Multi-mode resource-constrained project scheduling problem with material ordering under bonus–penalty policies

Author

Listed:
  • Nima Zoraghi

    (Islamic Azad University)

  • Aria Shahsavar

    (Islamic Azad University)

  • Babak Abbasi

    (RMIT University)

  • Vincent Peteghem

    (EDHEC Business School)

Abstract

This study emphasizes that project scheduling and material ordering (time and quantity of an order) must be considered simultaneously to minimize the total cost, as setting the material ordering decisions after the project scheduling phase leads to non-optimal solutions. Hence, this paper mathematically formulates the model for the multi-mode resource-constrained project scheduling with material ordering (MRCPSMO) problem. In order to be more realistic, bonus and penalty policies are included for the project. The objective function of the model consists of four elements: the material holding cost, the material ordering cost, the bonus paid by the client and the cost of delay in the project completion. Since MRCPSMO is NP-hard, the paper proposes three hybrid meta-heuristic algorithms called PSO-GA, GA-GA and SA-GA to obtain near-optimal solutions. In addition, the design of experiments and Taguchi method is used to tune the algorithms’ parameters. The proposed algorithms consist of two components: an outside search, in which the algorithm searches for the best schedule and mode assignment, and the inside search, which determines the time and quantity of orders of the nonrenewable resources. First, a comparison is made for each individual component with the exact or best solutions available in the literature. Then, a set of standard PROGEN test problems is solved by the proposed hybrid algorithms under fixed CPU time. The results reveal that the PSO-GA algorithm outperforms both GA-GA and SA-GA algorithms and provides good solutions in a reasonable time.

Suggested Citation

  • Nima Zoraghi & Aria Shahsavar & Babak Abbasi & Vincent Peteghem, 2017. "Multi-mode resource-constrained project scheduling problem with material ordering under bonus–penalty policies," TOP: An Official Journal of the Spanish Society of Statistics and Operations Research, Springer;Sociedad de Estadística e Investigación Operativa, vol. 25(1), pages 49-79, April.
  • Handle: RePEc:spr:topjnl:v:25:y:2017:i:1:d:10.1007_s11750-016-0415-2
    DOI: 10.1007/s11750-016-0415-2
    as

    Download full text from publisher

    File URL: http://link.springer.com/10.1007/s11750-016-0415-2
    File Function: Abstract
    Download Restriction: Access to the full text of the articles in this series is restricted.

