On the use of multivariate regression methods for longest path calculations from earned value management observations

Author

Listed:
  • Vanhoucke, Mario
  • Colin, Jeroen

Abstract

This paper explores the use of multivariate regression methods for project schedule control within a statistical project control framework. These multivariate regression methods monitor the activity level performance of an ongoing project from the earned value management/earned schedule (EVM/ES) observations that are made at a high level of the work breakdown structure (WBS). These estimates can be used to calculate the longest path in the project and to produce warning signals for project schedule control. The effort that is spent by the project manager is thereby reduced, since a drill-down of the WBS is no longer required for every review period. An extensive computational experiment was set up to test and compare four distinct multivariate regression methods on a database of project networks. The kernel principal component regression method, when used with a radial base function kernel, was found to outperform the other presented regression methods.

Suggested Citation

  • Vanhoucke, Mario & Colin, Jeroen, 2016. "On the use of multivariate regression methods for longest path calculations from earned value management observations," Omega, Elsevier, vol. 61(C), pages 127-140.
  • Handle: RePEc:eee:jomega:v:61:y:2016:i:c:p:127-140
    DOI: 10.1016/j.omega.2015.07.013
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0305048315001553
    Download Restriction: Full text for ScienceDirect subscribers only

    File URL: https://libkey.io/10.1016/j.omega.2015.07.013?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Trietsch, Dan & Mazmanyan, Lilit & Gevorgyan, Lilit & Baker, Kenneth R., 2012. "Modeling activity times by the Parkinson distribution with a lognormal core: Theory and validation," European Journal of Operational Research, Elsevier, vol. 216(2), pages 386-396.
    2. Colin, Jeroen & Vanhoucke, Mario, 2014. "Setting tolerance limits for statistical project control using earned value management," Omega, Elsevier, vol. 49(C), pages 107-122.
    3. Jörg Henseler, 2010. "On the convergence of the partial least squares path modeling algorithm," Computational Statistics, Springer, vol. 25(1), pages 107-120, March.
    4. Kettaneh, Nouna & Berglund, Anders & Wold, Svante, 2005. "PCA and PLS with very large data sets," Computational Statistics & Data Analysis, Elsevier, vol. 48(1), pages 69-85, January.
    5. Mario Vanhoucke, 2014. "Earned Value Management," Management for Professionals, in: Integrated Project Management and Control, edition 127, chapter 0, pages 17-31, Springer.
    6. Vanhoucke, Mario, 2011. "On the dynamic use of project performance and schedule risk information during projecttracking," Omega, Elsevier, vol. 39(4), pages 416-426, August.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2022. "Using Earned Value Management and Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 297(2), pages 451-466.
    2. Mohammadreza Sharifi Ghazvini & Vahidreza Ghezavati & Sadigh Raissi & Ahmad Makui, 2017. "An Integrated Efficiency–Risk Approach in Sustainable Project Control," Sustainability, MDPI, vol. 9(9), pages 1-20, September.
    3. Martens, Annelies & Vanhoucke, Mario, 2017. "A buffer control method for top-down project control," European Journal of Operational Research, Elsevier, vol. 262(1), pages 274-286.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Martens, Annelies & Vanhoucke, Mario, 2019. "The impact of applying effort to reduce activity variability on the project time and cost performance," European Journal of Operational Research, Elsevier, vol. 277(2), pages 442-453.
    2. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2022. "Using Earned Value Management and Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 297(2), pages 451-466.
    3. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2020. "The impact of a limited budget on the corrective action taking process," European Journal of Operational Research, Elsevier, vol. 286(3), pages 1070-1086.
