Project duration prediction using a Monte Carlo simulation of the periodic output of the project resources

Author

Listed:
  • Button Scott D.

Abstract

Bounding the project completion date for upcoming and active projects is important to organizations that perform projects. The output of these projects is often delivered to other organizations. For the purposes of planning, the customer organizations need a commitment date. One method for establishing this commitment is to simulate the project duration, using Monte Carlo methods for each task. I show an approach that models the periodic output of the resources, permitting more flexibility for modeling the real work of an organization.

Suggested Citation

  • Button Scott D., 2003. "Project duration prediction using a Monte Carlo simulation of the periodic output of the project resources," Monte Carlo Methods and Applications, De Gruyter, vol. 9(3), pages 217-225, September.
  • Handle: RePEc:bpj:mcmeap:v:9:y:2003:i:3:p:217-225:n:3
    DOI: 10.1515/156939603322728987
    as

    Download full text from publisher

    File URL: https://doi.org/10.1515/156939603322728987
    Download Restriction: For access to full text, subscription to the journal or payment for the individual article is required.

    File URL: https://libkey.io/10.1515/156939603322728987?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. D. G. Malcolm & J. H. Roseboom & C. E. Clark & W. Fazar, 1959. "Application of a Technique for Research and Development Program Evaluation," Operations Research, INFORMS, vol. 7(5), pages 646-669, October.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Kamburowski, J., 1997. "New validations of PERT times," Omega, Elsevier, vol. 25(3), pages 323-328, June.
    2. Xiong, Jian & Leus, Roel & Yang, Zhenyu & Abbass, Hussein A., 2016. "Evolutionary multi-objective resource allocation and scheduling in the Chinese navigation satellite system project," European Journal of Operational Research, Elsevier, vol. 251(2), pages 662-675.
    3. Pérez, José García & Martín, María del Mar López & García, Catalina García & Sánchez Granero, Miguel Ángel, 2016. "Project management under uncertainty beyond beta: The generalized bicubic distribution," Operations Research Perspectives, Elsevier, vol. 3(C), pages 67-76.
    4. Elise D. Miller-Hooks & Hani S. Mahmassani, 2000. "Least Expected Time Paths in Stochastic, Time-Varying Transportation Networks," Transportation Science, INFORMS, vol. 34(2), pages 198-215, May.
    5. Zhen Song & Håkan Schunnesson & Mikael Rinne & John Sturgul, 2015. "An Approach to Realizing Process Control for Underground Mining Operations of Mobile Machines," PLOS ONE, Public Library of Science, vol. 10(6), pages 1-17, June.
    6. V. Sireesha & N. Ravi Shankar, 2013. "A new approach to find project characteristics and multiple possible critical paths in a fuzzy project network," Fuzzy Information and Engineering, Springer, vol. 5(1), pages 69-85, March.
    7. Vaseghi, Forough & Martens, Annelies & Vanhoucke, Mario, 2024. "Analysis of the impact of corrective actions for stochastic project networks," European Journal of Operational Research, Elsevier, vol. 316(2), pages 503-518.
    8. Carlo Orsi, 2022. "On the conditional noncentral beta distribution," Statistica Neerlandica, Netherlands Society for Statistics and Operations Research, vol. 76(2), pages 164-189, May.
    9. Kotz, Samuel & van Dorp, J. René, 2005. "A link between two-sided power and asymmetric Laplace distributions: with applications to mean and variance approximations," Statistics & Probability Letters, Elsevier, vol. 71(4), pages 383-394, March.
    10. Edieal Pinker & Joseph Szmerekovsky & Vera Tilson, 2013. "Technical Note---Managing a Secret Project," Operations Research, INFORMS, vol. 61(1), pages 65-72, February.
    11. Alessio Angius & András Horváth & Marcello Urgo, 2021. "A Kronecker Algebra Formulation for Markov Activity Networks with Phase-Type Distributions," Mathematics, MDPI, vol. 9(12), pages 1-22, June.
    12. Trietsch, Dan & Mazmanyan, Lilit & Gevorgyan, Lilit & Baker, Kenneth R., 2012. "Modeling activity times by the Parkinson distribution with a lognormal core: Theory and validation," European Journal of Operational Research, Elsevier, vol. 216(2), pages 386-396.
    13. Ali Shafaat & C. Robert Kenley, 2020. "Model‐based design of project systems, modes, and states," Systems Engineering, John Wiley & Sons, vol. 23(2), pages 165-176, March.
    14. Carmichael, David G. & Ballouz, Joseph J. & Balatbat, Maria C.A., 2015. "Improving the attractiveness of CDM projects through allowing and incorporating options," Energy Policy, Elsevier, vol. 86(C), pages 784-791.
    15. Li, Xiaobo & Natarajan, Karthik & Teo, Chung-Piaw & Zheng, Zhichao, 2014. "Distributionally robust mixed integer linear programs: Persistency models with applications," European Journal of Operational Research, Elsevier, vol. 233(3), pages 459-473.
    16. Illana Bendavid & Boaz Golany, 2011. "Setting gates for activities in the stochastic project scheduling problem through the cross entropy methodology," Annals of Operations Research, Springer, vol. 189(1), pages 25-42, September.
    17. Andrew M. Ross, 2010. "Computing Bounds on the Expected Maximum of Correlated Normal Variables," Methodology and Computing in Applied Probability, Springer, vol. 12(1), pages 111-138, March.
    18. R. Alan Bowman, 2003. "Sensitivity curves for effective project management," Naval Research Logistics (NRL), John Wiley & Sons, vol. 50(5), pages 481-497, August.
    19. Serpell Alfredo Federico & Ferrada Ximena & Rubio Larissa, 2019. "Measuring the performance of project risk management: a preliminary model," Organization, Technology and Management in Construction, Sciendo, vol. 11(1), pages 1984-1991, January.
    20. CATTARUZZO Sebastiano, 2020. "On R&D sectoral intensities and convergence clubs," JRC Working Papers on Corporate R&D and Innovation 2020-01, Joint Research Centre.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:bpj:mcmeap:v:9:y:2003:i:3:p:217-225:n:3. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Peter Golla (email available below). General contact details of provider: https://www.degruyter.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.