How to apply penalties to avoid delays in projects

Author

Listed:
  • Bergantiños, Gustavo
  • Lorenzo, Leticia

Abstract

A planner wants to carry out a project involving several firms. In many cases the planner, for instance the Spanish Administration, includes in the contract a penalty clause that imposes a payment per day if the firms do not complete their activities or the project on time. We discuss two ways of including such penalty clauses in contracts. In the first the penalty applies only when the whole project is delayed. In the second the penalty applies to each firm that incurs a delay even if the project is completed on time. We compare the two penalty systems and find that the optimal penalty (for the planner) is larger in the second method, the utility of the planner is always at least as large or larger in the second case and the utility of the firms is always at least as large or larger in the first. Surprisingly, the final delay in the project is unrelated to which penalty system is chosen.

Suggested Citation

  • Bergantiños, Gustavo & Lorenzo, Leticia, 2019. "How to apply penalties to avoid delays in projects," MPRA Paper 91718, University Library of Munich, Germany.
  • Handle: RePEc:pra:mprapa:91718
    as

    Download full text from publisher

    File URL: https://mpra.ub.uni-muenchen.de/91718/1/MPRA_paper_91718.pdf
    File Function: original version
    Download Restriction: no

    File URL: https://mpra.ub.uni-muenchen.de/104574/1/MPRA_paper_104574.pdf
    File Function: revised version
    Download Restriction: no
    ---><---

    Other versions of this item:

    References listed on IDEAS

    as
    1. Jonathan Levin, 2003. "Relational Incentive Contracts," American Economic Review, American Economic Association, vol. 93(3), pages 835-857, June.
    2. Dagan, Nir & Serrano, Roberto & Volij, Oscar, 1997. "A Noncooperative View of Consistent Bankruptcy Rules," Games and Economic Behavior, Elsevier, vol. 18(1), pages 55-72, January.
    3. Rodica Brânzei & Giulio Ferrari & Vito Fragnelli & Stef Tijs, 2002. "Two Approaches to the Problem of Sharing Delay Costs in Joint Projects," Annals of Operations Research, Springer, vol. 109(1), pages 359-374, January.
    4. Gregory Lewis & Patrick Bajari, 2014. "Moral Hazard, Incentive Contracts, and Risk: Evidence from Procurement," The Review of Economic Studies, Review of Economic Studies Ltd, vol. 81(3), pages 1201-1228.
    5. Decio Coviello & Luigi Moretti & Giancarlo Spagnolo & Paola Valbonesi, 2018. "Court Efficiency and Procurement Performance," Scandinavian Journal of Economics, Wiley Blackwell, vol. 120(3), pages 826-858, July.
    6. Sergio Vergalli & Chiara D’Alpaos & Michele Moretto & Paola Valbonesi, 2009. ""It Is Never too late": Optimal Penalty for Investment Delay in Public Procurement Contracts," Working Papers 2009.78, Fondazione Eni Enrico Mattei.
    7. Chiara D’Alpaos & Michele Moretto & Paola Valbonesi & Sergio Vergalli, 2013. "Time overruns as opportunistic behavior in public procurement," Journal of Economics, Springer, vol. 110(1), pages 25-43, September.
    8. Perez-Castrillo, David & Wettstein, David, 2001. "Bidding for the Surplus : A Non-cooperative Approach to the Shapley Value," Journal of Economic Theory, Elsevier, vol. 100(2), pages 274-294, October.
    9. Moulin, Herve & Shenker, Scott, 1992. "Serial Cost Sharing," Econometrica, Econometric Society, vol. 60(5), pages 1009-1037, September.
    10. Thomson, William, 2003. "Axiomatic and game-theoretic analysis of bankruptcy and taxation problems: a survey," Mathematical Social Sciences, Elsevier, vol. 45(3), pages 249-297, July.
    11. Hart, Sergiu & Mas-Colell, Andreu, 1996. "Bargaining and Value," Econometrica, Econometric Society, vol. 64(2), pages 357-380, March.
    12. Perry, Motty & Reny, Philip J, 1994. "A Noncooperative View of Coalition Formation and the Core," Econometrica, Econometric Society, vol. 62(4), pages 795-817, July.
    13. Gregory Lewis & Patrick Bajari, 2011. "Procurement Contracting With Time Incentives: Theory and Evidence," The Quarterly Journal of Economics, President and Fellows of Harvard College, vol. 126(3), pages 1173-1211.
    14. Katherine Doornik, 2010. "Incentive Contracts with Enforcement Costs," The Journal of Law, Economics, and Organization, Oxford University Press, vol. 26(1), pages 115-143, April.
    15. D. G. Malcolm & J. H. Roseboom & C. E. Clark & W. Fazar, 1959. "Application of a Technique for Research and Development Program Evaluation," Operations Research, INFORMS, vol. 7(5), pages 646-669, October.
    16. Aumann, Robert J. & Maschler, Michael, 1985. "Game theoretic analysis of a bankruptcy problem from the Talmud," Journal of Economic Theory, Elsevier, vol. 36(2), pages 195-213, August.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. J. C. Gonçalves-Dosantos & I. García-Jurado & J. Costa, 2020. "Sharing delay costs in stochastic scheduling problems with delays," 4OR, Springer, vol. 18(4), pages 457-476, December.
    2. Šůcha, Přemysl & Agnetis, Alessandro & Šidlovský, Marko & Briand, Cyril, 2021. "Nash equilibrium solutions in multi-agent project scheduling with milestones," European Journal of Operational Research, Elsevier, vol. 294(1), pages 29-41.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Decio Coviello & Luigi Moretti & Giancarlo Spagnolo & Paola Valbonesi, 2018. "Court Efficiency and Procurement Performance," Scandinavian Journal of Economics, Wiley Blackwell, vol. 120(3), pages 826-858, July.
    2. Hu, Cheng-Cheng & Tsay, Min-Hung & Yeh, Chun-Hsien, 2018. "A study of the nucleolus in the nested cost-sharing problem: Axiomatic and strategic perspectives," Games and Economic Behavior, Elsevier, vol. 109(C), pages 82-98.
    3. Schouten, Jop, 2022. "Cooperation, allocation and strategy in interactive decision-making," Other publications TiSEM d5d41448-8033-4f6b-8ec0-c, Tilburg University, School of Economics and Management.
    4. Yuan Ju & David Wettstein, 2009. "Implementing cooperative solution concepts: a generalized bidding approach," Economic Theory, Springer;Society for the Advancement of Economic Theory (SAET), vol. 39(2), pages 307-330, May.
    5. Giuseppe Francesco Gori & Patrizia Lattarulo & Marco Mariani, 2021. "The Expediting Effect of Monitoring on Infrastructural Works. A Regression-Discontinuity Approach with Multiple Assignment Variables," Papers 2102.09625, arXiv.org.
    6. Cesare Dosi & Michele Moretto, 2017. "Cost Uncertainty and Time Overruns in Public Procurement: a Scoring Auction for a Contract with Delay Penalties," Working Papers 2017.02, Fondazione Eni Enrico Mattei.
    7. Roberto Serrano, 2004. "Fifty Years of the Nash Program, 1953-2003," Working Papers 2004-20, Brown University, Department of Economics.
    8. Van Essen, Matt & Wooders, John, 2021. "Allocating positions fairly: Auctions and Shapley value," Journal of Economic Theory, Elsevier, vol. 196(C).
    9. Cesare Dosi & Michele Moretto, 2017. "Cost Uncertainty and Time Overruns in Public Procurement: a Scoring Auction for a Contract with Delay Penalties," Working Papers 2017.02, Fondazione Eni Enrico Mattei.
    10. M. Albizuri & J. Echarri & J. Zarzuelo, 2015. "A non-cooperative mechanism for the Shapley value of airport problems," Annals of Operations Research, Springer, vol. 235(1), pages 1-11, December.
    11. Roberto Serrano, 2005. "Fifty years of the Nash program, 1953-2003," Investigaciones Economicas, Fundación SEPI, vol. 29(2), pages 219-258, May.
    12. Peris, Josep E. & Jiménez-Gómez, José M., 2012. "A Proportional Approach to Bankruptcy Problems with a guaranteed minimum," QM&ET Working Papers 12-7, University of Alicante, D. Quantitative Methods and Economic Theory.
    13. William Thomson, 2014. "Compromising between the proportional and constrained equal awards rules," RCER Working Papers 584, University of Rochester - Center for Economic Research (RCER).
    14. José M. Jiménez Gómez, 2010. "Noncooperative justifications for old bankruptcy rules," Working Papers. Serie AD 2010-15, Instituto Valenciano de Investigaciones Económicas, S.A. (Ivie).
    15. Chiara D’Alpaos & Michele Moretto & Paola Valbonesi & Sergio Vergalli, 2013. "Time overruns as opportunistic behavior in public procurement," Journal of Economics, Springer, vol. 110(1), pages 25-43, September.
    16. Jaume García-Segarra & Miguel Ginés-Vilar, 2023. "Additive adjudication of conflicting claims," International Journal of Game Theory, Springer;Game Theory Society, vol. 52(1), pages 93-116, March.
    17. Juan D. Moreno-Ternero & Min-Hung Tsay & Chun-Hsien Yeh, 2020. "A strategic justification of the Talmud rule based on lower and upper bounds," International Journal of Game Theory, Springer;Game Theory Society, vol. 49(4), pages 1045-1057, December.
    18. José Alcalde & María Marco & José Silva, 2008. "The minimal overlap rule revisited," Social Choice and Welfare, Springer;The Society for Social Choice and Welfare, vol. 31(1), pages 109-128, June.
    19. Büyükboyacı, Mürüvvet & Gürdal, Mehmet Y. & Kıbrıs, Arzu & Kıbrıs, Özgür, 2019. "An experimental study of the investment implications of bankruptcy laws," Journal of Economic Behavior & Organization, Elsevier, vol. 158(C), pages 607-629.
    20. Emin Karagözoğlu, 2014. "A noncooperative approach to bankruptcy problems with an endogenous estate," Annals of Operations Research, Springer, vol. 217(1), pages 299-318, June.

    More about this item

    Keywords

    game theory; PERT; delays; penalties;
    All these keywords.

    JEL classification:

    • C72 - Mathematical and Quantitative Methods - - Game Theory and Bargaining Theory - - - Noncooperative Games

    NEP fields

    This paper has been announced in the following NEP Reports:

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:pra:mprapa:91718. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Joachim Winter (email available below). General contact details of provider: https://edirc.repec.org/data/vfmunde.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.