A survey of variants and extensions of the resource-constrained project scheduling problem

Author

Listed:
  • Hartmann, Sönke
  • Briskorn, Dirk

Abstract

The resource-constrained project scheduling problem (RCPSP) consists of activities that must be scheduled subject to precedence and resource constraints such that the makespan is minimized. It has become a well-known standard problem in the context of project scheduling which has attracted numerous researchers who developed both exact and heuristic scheduling procedures. However, it is a rather basic model with assumptions that are too restrictive for many practical applications. Consequently, various extensions of the basic RCPSP have been developed. This paper gives an overview over these extensions. The extensions are classified according to the structure of the RCPSP. We summarize generalizations of the activity concept, of the precedence relations and of the resource constraints. Alternative objectives and approaches for scheduling multiple projects are discussed as well. In addition to popular variants and extensions such as multiple modes, minimal and maximal time lags, and net present value-based objectives, the paper also provides a survey of many less known concepts.

Suggested Citation

  • Hartmann, Sönke & Briskorn, Dirk, 2008. "A survey of variants and extensions of the resource-constrained project scheduling problem," Working Paper Series 02/2008, Hamburg School of Business Administration (HSBA).
  • Handle: RePEc:zbw:hsbawp:022008
    as

    Download full text from publisher

    File URL: https://www.econstor.eu/bitstream/10419/45542/1/657527556.pdf
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Mika, Marek & Waligora, Grzegorz & Weglarz, Jan, 2008. "Tabu search for multi-mode resource-constrained project scheduling with schedule-dependent setup times," European Journal of Operational Research, Elsevier, vol. 187(3), pages 1238-1250, June.
    2. Klein, Robert & Scholl, Armin, 1998. "Scattered branch and bound: an adaptive search strategy applied to resource-constrained project scheduling," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 14076, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
    3. D. Debels & M. Vanhoucke, 2006. "The impact of various activity assumptions on the lead-time and resource utilization of resource-constrained projects," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 06/385, Ghent University, Faculty of Economics and Business Administration.
    4. Shtub, Avraham & LeBlanc, Larry J. & Cai, Ziyong, 1996. "Scheduling programs with repetitive projects: A comparison of a simulated annealing, a genetic and a pair-wise swap algorithm," European Journal of Operational Research, Elsevier, vol. 88(1), pages 124-138, January.
    5. Gonçalves, J.F. & Mendes, J.J.M. & Resende, M.G.C., 2008. "A genetic algorithm for the resource constrained multi-project scheduling problem," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1171-1190, September.
    6. Sönke Hartmann, 2001. "Project Scheduling with Multiple Modes: A Genetic Algorithm," Annals of Operations Research, Springer, vol. 102(1), pages 111-135, February.
    7. Demeulemeester, Erik L. & Herroelen, Willy S., 1996. "An efficient optimal solution procedure for the preemptive resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 90(2), pages 334-348, April.
    8. Hartmann, Sonke & Kolisch, Rainer, 2000. "Experimental evaluation of state-of-the-art heuristics for the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 127(2), pages 394-407, December.
    9. Nalini Dayanand & Rema Padman, 2001. "Project Contracts and Payment Schedules: The Client's Problem," Management Science, INFORMS, vol. 47(12), pages 1654-1667, December.
    10. Rodica Brânzei & Giulio Ferrari & Vito Fragnelli & Stef Tijs, 2002. "Two Approaches to the Problem of Sharing Delay Costs in Joint Projects," Annals of Operations Research, Springer, vol. 109(1), pages 359-374, January.
    11. Rom, Walter O. & Tukel, Oya Icmeli & Muscatello, Joseph R., 2002. "MRP in a job shop environment using a resource constrained project scheduling model," Omega, Elsevier, vol. 30(4), pages 275-286, August.