    File URL: https://libkey.io/10.1007/s11750-016-0415-2?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Mika, Marek & Waligora, Grzegorz & Weglarz, Jan, 2008. "Tabu search for multi-mode resource-constrained project scheduling with schedule-dependent setup times," European Journal of Operational Research, Elsevier, vol. 187(3), pages 1238-1250, June.
    2. Coelho, José & Vanhoucke, Mario, 2011. "Multi-mode resource-constrained project scheduling using RCPSP and SAT solvers," European Journal of Operational Research, Elsevier, vol. 213(1), pages 73-82, August.
    3. Rainer Kolisch & Arno Sprecher & Andreas Drexl, 1995. "Characterization and Generation of a General Class of Resource-Constrained Project Scheduling Problems," Management Science, INFORMS, vol. 41(10), pages 1693-1703, October.
    4. V. Van Peteghem & M. Vanhoucke, 2009. "Using Resource Scarceness Characteristics to Solve the Multi-Mode Resource-Constrained Project Scheduling Problem," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 09/595, Ghent University, Faculty of Economics and Business Administration.
    5. Shadrokh, Shahram & Kianfar, Fereydoon, 2007. "A genetic algorithm for resource investment project scheduling problem, tardiness permitted with penalty," European Journal of Operational Research, Elsevier, vol. 181(1), pages 86-101, August.
    6. Sönke Hartmann, 2001. "Project Scheduling with Multiple Modes: A Genetic Algorithm," Annals of Operations Research, Springer, vol. 102(1), pages 111-135, February.
    7. Boctor, Fayez F., 1996. "A new and efficient heuristic for scheduling projects with resource restrictions and multiple execution modes," European Journal of Operational Research, Elsevier, vol. 90(2), pages 349-361, April.
    8. Rodica Brânzei & Giulio Ferrari & Vito Fragnelli & Stef Tijs, 2002. "Two Approaches to the Problem of Sharing Delay Costs in Joint Projects," Annals of Operations Research, Springer, vol. 109(1), pages 359-374, January.
    9. D. G. Malcolm & J. H. Roseboom & C. E. Clark & W. Fazar, 1959. "Application of a Technique for Research and Development Program Evaluation," Operations Research, INFORMS, vol. 7(5), pages 646-669, October.
    10. Arantza Estévez-Fernández & Peter Borm & Herbert Hamers, 2007. "Project games," International Journal of Game Theory, Springer;Game Theory Society, vol. 36(2), pages 149-176, October.
      • Estevez Fernandez, M.A. & Borm, P.E.M. & Hamers, H.J.M., 2005. "Project Games," Discussion Paper 2005-91, Tilburg University, Center for Economic Research.
      • Estevez Fernandez, M.A. & Borm, P.E.M. & Hamers, H.J.M., 2007. "Project games," Other publications TiSEM 809ba203-2bd2-48ce-ae6d-b, Tilburg University, School of Economics and Management.
      • Estevez Fernandez, M.A. & Borm, P.E.M. & Hamers, H.J.M., 2005. "Project Games," Other publications TiSEM 21fd9b62-93b6-4a8b-9bf4-4, Tilburg University, School of Economics and Management.
    11. Hartmann, Sonke & Sprecher, Arno, 1996. "A note on "hierarchical models for multi-project planning and scheduling"," European Journal of Operational Research, Elsevier, vol. 94(2), pages 377-383, October.
    12. F. Brian Talbot, 1982. "Resource-Constrained Project Scheduling with Time-Resource Tradeoffs: The Nonpreemptive Case," Management Science, INFORMS, vol. 28(10), pages 1197-1210, October.
    13. Joanna Józefowska & Marek Mika & Rafał Różycki & Grzegorz Waligóra & Jan Węglarz, 2001. "Simulated Annealing for Multi-Mode Resource-Constrained Project Scheduling," Annals of Operations Research, Springer, vol. 102(1), pages 137-155, February.
    14. Speranza, M. Grazia & Vercellis, Carlo, 1993. "Hierarchical models for multi-project planning and scheduling," European Journal of Operational Research, Elsevier, vol. 64(2), pages 312-325, January.
    15. Kolisch, Rainer & Sprecher, Arno, 1996. "PSPLIB - a project scheduling problem library," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 396, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    16. Peteghem, Vincent Van & Vanhoucke, Mario, 2010. "A genetic algorithm for the preemptive and non-preemptive multi-mode resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 201(2), pages 409-418, March.
    17. Mika, Marek & Waligora, Grzegorz & Weglarz, Jan, 2005. "Simulated annealing and tabu search for multi-mode resource-constrained project scheduling with positive discounted cash flows and different payment models," European Journal of Operational Research, Elsevier, vol. 164(3), pages 639-668, August.
    18. G. Bergantiños & E. Sánchez, 2002. "How to Distribute Costs Associated with a Delayed Project," Annals of Operations Research, Springer, vol. 109(1), pages 159-174, January.
    19. Elloumi, Sonda & Fortemps, Philippe, 2010. "A hybrid rank-based evolutionary algorithm applied to multi-mode resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 205(1), pages 31-41, August.
    20. Kolisch, Rainer & Hartmann, Sönke, 1999. "Heuristic algorithms for the resource-constrained project scheduling problem: classification and computational analysis," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 10966, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
    21. He, Zhengwen & Xu, Yu, 2008. "Multi-mode project payment scheduling problems with bonus-penalty structure," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1191-1207, September.
    22. J Alcaraz & C Maroto & R Ruiz, 2003. "Solving the Multi-Mode Resource-Constrained Project Scheduling Problem with genetic algorithms," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 54(6), pages 614-626, June.
