On equivalence between the proportionate flow shop and single‐machine scheduling problems

Author

Listed:
  • S.S. Panwalkar
  • Christos Koulamas

Abstract

We derive sufficient conditions which, when satisfied, guarantee that an optimal solution for a single‐machine scheduling problem is also optimal for the corresponding proportionate flow shop scheduling problem. We then utilize these sufficient conditions to show the solvability in polynomial time of numerous proportionate flow shop scheduling problems with fixed job processing times, position‐dependent job processing times, controllable job processing times, and also problems with job rejection. © 2015 Wiley Periodicals, Inc. Naval Research Logistics 62: 595–603, 2015

Suggested Citation

  • S.S. Panwalkar & Christos Koulamas, 2015. "On equivalence between the proportionate flow shop and single‐machine scheduling problems," Naval Research Logistics (NRL), John Wiley & Sons, vol. 62(7), pages 595-603, October.
  • Handle: RePEc:wly:navres:v:62:y:2015:i:7:p:595-603
    DOI: 10.1002/nav.21666
    as

    Download full text from publisher

    File URL: https://doi.org/10.1002/nav.21666
    Download Restriction: no

    File URL: https://libkey.io/10.1002/nav.21666?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Koulamas, Christos & Kyparisis, George J., 2007. "Single-machine and two-machine flowshop scheduling with general learning functions," European Journal of Operational Research, Elsevier, vol. 178(2), pages 402-407, April.
    2. Biskup, Dirk & Simons, Dirk, 2004. "Common due date scheduling with autonomous and induced learning," European Journal of Operational Research, Elsevier, vol. 159(3), pages 606-616, December.
    3. Dvir Shabtay & Nufar Gaspar & Liron Yedidsion, 2012. "A bicriteria approach to scheduling a single machine with job rejection and positional penalties," Journal of Combinatorial Optimization, Springer, vol. 23(4), pages 395-424, May.
    4. E. L. Lawler, 1973. "Optimal Sequencing of a Single Machine Subject to Precedence Constraints," Management Science, INFORMS, vol. 19(5), pages 544-546, January.
    5. Biskup, Dirk, 1999. "Single-machine scheduling with learning considerations," European Journal of Operational Research, Elsevier, vol. 115(1), pages 173-178, May.
    6. Gordon, Valery & Proth, Jean-Marie & Chu, Chengbin, 2002. "A survey of the state-of-the-art of common due date assignment and scheduling research," European Journal of Operational Research, Elsevier, vol. 139(1), pages 1-25, May.
    7. S. S. Panwalkar & M. L. Smith & A. Seidmann, 1982. "Common Due Date Assignment to Minimize Total Penalty for the One Machine Scheduling Problem," Operations Research, INFORMS, vol. 30(2), pages 391-399, April.
    8. Sid Browne & Uri Yechiali, 1990. "Scheduling Deteriorating Jobs on a Single Processor," Operations Research, INFORMS, vol. 38(3), pages 495-498, June.
    9. Estevez Fernandez, M.A. & Mosquera, M.A. & Borm, P.E.M. & Hamers, H.J.M., 2006. "Proportionate Flow Shop Games," Other publications TiSEM d54cb827-3347-4150-9792-b, Tilburg University, School of Economics and Management.
    10. Allesandro Agnetis & Pitu B. Mirchandani & Dario Pacciarelli & Andrea Pacifici, 2004. "Scheduling Problems with Two Competing Agents," Operations Research, INFORMS, vol. 52(2), pages 229-242, April.
    11. S.S. Panwalkar & Christos Koulamas, 2015. "Proportionate flow shop: New complexity results and models with due date assignment," Naval Research Logistics (NRL), John Wiley & Sons, vol. 62(2), pages 98-106, March.
    12. Koulamas, Christos & Gupta, Sushil & Kyparisis, George J., 2010. "A unified analysis for the single-machine scheduling problem with controllable and non-controllable variable job processing times," European Journal of Operational Research, Elsevier, vol. 205(2), pages 479-482, September.