    4. Plaza, Malgorzata, 2016. "Balancing the costs of human resources on an ERP project," Omega, Elsevier, vol. 59(PB), pages 171-183.
    5. Martens, Annelies & Vanhoucke, Mario, 2017. "A buffer control method for top-down project control," European Journal of Operational Research, Elsevier, vol. 262(1), pages 274-286.
    6. Cohen, Izack & Iluz, Michal, 2015. "When cost–effective design strategies are not enough: Evidence from an experimental study on the role of redundant goals," Omega, Elsevier, vol. 56(C), pages 99-111.
    7. Womer, K. & Li, H. & Camm, J. & Osterman, C. & Radhakrishnan, R., 2017. "Learning and Bayesian updating in long cycle made-to-order (MTO) production," Omega, Elsevier, vol. 69(C), pages 29-42.
    8. Wauters, Mathieu & Vanhoucke, Mario, 2017. "A Nearest Neighbour extension to project duration forecasting with Artificial Intelligence," European Journal of Operational Research, Elsevier, vol. 259(3), pages 1097-1111.
    9. Mohammadreza Sharifi Ghazvini & Vahidreza Ghezavati & Sadigh Raissi & Ahmad Makui, 2017. "An Integrated Efficiency–Risk Approach in Sustainable Project Control," Sustainability, MDPI, vol. 9(9), pages 1-20, September.
    10. Merkourios Papanikolaou & Yiannis Xenidis, 2020. "Risk-Informed Performance Assessment of Construction Projects," Sustainability, MDPI, vol. 12(13), pages 1-20, July.
    11. Colin, Jeroen & Vanhoucke, Mario, 2014. "Setting tolerance limits for statistical project control using earned value management," Omega, Elsevier, vol. 49(C), pages 107-122.
    12. Richard E. Wendell & Timothy J. Lowe & Mike M. Gordon, 2023. "Dangers in using earned duration and other earned value metrics to measure a project’s schedule performance," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 31(2), pages 665-680, June.
    13. M. T. Hajiali & M. R. Mosavi & K. Shahanaghi, 2014. "Estimation of Project Completion Time-Based on a Mixture of Expert in an Interactive Space," Modern Applied Science, Canadian Center of Science and Education, vol. 8(6), pages 229-229, December.
    14. Junguang Zhang & Xiwei Song & Hongyu Chen & Ruixia (Sandy) Shi, 2016. "Determination of critical chain project buffer based on information flow interactions," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 67(9), pages 1146-1157, September.
    15. Zaitul Zaitul & Novianti Neva & Ilona Desi, 2022. "Village-Based Tourism Performance: Tourist Satisfaction and Revisit Intention," Polish Journal of Sport and Tourism, Sciendo, vol. 29(2), pages 36-43, June.
    16. Menrad, K. & Emberger-Klein, A. & Schops, J., 2018. "Factors influencing consumers behavioral intention towards climate-friendly food consumption in Southern Germany," 2018 Conference, July 28-August 2, 2018, Vancouver, British Columbia 277108, International Association of Agricultural Economists.
    17. Matthias Thürer & Nuno O. Fernandes & Mark Stevenson & Cristovao Silva & Silvio Carmo-Silva, 2019. "POLC-A: an assessment of POLCA’s authorization element," Journal of Intelligent Manufacturing, Springer, vol. 30(6), pages 2435-2447, August.
    18. Lawrence, Akvile & Karlsson, Magnus & Nehler, Therese & Thollander, Patrik, 2019. "Effects of monetary investment, payback time and firm characteristics on electricity saving in energy-intensive industry," Applied Energy, Elsevier, vol. 240(C), pages 499-512.
    19. Sarstedt, Marko & Ringle, Christian M. & Smith, Donna & Reams, Russell & Hair, Joseph F., 2014. "Partial least squares structural equation modeling (PLS-SEM): A useful tool for family business researchers," Journal of Family Business Strategy, Elsevier, vol. 5(1), pages 105-115.
    20. Lemos, R.F. & Ronconi, D.P., 2015. "Heuristics for the stochastic single-machine problem with E/T costs," International Journal of Production Economics, Elsevier, vol. 168(C), pages 131-142.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:jomega:v:61:y:2016:i:c:p:127-140. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/wps/find/journaldescription.cws_home/375/description#description .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.