal of Operational Research, Elsevier, vol. 308(1), pages 54-75.
- Cédric Verbeeck & Vincent Peteghem & Mario Vanhoucke & Pieter Vansteenwegen & El-Houssaine Aghezzaf, 2017. "A metaheuristic solution approach for the time-constrained project scheduling problem," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 39(2), pages 353-371, March.
- Gómez Sánchez, Mariam & Lalla-Ruiz, Eduardo & Fernández Gil, Alejandro & Castro, Carlos & Voß, Stefan, 2023. "Resource-constrained multi-project scheduling problem: A survey," European Journal of Operational Research, Elsevier, vol. 309(3), pages 958-976.
- Alfredo S. Ramos & Pablo A. Miranda-Gonzalez & Samuel Nucamendi-Guillén & Elias Olivares-Benitez, 2023. "A Formulation for the Stochastic Multi-Mode Resource-Constrained Project Scheduling Problem Solved with a Multi-Start Iterated Local Search Metaheuristic," Mathematics, MDPI, vol. 11(2), pages 1-25, January.
- Bernardo F. Almeida & Isabel Correia & Francisco Saldanha-da-Gama, 2018. "A biased random-key genetic algorithm for the project scheduling problem with flexible resources," TOP: An Official Journal of the Spanish Society of Statistics and Operations Research, Springer;Sociedad de Estadística e Investigación Operativa, vol. 26(2), pages 283-308, July.
- Hartmann, Sönke & Briskorn, Dirk, 2022. "An updated survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 297(1), pages 1-14.
- Luise-Sophie Hoffmann & Carolin Kellenbrink & Stefan Helber, 2020. "Simultaneous structuring and scheduling of multiple projects with flexible project structures," Journal of Business Economics, Springer, vol. 90(5), pages 679-711, June.
- Bouleimen, K. & Lecocq, H., 2003. "A new efficient simulated annealing algorithm for the resource-constrained project scheduling problem and its multiple mode version," European Journal of Operational Research, Elsevier, vol. 149(2), pages 268-281, September.
- Anıl Can & Gündüz Ulusoy, 2014. "Multi-project scheduling with two-stage decomposition," Annals of Operations Research, Springer, vol. 217(1), pages 95-116, June.
- Van Peteghem, Vincent & Vanhoucke, Mario, 2014.
"An experimental investigation of metaheuristics for the multi-mode resource-constrained project scheduling problem on new dataset instances,"
European Journal of Operational Research, Elsevier, vol. 235(1), pages 62-72.
- V. Van Peteghem & M. Vanhoucke, 2011. "An Experimental Investigation of Metaheuristics for the Multi-Mode Resource-Constrained Project Scheduling Problem on New Dataset Instances," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 11/758, Ghent University, Faculty of Economics and Business Administration.
- Wuliang Peng & Jiali lin & Jingwen Zhang & Liangwei Chen, 2022. "A bi-objective hierarchical program scheduling problem and its solution based on NSGA-III," Annals of Operations Research, Springer, vol. 308(1), pages 389-414, January.
More about this item
Keywords
Bus body assembly; Genetic Algorithm; RCMPSP;All these keywords.
Statistics
Access and download statisticsCorrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:proeco:v:140:y:2012:i:1:p:431-438. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/ijpe .
Please note that corrections may take a couple of weeks to filter through the various RePEc services.