    13. John J. Kanet, 1981. "Minimizing the average deviation of job completion times about a common due date," Naval Research Logistics Quarterly, John Wiley & Sons, vol. 28(4), pages 643-651, December.
    14. Clyde L. Monma & Alexander Schrijver & Michael J. Todd & Victor K. Wei, 1990. "Convex Resource Allocation Problems on Directed Acyclic Graphs: Duality, Complexity, Special Cases, and Extensions," Mathematics of Operations Research, INFORMS, vol. 15(4), pages 736-748, November.
    15. B Mor & G Mosheiov, 2014. "Polynomial time solutions for scheduling problems on a proportionate flowshop with two competing agents," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 65(1), pages 151-157, January.
    16. Kenneth R. Baker & Gary D. Scudder, 1990. "Sequencing with Earliness and Tardiness Penalties: A Review," Operations Research, INFORMS, vol. 38(1), pages 22-36, February.
    17. Peng Si Ow, 1985. "Focused Scheduling in Proportionate Flowshops," Management Science, INFORMS, vol. 31(7), pages 852-869, July.
    18. Koulamas, Christos, 2011. "A unified solution approach for the due date assignment problem with tardy jobs," International Journal of Production Economics, Elsevier, vol. 132(2), pages 292-295, August.
    19. Panwalkar, S. S. & Rajagopalan, R., 1992. "Single-machine sequencing with controllable processing times," European Journal of Operational Research, Elsevier, vol. 59(2), pages 298-302, June.
    20. S.S. Panwalkar & Milton L. Smith & Christos Koulamas, 2013. "Review of the ordered and proportionate flow shop scheduling research," Naval Research Logistics (NRL), John Wiley & Sons, vol. 60(1), pages 46-55, February.
    21. Michael Pinedo, 1982. "Minimizing the Expected Makespan in Stochastic Flow Shops," Operations Research, INFORMS, vol. 30(1), pages 148-162, February.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Jin Qian & Haiyan Han, 2022. "Improved algorithms for proportionate flow shop scheduling with due-window assignment," Annals of Operations Research, Springer, vol. 309(1), pages 249-258, February.
    2. Yu, Tae-Sun & Han, Jun-Hee, 2021. "Scheduling proportionate flow shops with preventive machine maintenance," International Journal of Production Economics, Elsevier, vol. 231(C).
    3. Xinyu Sun & Xin-Na Geng & Tao Liu, 2020. "Due-window assignment scheduling in the proportionate flow shop setting," Annals of Operations Research, Springer, vol. 292(1), pages 113-131, September.
    4. Koulamas, Christos, 2020. "The proportionate flow shop total tardiness problem," European Journal of Operational Research, Elsevier, vol. 284(2), pages 439-444.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Koulamas, Christos & Kyparisis, George J., 2023. "A classification of dynamic programming formulations for offline deterministic single-machine scheduling problems," European Journal of Operational Research, Elsevier, vol. 305(3), pages 999-1017.
    2. Qian, Jianbo & Steiner, George, 2013. "Fast algorithms for scheduling with learning effects and time-dependent processing times on a single machine," European Journal of Operational Research, Elsevier, vol. 225(3), pages 547-551.
    3. S.S. Panwalkar & Christos Koulamas, 2015. "Proportionate flow shop: New complexity results and models with due date assignment," Naval Research Logistics (NRL), John Wiley & Sons, vol. 62(2), pages 98-106, March.
    4. Dvir Shabtay & George Steiner, 2008. "The single-machine earliness-tardiness scheduling problem with due date assignment and resource-dependent processing times," Annals of Operations Research, Springer, vol. 159(1), pages 25-40, March.
    5. Koulamas, Christos & Gupta, Sushil & Kyparisis, George J., 2010. "A unified analysis for the single-machine scheduling problem with controllable and non-controllable variable job processing times," European Journal of Operational Research, Elsevier, vol. 205(2), pages 479-482, September.
