Systematic Literature Review of Implementing the Project Control System Using Earned Value Management (EVM)

Author

Listed:
  • Samira Nadafi

    (Assistant professor, Department of Industrial Engineering, Engineering College, Shahid Bahonar University of Kerman, Kerman, Iran)

  • Seyed Hamed Moosavirad

    (Assistant professor, Department of Industrial Engineering, Engineering College, Shahid Bahonar University of Kerman, Kerman, Iran)

  • Shahram Ariafar

    (Assistant professor, Department of Industrial Engineering, Engineering College, Shahid Bahonar University of Kerman, Kerman, Iran)

Abstract

Project control is considered as one of the major and key issues in organizations. The project is assessed from three dimensions including time, cost, and scope. Therefore, the purpose of this study is to review the methods and criteria that have been used in the project control literature. This study is a systematic review of 40 papers that have been published in two time periods between 2006 and 2017 or from 1387 to 1392 according to the electronic databases. It was found that 20 of these articles that form 50% of the total articles have not used the Earned Value Management method for project control. Therefore, there are still other methods that can be applied for implementing in the project control system. The results revealed that Earned Value Management is one of the popular methods for implementing the project control system by controlling the project time and costs. Ultimately, the case study papers and their aims have been analyzed in this study.

Suggested Citation

  • Samira Nadafi & Seyed Hamed Moosavirad & Shahram Ariafar, 2017. "Systematic Literature Review of Implementing the Project Control System Using Earned Value Management (EVM)," European Journal of Studies in Management and Business, EUROKD, vol. 1, pages 34-46.
  • Handle: RePEc:bco:mbrqaa::v:1:y:2017:p:34-46
    DOI: 10.32038/mbrq.2017.01.03
    as

    Download full text from publisher

    File URL: https://api.eurokd.com/Uploads/Article/330/mbrq.2017.01.03.pdf
    Download Restriction: no

    File URL: https://libkey.io/10.32038/mbrq.2017.01.03?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Vanhoucke, Mario & Colin, Jeroen, 2016. "On the use of multivariate regression methods for longest path calculations from earned value management observations," Omega, Elsevier, vol. 61(C), pages 127-140.
    2. Colin, Jeroen & Vanhoucke, Mario, 2014. "Setting tolerance limits for statistical project control using earned value management," Omega, Elsevier, vol. 49(C), pages 107-122.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2022. "Using Earned Value Management and Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 297(2), pages 451-466.
    2. Martens, Annelies & Vanhoucke, Mario, 2017. "A buffer control method for top-down project control," European Journal of Operational Research, Elsevier, vol. 262(1), pages 274-286.
    3. Song, Jie & Song, Jinbo & Vanhoucke, Mario, 2025. "Automatic selection of the best performing control point approach for project control with resource constraints," European Journal of Operational Research, Elsevier, vol. 322(1), pages 15-38.
    4. Mohammadreza Sharifi Ghazvini & Vahidreza Ghezavati & Sadigh Raissi & Ahmad Makui, 2017. "An Integrated Efficiency–Risk Approach in Sustainable Project Control," Sustainability, MDPI, vol. 9(9), pages 1-20, September.
    5. Vanhoucke, Mario & Colin, Jeroen, 2016. "On the use of multivariate regression methods for longest path calculations from earned value management observations," Omega, Elsevier, vol. 61(C), pages 127-140.
    6. Martens, Annelies & Vanhoucke, Mario, 2019. "The impact of applying effort to reduce activity variability on the project time and cost performance," European Journal of Operational Research, Elsevier, vol. 277(2), pages 442-453.
    7. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2020. "The impact of a limited budget on the corrective action taking process," European Journal of Operational Research, Elsevier, vol. 286(3), pages 1070-1086.
    8. Womer, K. & Li, H. & Camm, J. & Osterman, C. & Radhakrishnan, R., 2017. "Learning and Bayesian updating in long cycle made-to-order (MTO) production," Omega, Elsevier, vol. 69(C), pages 29-42.
    9. Wauters, Mathieu & Vanhoucke, Mario, 2017. "A Nearest Neighbour extension to project duration forecasting with Artificial Intelligence," European Journal of Operational Research, Elsevier, vol. 259(3), pages 1097-1111.
    10. Lenah Cleo Kelepile, 2024. "A Comprehensive Analysis of Monitoring and Control Mechanisms in Operational Relocation Project at Limkokwing University, Botswana," International Journal of Research and Innovation in Social Science, International Journal of Research and Innovation in Social Science (IJRISS), vol. 8(5), pages 1759-1771, May.
    11. Plaza, Malgorzata, 2016. "Balancing the costs of human resources on an ERP project," Omega, Elsevier, vol. 59(PB), pages 171-183.
    12. Cohen, Izack & Iluz, Michal, 2015. "When cost–effective design strategies are not enough: Evidence from an experimental study on the role of redundant goals," Omega, Elsevier, vol. 56(C), pages 99-111.
    13. Merkourios Papanikolaou & Yiannis Xenidis, 2020. "Risk-Informed Performance Assessment of Construction Projects," Sustainability, MDPI, vol. 12(13), pages 1-20, July.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:bco:mbrqaa::v:1:y:2017:p:34-46. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Sara Gunen (email available below). General contact details of provider: .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.