    12. Al-Fawzan, M. A. & Haouari, Mohamed, 2005. "A bi-objective model for robust resource-constrained project scheduling," International Journal of Production Economics, Elsevier, vol. 96(2), pages 175-187, May.
    13. S Hartmann, 2000. "Packing problems and project scheduling models: an integrating perspective," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 51(9), pages 1083-1092, September.
    14. Robert Klein & Armin Scholl, 2000. "PROGRESS: Optimally solving the generalized resource-constrained project scheduling problem," Mathematical Methods of Operations Research, Springer;Gesellschaft für Operations Research (GOR);Nederlands Genootschap voor Besliskunde (NGB), vol. 52(3), pages 467-488, December.
    15. Heilmann, Roland, 2003. "A branch-and-bound procedure for the multi-mode resource-constrained project scheduling problem with minimum and maximum time lags," European Journal of Operational Research, Elsevier, vol. 144(2), pages 348-365, January.
    16. Hapke, Maciej & Jaszkiewicz, Andrzej & Slowinski, Roman, 1998. "Interactive analysis of multiple-criteria project scheduling problems," European Journal of Operational Research, Elsevier, vol. 107(2), pages 315-324, June.
    17. A. Kimms, 2001. "Maximizing the Net Present Value of a Project Under Resource Constraints Using a Lagrangian Relaxation Based Heuristic with Tight Upper Bounds," Annals of Operations Research, Springer, vol. 102(1), pages 221-236, February.
    18. De Reyck, Bert & Herroelen, Willy, 1999. "The multi-mode resource-constrained project scheduling problem with generalized precedence relations," European Journal of Operational Research, Elsevier, vol. 119(2), pages 538-556, December.
    19. Herroelen, Willy S. & Van Dommelen, Patrick & Demeulemeester, Erik L., 1997. "Project network models with discounted cash flows a guided tour through recent developments," European Journal of Operational Research, Elsevier, vol. 100(1), pages 97-121, July.
    20. Ulusoy, Gunduz & Cebelli, Serkan, 2000. "An equitable approach to the payment scheduling problem in project management," European Journal of Operational Research, Elsevier, vol. 127(2), pages 262-278, December.
    21. Mario Vanhoucke & Erik Demeulemeester & Willy Herroelen, 2001. "On Maximizing the Net Present Value of a Project Under Renewable Resource Constraints," Management Science, INFORMS, vol. 47(8), pages 1113-1121, August.
    22. G Zhu & J F Bard & G Yu, 2005. "Disruption management for resource-constrained project scheduling," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 56(4), pages 365-381, April.
    23. Rainer Kolisch & Arno Sprecher & Andreas Drexl, 1995. "Characterization and Generation of a General Class of Resource-Constrained Project Scheduling Problems," Management Science, INFORMS, vol. 41(10), pages 1693-1703, October.
    24. Shadrokh, Shahram & Kianfar, Fereydoon, 2007. "A genetic algorithm for resource investment project scheduling problem, tardiness permitted with penalty," European Journal of Operational Research, Elsevier, vol. 181(1), pages 86-101, August.
    25. Robert H. Doersch & James H. Patterson, 1977. "Scheduling a Project to Maximize Its Present Value: A Zero-One Programming Approach," Management Science, INFORMS, vol. 23(8), pages 882-889, April.
    26. Böttcher, Jan & Drexl, A. & Kolisch, R. & Salewski, F., 1999. "Project scheduling under partially renewable resource constraints," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 345, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
    27. Damay, Jean & Quilliot, Alain & Sanlaville, Eric, 2007. "Linear programming based algorithms for preemptive and non-preemptive RCPSP," European Journal of Operational Research, Elsevier, vol. 182(3), pages 1012-1022, November.
    28. Drexl, Andreas & Salewski, Frank, 1997. "Distribution requirements and compactness constraints in school timetabling," European Journal of Operational Research, Elsevier, vol. 102(1), pages 193-214, October.