    23. Weglarz, Jan & Józefowska, Joanna & Mika, Marek & Waligóra, Grzegorz, 2011. "Project scheduling with finite or infinite number of activity processing modes - A survey," European Journal of Operational Research, Elsevier, vol. 208(3), pages 177-205, February.
    24. Sprecher, Arno & Drexl, Andreas, 1998. "Multi-mode resource-constrained project scheduling by a simple, general and powerful sequencing algorithm," European Journal of Operational Research, Elsevier, vol. 107(2), pages 431-450, June.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Hartmann, Sönke & Briskorn, Dirk, 2022. "An updated survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 297(1), pages 1-14.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Weglarz, Jan & Józefowska, Joanna & Mika, Marek & Waligóra, Grzegorz, 2011. "Project scheduling with finite or infinite number of activity processing modes - A survey," European Journal of Operational Research, Elsevier, vol. 208(3), pages 177-205, February.
    2. Van Peteghem, Vincent & Vanhoucke, Mario, 2014. "An experimental investigation of metaheuristics for the multi-mode resource-constrained project scheduling problem on new dataset instances," European Journal of Operational Research, Elsevier, vol. 235(1), pages 62-72.
    3. Luis F. Machado-Domínguez & Carlos D. Paternina-Arboleda & Jorge I. Vélez & Agustin Barrios-Sarmiento, 2021. "A memetic algorithm to address the multi-node resource-constrained project scheduling problem," Journal of Scheduling, Springer, vol. 24(4), pages 413-429, August.
    4. Peteghem, Vincent Van & Vanhoucke, Mario, 2010. "A genetic algorithm for the preemptive and non-preemptive multi-mode resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 201(2), pages 409-418, March.
    5. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    6. V. Van Peteghem & M. Vanhoucke, 2008. "A Genetic Algorithm for the Multi-Mode Resource-Constrained Project Scheduling Problem," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 08/494, Ghent University, Faculty of Economics and Business Administration.
    7. Hartmann, Sönke & Briskorn, Dirk, 2008. "A survey of variants and extensions of the resource-constrained project scheduling problem," Working Paper Series 02/2008, Hamburg School of Business Administration (HSBA).
    8. Kolisch, R. & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Omega, Elsevier, vol. 29(3), pages 249-272, June.
    9. Zhengwen He & Nengmin Wang & Pengxiang Li, 2014. "Simulated annealing for financing cost distribution based project payment scheduling from a joint perspective," Annals of Operations Research, Springer, vol. 213(1), pages 203-220, February.
    10. Coelho, José & Vanhoucke, Mario, 2011. "Multi-mode resource-constrained project scheduling using RCPSP and SAT solvers," European Journal of Operational Research, Elsevier, vol. 213(1), pages 73-82, August.
    11. Luis F. Machado-Domínguez & Carlos D. Paternina-Arboleda & Jorge I. Vélez & Agustín Barrios-Sarmiento, 2022. "An adaptative bacterial foraging optimization algorithm for solving the MRCPSP with discounted cash flows," TOP: An Official Journal of the Spanish Society of Statistics and Operations Research, Springer;Sociedad de Estadística e Investigación Operativa, vol. 30(2), pages 221-248, July.
    12. V. Van Peteghem & M. Vanhoucke, 2009. "An Artificial Immune System for the Multi-Mode Resource-Constrained Project Scheduling Problem," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 09/555, Ghent University, Faculty of Economics and Business Administration.
    13. Dayal Madhukar & Verma, Sanjay, 2015. "Multi-processor Exact Procedures for Regular Measures of the Multi-mode RCPSP," IIMA Working Papers WP2015-03-25, Indian Institute of Management Ahmedabad, Research and Publication Department.
    14. He, Zhengwen & Liu, Renjing & Jia, Tao, 2012. "Metaheuristics for multi-mode capital-constrained project payment scheduling," European Journal of Operational Research, Elsevier, vol. 223(3), pages 605-613.
    15. Alfredo S. Ramos & Pablo A. Miranda-Gonzalez & Samuel Nucamendi-Guillén & Elias Olivares-Benitez, 2023. "A Formulation for the Stochastic Multi-Mode Resource-Constrained Project Scheduling Problem Solved with a Multi-Start Iterated Local Search Metaheuristic," Mathematics, MDPI, vol. 11(2), pages 1-25, January.
    16. Geiger, Martin Josef, 2017. "A multi-threaded local search algorithm and computer implementation for the multi-mode, resource-constrained multi-project scheduling problem," European Journal of Operational Research, Elsevier, vol. 256(3), pages 729-741.
    17. Elloumi, Sonda & Fortemps, Philippe, 2010. "A hybrid rank-based evolutionary algorithm applied to multi-mode resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 205(1), pages 31-41, August.
    18. Kellenbrink, Carolin & Helber, Stefan, 2015. "Scheduling resource-constrained projects with a flexible project structure," European Journal of Operational Research, Elsevier, vol. 246(2), pages 379-391.
    19. He, Naihui & Zhang, David Z. & Yuce, Baris, 2022. "Integrated multi-project planning and scheduling - a multiagent approach," European Journal of Operational Research, Elsevier, vol. 302(2), pages 688-699.
    20. Dayal Madhukar & Verma, Sanjay, 2014. "Breadth-first and Best-first Exact Procedures for Regular Measures of the Multi-mode RCPSP," IIMA Working Papers WP2014-10-04, Indian Institute of Management Ahmedabad, Research and Publication Department.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:spr:topjnl:v:25:y:2017:i:1:d:10.1007_s11750-016-0415-2. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Sonal Shukla or Springer Nature Abstracting and Indexing (email available below). General contact details of provider: http://www.springer.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.