    6. Shabtay, Dvir & Steiner, George & Zhang, Rui, 2016. "Optimal coordination of resource allocation, due date assignment and scheduling decisions," Omega, Elsevier, vol. 65(C), pages 41-54.
    7. T C E Cheng & L Kang & C T Ng, 2004. "Due-date assignment and single machine scheduling with deteriorating jobs," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 55(2), pages 198-203, February.
    8. Leyvand, Yaron & Shabtay, Dvir & Steiner, George, 2010. "A unified approach for scheduling with convex resource consumption functions using positional penalties," European Journal of Operational Research, Elsevier, vol. 206(2), pages 301-312, October.
    9. Janiak, Adam & Janiak, Władysław A. & Krysiak, Tomasz & Kwiatkowski, Tomasz, 2015. "A survey on scheduling problems with due windows," European Journal of Operational Research, Elsevier, vol. 242(2), pages 347-357.
    10. Baruch Mor, 2019. "Minmax scheduling problems with common due-date and completion time penalty," Journal of Combinatorial Optimization, Springer, vol. 38(1), pages 50-71, July.
    11. Lee, Kangbok & Zheng, Feifeng & Pinedo, Michael L., 2019. "Online scheduling of ordered flow shops," European Journal of Operational Research, Elsevier, vol. 272(1), pages 50-60.
    12. Shabtay, Dvir, 2010. "Scheduling and due date assignment to minimize earliness, tardiness, holding, due date assignment and batch delivery costs," International Journal of Production Economics, Elsevier, vol. 123(1), pages 235-242, January.
    13. Gordon, Valery & Proth, Jean-Marie & Chu, Chengbin, 2002. "A survey of the state-of-the-art of common due date assignment and scheduling research," European Journal of Operational Research, Elsevier, vol. 139(1), pages 1-25, May.
    14. Oğuzhan Ahmet Arik, 2023. "A heuristic for single machine common due date assignment problem with different earliness/tardiness weights," OPSEARCH, Springer;Operational Research Society of India, vol. 60(3), pages 1561-1574, September.
    15. Chen, Ke & Cheng, T.C.E. & Huang, Hailiang & Ji, Min & Yao, Danli, 2023. "Single-machine scheduling with autonomous and induced learning to minimize total weighted number of tardy jobs," European Journal of Operational Research, Elsevier, vol. 309(1), pages 24-34.
    16. W-H Kuo & D-L Yang, 2011. "A note on due-date assignment and single-machine scheduling with deteriorating jobs and learning effects," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 62(1), pages 206-210, January.
    17. Chung‐Lun Li & T. C. E. Cheng, 1994. "The parallel machine min‐max weighted absolute lateness scheduling problem," Naval Research Logistics (NRL), John Wiley & Sons, vol. 41(1), pages 33-46, February.
    18. Biskup, Dirk & Simons, Dirk, 2004. "Common due date scheduling with autonomous and induced learning," European Journal of Operational Research, Elsevier, vol. 159(3), pages 606-616, December.
    19. S.S. Panwalkar & Milton L. Smith & Christos Koulamas, 2013. "Review of the ordered and proportionate flow shop scheduling research," Naval Research Logistics (NRL), John Wiley & Sons, vol. 60(1), pages 46-55, February.
    20. Wen-Hung Wu & Yunqiang Yin & T C E Cheng & Win-Chin Lin & Juei-Chao Chen & Shin-Yi Luo & Chin-Chia Wu, 2017. "A combined approach for two-agent scheduling with sum-of-processing-times-based learning effect," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 68(2), pages 111-120, February.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:wly:navres:v:62:y:2015:i:7:p:595-603. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Wiley Content Delivery (email available below). General contact details of provider: https://doi.org/10.1002/(ISSN)1520-6750 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.