    29. Brucker, Peter & Drexl, Andreas & Mohring, Rolf & Neumann, Klaus & Pesch, Erwin, 1999. "Resource-constrained project scheduling: Notation, classification, models, and methods," European Journal of Operational Research, Elsevier, vol. 112(1), pages 3-41, January.
    30. Icmeli-Tukel, Oya & Rom, Walter O., 1997. "Ensuring quality in resource constrained project scheduling," European Journal of Operational Research, Elsevier, vol. 103(3), pages 483-496, December.
    31. Viana, Ana & Pinho de Sousa, Jorge, 2000. "Using metaheuristics in multiobjective resource constrained project scheduling," European Journal of Operational Research, Elsevier, vol. 120(2), pages 359-374, January.
    32. Neumann, Klaus & Schwindt, Christoph & Trautmann, Norbert, 2005. "Scheduling of continuous and discontinuous material flows with intermediate storage restrictions," European Journal of Operational Research, Elsevier, vol. 165(2), pages 495-509, September.
    33. Drezet, L.-E. & Billaut, J.-C., 2008. "A project scheduling problem with labour constraints and time-dependent activities requirements," International Journal of Production Economics, Elsevier, vol. 112(1), pages 217-225, March.
    34. Kolisch, R., 2000. "Integrated scheduling, assembly area- and part-assignment for large-scale, make-to-order assemblies," International Journal of Production Economics, Elsevier, vol. 64(1-3), pages 127-141, March.
    35. Jan Böttcher & Andreas Drexl & Rainer Kolisch & Frank Salewski, 1999. "Project Scheduling Under Partially Renewable Resource Constraints," Management Science, INFORMS, vol. 45(4), pages 543-559, April.
    36. Rummel, Jeffrey L. & Walter, Zhiping & Dewan, Rajiv & Seidmann, Abraham, 2005. "Activity consolidation to improve responsiveness," European Journal of Operational Research, Elsevier, vol. 161(3), pages 683-703, March.
    37. Vanhoucke, Mario & Demeulemeester, Erik & Herroelen, Willy, 2003. "Progress payments in project scheduling problems," European Journal of Operational Research, Elsevier, vol. 148(3), pages 604-620, August.
    38. Kolisch, Rainer & Sprecher, Arno, 1996. "PSPLIB - a project scheduling problem library," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 396, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    39. Doerner, K.F. & Gutjahr, W.J. & Hartl, R.F. & Strauss, C. & Stummer, C., 2008. "Nature-inspired metaheuristics for multiobjective activity crashing," Omega, Elsevier, vol. 36(6), pages 1019-1037, December.
    40. I. Kurtulus & E. W. Davis, 1982. "Multi-Project Scheduling: Categorization of Heuristic Rules Performance," Management Science, INFORMS, vol. 28(2), pages 161-172, February.
    41. M. Vanhoucke, 2004. "Work Continuity Constraints In Project Scheduling," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 04/265, Ghent University, Faculty of Economics and Business Administration.
    42. Yang, Hsu-Hao & Chen, Yen-Liang, 2000. "Finding the critical path in an activity network with time-switch constraints," European Journal of Operational Research, Elsevier, vol. 120(3), pages 603-613, February.
    43. A Drexl & A Kimms, 2001. "Optimization guided lower and upper bounds for the resource investment problem," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 52(3), pages 340-351, March.
    44. Lova, Antonio & Maroto, Concepcion & Tormos, Pilar, 2000. "A multicriteria heuristic method to improve resource allocation in multiproject scheduling," European Journal of Operational Research, Elsevier, vol. 127(2), pages 408-424, December.
    45. Kolisch, Rainer & Hartmann, Sonke, 2006. "Experimental investigation of heuristics for resource-constrained project scheduling: An update," European Journal of Operational Research, Elsevier, vol. 174(1), pages 23-37, October.
    46. Demeulemeester, Erik L. & Herroelen, Willy S., 1996. "Modelling setup times, process batches and transfer batches using activity network logic," European Journal of Operational Research, Elsevier, vol. 89(2), pages 355-365, March.
    47. Slowinski, Roman & Soniewicki, Boleslaw & Weglarz, Jan, 1994. "DSS for multiobjective project scheduling," European Journal of Operational Research, Elsevier, vol. 79(2), pages 220-229, December.
    48. Slowinski, Roman, 1981. "Multiobjective network scheduling with efficient use of renewable and nonrenewable resources," European Journal of Operational Research, Elsevier, vol. 7(3), pages 265-273, July.
    49. Buddhakulsomsiri, Jirachai & Kim, David S., 2006. "Properties of multi-mode resource-constrained project scheduling problems with resource vacations and activity splitting," European Journal of Operational Research, Elsevier, vol. 175(1), pages 279-295, November.
    50. Bartels, J.-H. & Zimmermann, J., 2009. "Scheduling tests in automotive R&D projects," European Journal of Operational Research, Elsevier, vol. 193(3), pages 805-819, March.
    51. Tavares, L. V., 2002. "A review of the contribution of Operational Research to Project Management," European Journal of Operational Research, Elsevier, vol. 136(1), pages 1-18, January.
    52. Buddhakulsomsiri, Jirachai & Kim, David S., 2007. "Priority rule-based heuristic for multi-mode resource-constrained project scheduling problems with resource vacations and activity splitting," European Journal of Operational Research, Elsevier, vol. 178(2), pages 374-390, April.
    53. Kolisch, R. & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Omega, Elsevier, vol. 29(3), pages 249-272, June.
    54. Agrawal, M. K. & Elmaghraby, S. E. & Herroelen, W. S., 1996. ": A generator of testsets for project activity nets," European Journal of Operational Research, Elsevier, vol. 90(2), pages 376-382, April.
    55. Bandelloni, M. & Tucci, M. & Rinaldi, R., 1994. "Optimal resource leveling using non-serial dyanamic programming," European Journal of Operational Research, Elsevier, vol. 78(2), pages 162-177, October.
    56. Tiwari, Vikram & Patterson, James H. & Mabert, Vincent A., 2009. "Scheduling projects with heterogeneous resources to meet time and quality objectives," European Journal of Operational Research, Elsevier, vol. 193(3), pages 780-790, March.
    57. Drexl, Andreas & Nissen, Rudiger & Patterson, James H. & Salewski, Frank, 2000. "ProGen/[pi]x - An instance generator for resource-constrained project scheduling problems with partially renewable resources and further extensions," European Journal of Operational Research, Elsevier, vol. 125(1), pages 59-72, August.
    58. Chen, Jiaqiong & Askin, Ronald G., 2009. "Project selection, scheduling and resource allocation with time dependent returns," European Journal of Operational Research, Elsevier, vol. 193(1), pages 23-34, February.
    59. Nazareth, Terence & Verma, Sanjay & Bhattacharya, Subir & Bagchi, Amitava, 1999. "The multiple resource constrained project scheduling problem: A breadth-first approach," European Journal of Operational Research, Elsevier, vol. 112(2), pages 347-366, January.
    60. Bouleimen, K. & Lecocq, H., 2003. "A new efficient simulated annealing algorithm for the resource-constrained project scheduling problem and its multiple mode version," European Journal of Operational Research, Elsevier, vol. 149(2), pages 268-281, September.
    61. Mika, Marek & Waligora, Grzegorz & Weglarz, Jan, 2005. "Simulated annealing and tabu search for multi-mode resource-constrained project scheduling with positive discounted cash flows and different payment models," European Journal of Operational Research, Elsevier, vol. 164(3), pages 639-668, August.
    62. Tukel, Oya Icmeli & Wasti, S. Nazli, 2001. "Analysis of supplier buyer relationships using resource constrained project scheduling strategies," European Journal of Operational Research, Elsevier, vol. 129(2), pages 271-276, March.
    63. Gündüz Ulusoy & Funda Sivrikaya-Şerifoğlu & Şule Şahin, 2001. "Four Payment Models for the Multi-Mode Resource Constrained Project Scheduling Problem with Discounted Cash Flows," Annals of Operations Research, Springer, vol. 102(1), pages 237-261, February.
    64. Guidong Zhu & Jonathan F. Bard & Gang Yu, 2006. "A Branch-and-Cut Procedure for the Multimode Resource-Constrained Project-Scheduling Problem," INFORMS Journal on Computing, INFORMS, vol. 18(3), pages 377-390, August.
    65. Joanna Józefowska & Marek Mika & Rafał Różycki & Grzegorz Waligóra & Jan Weglarz, 2000. "Solving the discrete-continuous project scheduling problem via its discretization," Mathematical Methods of Operations Research, Springer;Gesellschaft für Operations Research (GOR);Nederlands Genootschap voor Besliskunde (NGB), vol. 52(3), pages 489-499, December.
    66. J Alcaraz & C Maroto & R Ruiz, 2003. "Solving the Multi-Mode Resource-Constrained Project Scheduling Problem with genetic algorithms," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 54(6), pages 614-626, June.
    67. Rolf H. Möhring & Andreas S. Schulz & Frederik Stork & Marc Uetz, 2003. "Solving Project Scheduling Problems by Minimum Cut Computations," Management Science, INFORMS, vol. 49(3), pages 330-350, March.
    68. Chen, Vincent Y. X., 1994. "A 0-1 goal programming model for scheduling multiple maintenance projects at a copper mine," European Journal of Operational Research, Elsevier, vol. 76(1), pages 176-191, July.
    69. Neumann, K. & Zimmermann, J., 2000. "Procedures for resource leveling and net present value problems in project scheduling with general temporal and resource constraints," European Journal of Operational Research, Elsevier, vol. 127(2), pages 425-443, December.
    70. Herroelen, Willy & Leus, Roel, 2005. "Project scheduling under uncertainty: Survey and research potentials," European Journal of Operational Research, Elsevier, vol. 165(2), pages 289-306, September.
    71. Giuseppe Confessore & Stefano Giordani & Silvia Rismondo, 2007. "A market-based multi-agent system model for decentralized multi-project scheduling," Annals of Operations Research, Springer, vol. 150(1), pages 115-135, March.
    72. Hartmann, Sönke & Kolisch, R., 2000. "Experimental evaluation of state-of-the-art heuristics for the resource-constrained project scheduling problem," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 11180, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
    73. Haase, Knut & Latteier, Jorg & Schirmer, Andreas, 1998. "The course scheduling problem at Lufthansa Technical Training," European Journal of Operational Research, Elsevier, vol. 110(3), pages 441-456, November.
    74. Huan Neng Chiu & Deng Maw Tsai, 2002. "An efficient search procedure for the resource-constrained multi-project scheduling problem with discounted cash flows," Construction Management and Economics, Taylor & Francis Journals, vol. 20(1), pages 55-66.
    75. Lawrence, Stephen R. & Morton, Thomas E., 1993. "Resource-constrained multi-project scheduling with tardy costs: Comparing myopic, bottleneck, and resource pricing heuristics," European Journal of Operational Research, Elsevier, vol. 64(2), pages 168-187, January.
    76. Rainer Kolisch & Konrad Meyer, 2006. "Selection and Scheduling of Pharmaceutical Research Projects," International Series in Operations Research & Management Science, in: Joanna Józefowska & Jan Weglarz (ed.), Perspectives in Modern Project Scheduling, chapter 0, pages 321-344, Springer.
    77. Vanhoucke, Mario & Coelho, Jose & Debels, Dieter & Maenhout, Broos & Tavares, Luis V., 2008. "An evaluation of the adequacy of project network generators with systematically sampled networks," European Journal of Operational Research, Elsevier, vol. 187(2), pages 511-524, June.
    78. Alvarez-Valdes, R. & Crespo, E. & Tamarit, J.M. & Villa, F., 2008. "GRASP and path relinking for project scheduling under partially renewable resources," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1153-1170, September.
    79. Jacek Błażewicz & Klaus H. Ecker & Erwin Pesch & Günter Schmidt & Jan Węglarz, 2007. "Handbook on Scheduling," International Handbooks on Information Systems, Springer, number 978-3-540-32220-7, November.
    80. N.R. Achuthan & A. Hardjawidjaja, 2001. "Project Scheduling under Time Dependent Costs – A Branch and Bound Algorithm," Annals of Operations Research, Springer, vol. 108(1), pages 55-74, November.
    81. Etgar, Ran & Shtub, Avraham & LeBlanc, Larry J., 1997. "Scheduling projects to maximize net present value -- the case of time-dependent, contingent cash flows," European Journal of Operational Research, Elsevier, vol. 96(1), pages 90-96, January.
    82. Oya Icmeli & S. Selcuk Erenguc, 1996. "A Branch and Bound Procedure for the Resource Constrained Project Scheduling Problem with Discounted Cash Flows," Management Science, INFORMS, vol. 42(10), pages 1395-1408, October.
    83. Klein, Robert & Scholl, Armin, 1998. "PROGRESS: Optimally solving the generalized resource-constrained project scheduling problem," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 14077, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
    84. Bianco, L. & Dell'Olmo, P. & Grazia Speranza, M., 1998. "Heuristics for multimode scheduling problems with dedicated resources," European Journal of Operational Research, Elsevier, vol. 107(2), pages 260-271, June.
    85. Salewski, Frank & Schirmer, Andreas & Drexl, Andreas, 1997. "Project scheduling under resource and mode identity constraints: Model, complexity, methods, and application," European Journal of Operational Research, Elsevier, vol. 102(1), pages 88-110, October.
    86. Sung, C. S. & Lim, S. K., 1994. "A project activity scheduling problem with net present value measure," International Journal of Production Economics, Elsevier, vol. 37(2-3), pages 177-187, December.
    87. Akkan, Can & Drexl, Andreas & Kimms, Alf, 2005. "Network decomposition-based benchmark results for the discrete time-cost tradeoff problem," European Journal of Operational Research, Elsevier, vol. 165(2), pages 339-358, September.
    88. Kobylanski, Przemyslaw & Kuchta, Dorota, 2007. "A note on the paper by M. A. Al-Fawzan and M. Haouari about a bi-objective problem for robust resource-constrained project scheduling," International Journal of Production Economics, Elsevier, vol. 107(2), pages 496-501, June.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Yangyang Liang & Nanfang Cui & Tian Wang & Erik Demeulemeester, 2019. "Robust resource-constrained max-NPV project scheduling with stochastic activity duration," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 41(1), pages 219-254, March.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    2. Weglarz, Jan & Józefowska, Joanna & Mika, Marek & Waligóra, Grzegorz, 2011. "Project scheduling with finite or infinite number of activity processing modes - A survey," European Journal of Operational Research, Elsevier, vol. 208(3), pages 177-205, February.
    3. Chen, Jiaqiong & Askin, Ronald G., 2009. "Project selection, scheduling and resource allocation with time dependent returns," European Journal of Operational Research, Elsevier, vol. 193(1), pages 23-34, February.
    4. He, Zhengwen & Wang, Nengmin & Jia, Tao & Xu, Yu, 2009. "Simulated annealing and tabu search for multi-mode project payment scheduling," European Journal of Operational Research, Elsevier, vol. 198(3), pages 688-696, November.
    5. Kolisch, R. & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Omega, Elsevier, vol. 29(3), pages 249-272, June.
    6. He, Zhengwen & Liu, Renjing & Jia, Tao, 2012. "Metaheuristics for multi-mode capital-constrained project payment scheduling," European Journal of Operational Research, Elsevier, vol. 223(3), pages 605-613.
    7. Peteghem, Vincent Van & Vanhoucke, Mario, 2010. "A genetic algorithm for the preemptive and non-preemptive multi-mode resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 201(2), pages 409-418, March.
    8. Zhengwen He & Nengmin Wang & Pengxiang Li, 2014. "Simulated annealing for financing cost distribution based project payment scheduling from a joint perspective," Annals of Operations Research, Springer, vol. 213(1), pages 203-220, February.
    9. Van Peteghem, Vincent & Vanhoucke, Mario, 2014. "An experimental investigation of metaheuristics for the multi-mode resource-constrained project scheduling problem on new dataset instances," European Journal of Operational Research, Elsevier, vol. 235(1), pages 62-72.
    10. Dayal Madhukar & Verma, Sanjay, 2015. "Multi-processor Exact Procedures for Regular Measures of the Multi-mode RCPSP," IIMA Working Papers WP2015-03-25, Indian Institute of Management Ahmedabad, Research and Publication Department.
    11. Mika, Marek & Waligora, Grzegorz & Weglarz, Jan, 2005. "Simulated annealing and tabu search for multi-mode resource-constrained project scheduling with positive discounted cash flows and different payment models," European Journal of Operational Research, Elsevier, vol. 164(3), pages 639-668, August.
    12. Abdollah Arasteh, 2020. "Considering Project Management Activities for Engineering Design Groups," SN Operations Research Forum, Springer, vol. 1(4), pages 1-29, December.
    13. Cédric Verbeeck & Vincent Peteghem & Mario Vanhoucke & Pieter Vansteenwegen & El-Houssaine Aghezzaf, 2017. "A metaheuristic solution approach for the time-constrained project scheduling problem," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 39(2), pages 353-371, March.
    14. V. Van Peteghem & M. Vanhoucke, 2009. "Using Resource Scarceness Characteristics to Solve the Multi-Mode Resource-Constrained Project Scheduling Problem," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 09/595, Ghent University, Faculty of Economics and Business Administration.
    15. He, Yukang & Jia, Tao & Zheng, Weibo, 2023. "Tabu search for dedicated resource-constrained multiproject scheduling to minimise the maximal cash flow gap under uncertainty," European Journal of Operational Research, Elsevier, vol. 310(1), pages 34-52.
    16. Hartmann, Sönke, 2011. "Project scheduling with resource capacities and requests varying with time," Working Paper Series 01/2011, Hamburg School of Business Administration (HSBA).
    17. Coelho, José & Vanhoucke, Mario, 2011. "Multi-mode resource-constrained project scheduling using RCPSP and SAT solvers," European Journal of Operational Research, Elsevier, vol. 213(1), pages 73-82, August.
    18. Anıl Can & Gündüz Ulusoy, 2014. "Multi-project scheduling with two-stage decomposition," Annals of Operations Research, Springer, vol. 217(1), pages 95-116, June.
    19. Gómez Sánchez, Mariam & Lalla-Ruiz, Eduardo & Fernández Gil, Alejandro & Castro, Carlos & Voß, Stefan, 2023. "Resource-constrained multi-project scheduling problem: A survey," European Journal of Operational Research, Elsevier, vol. 309(3), pages 958-976.
    20. Buddhakulsomsiri, Jirachai & Kim, David S., 2006. "Properties of multi-mode resource-constrained project scheduling problems with resource vacations and activity splitting," European Journal of Operational Research, Elsevier, vol. 175(1), pages 279-295, November.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:zbw:hsbawp:022008. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: ZBW - Leibniz Information Centre for Economics (email available below). General contact details of provider: https://edirc.repec.org/data/hsbaade.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.