Resource-Constrained Project Scheduling with Time-Resource Tradeoffs: The Nonpreemptive Case

Contents:

Author Info

  • F. Brian Talbot

    (University of Michigan)

Registered author(s):

    Abstract

    This paper introduces methods for formulating and solving a general class of nonpreemptive resource-constrained project scheduling problems in which the duration of each job is a function of the resources committed to it. The approach is broad enough to permit the evaluation of numerous time or resource-based objective functions, while simultaneously taking into account a variety of constraint types. Typical of the objective functions permitted are minimize project duration, minimize project cost given performance payments and penalties, and minimize the consumption of a critical resource. Resources which may be considered include those which are limited on a period-to-period basis such as skilled labor, as well as those such as money, which are consumed and constrained over the life of the project. At the planning stage the user of this approach is permitted to identify several alternative ways, or modes, of accomplishing each job in the project. Each mode may have a different duration, reflecting the magnitude and mix of the resources allocated to it. At the scheduling phase, the procedure derives a solution which specifies how each job should be performed, that is, which mode should be selected, and when each mode should be scheduled. In order to make the presentation concrete, this paper focuses on two problems: given multiple resource restrictions, minimize project completion time, and minimize project cost. The latter problem is also known as the resource-constrained time-cost tradeoff problem. Computational results indicate that the procedures provide cost-effective optimal solutions for small problems and good heuristic solutions for larger problems. The programmed solution algorithms are relatively simple and require only modest computing facilities, which permits them to be potentially useful scheduling tools for organizations having small computer systems.

    Download Info

    If you experience problems downloading a file, check if you have the proper application to view it first. In case of further problems read the IDEAS help page. Note that these files are not on the IDEAS site. Please be patient as the files may be large.
    File URL: http://dx.doi.org/10.1287/mnsc.28.10.1197
    Download Restriction: no

    Bibliographic Info

    Article provided by INFORMS in its journal Management Science.

    Volume (Year): 28 (1982)
    Issue (Month): 10 (October)
    Pages: 1197-1210

    as in new window
    Handle: RePEc:inm:ormnsc:v:28:y:1982:i:10:p:1197-1210

    Contact details of provider:
    Postal: 7240 Parkway Drive, Suite 300, Hanover, MD 21076 USA
    Phone: +1-443-757-3500
    Fax: 443-757-3515
    Email:
    Web page: http://www.informs.org/
    More information through EDIRC

    Related research

    Keywords: project management: resource constraints; programming: integer algorithms; enumerative; industries: construction;

    References

    No references listed on IDEAS
    You can help add them by filling out this form.

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as in new window

    Cited by:
    1. Mori, Masao & Tseng, Ching Chih, 1997. "A genetic algorithm for multi-mode resource constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 100(1), pages 134-141, July.
    2. Vo[ss], Stefan & Witt, Andreas, 2007. "Hybrid flow shop scheduling as a multi-mode multi-project scheduling problem with batching requirements: A real-world application," International Journal of Production Economics, Elsevier, vol. 105(2), pages 445-458, February.
    3. Sprecher, Arno & Kolisch, Rainer & Drexl, Andreas, 1995. "Semi-active, active, and non-delay schedules for the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 80(1), pages 94-102, January.
    4. Samaddar, Subhashish & Rabinowitz, Gad & Zhang, Guoqiang Peter, 2005. "An experimental analysis of solution performance in a resource sharing and scheduling problem," European Journal of Operational Research, Elsevier, vol. 165(1), pages 139-156, August.
    5. De Reyck, Bert & Herroelen, Willy, 1996. "On the use of the complexity index as a measure of complexity in activity networks," European Journal of Operational Research, Elsevier, vol. 91(2), pages 347-366, June.
    6. Martinez, Michael A. & Newman, Alexandra M., 2011. "A solution approach for optimizing long- and short-term production scheduling at LKAB's Kiruna mine," European Journal of Operational Research, Elsevier, vol. 211(1), pages 184-197, May.
    7. Tiwari, Vikram & Patterson, James H. & Mabert, Vincent A., 2009. "Scheduling projects with heterogeneous resources to meet time and quality objectives," European Journal of Operational Research, Elsevier, vol. 193(3), pages 780-790, March.
    8. Ulusoy, Gunduz & Ozdamar, Linet, 1996. "A framework for an interactive project scheduling system under limited resources," European Journal of Operational Research, Elsevier, vol. 90(2), pages 362-375, April.
    9. Kolisch, Rainer & Sprecher, Arno, 1997. "PSPLIB - A project scheduling problem library : OR Software - ORSEP Operations Research Software Exchange Program," European Journal of Operational Research, Elsevier, vol. 96(1), pages 205-216, January.
    10. Karen Puttkammer & Rainer Kleber & Tobias Schulz & Karl Inderfurth, 2011. "Simultane Maschinenbelegungs- und Personaleinsatzplanung in KMUs anhand eines Fallbeispiels aus der Druckereibranche," FEMM Working Papers 110010, Otto-von-Guericke University Magdeburg, Faculty of Economics and Management.
    11. Weglarz, Jan & Józefowska, Joanna & Mika, Marek & Waligóra, Grzegorz, 2011. "Project scheduling with finite or infinite number of activity processing modes - A survey," European Journal of Operational Research, Elsevier, vol. 208(3), pages 177-205, February.
    12. Boctor, Fayez F., 1996. "A new and efficient heuristic for scheduling projects with resource restrictions and multiple execution modes," European Journal of Operational Research, Elsevier, vol. 90(2), pages 349-361, April.
    13. Browning, Tyson R. & Yassine, Ali A., 2010. "Resource-constrained multi-project scheduling: Priority rule performance revisited," International Journal of Production Economics, Elsevier, vol. 126(2), pages 212-228, August.
    14. Chen, Shih-Pin & Tsai, Ming-Jiun, 2011. "Time-cost trade-off analysis of project networks in fuzzy environments," European Journal of Operational Research, Elsevier, vol. 212(2), pages 386-397, July.
    15. V. Van Peteghem & M. Vanhoucke, 2008. "A Genetic Algorithm for the Multi-Mode Resource-Constrained Project Scheduling Problem," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 08/494, Ghent University, Faculty of Economics and Business Administration.
    16. V. Van Peteghem & M. Vanhoucke, 2009. "An Artificial Immune System for the Multi-Mode Resource-Constrained Project Scheduling Problem," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 09/555, Ghent University, Faculty of Economics and Business Administration.
    17. Salewski, Frank & Schirmer, Andreas & Drexl, Andreas, 1997. "Project scheduling under resource and mode identity constraints: Model, complexity, methods, and application," European Journal of Operational Research, Elsevier, vol. 102(1), pages 88-110, October.
    18. Bianco, L. & Dell'Olmo, P. & Grazia Speranza, M., 1998. "Heuristics for multimode scheduling problems with dedicated resources," European Journal of Operational Research, Elsevier, vol. 107(2), pages 260-271, June.
    19. Lova, Antonio & Tormos, Pilar & Cervantes, Mariamar & Barber, Federico, 2009. "An efficient hybrid genetic algorithm for scheduling projects with resource constraints and multiple execution modes," International Journal of Production Economics, Elsevier, vol. 117(2), pages 302-316, February.
    20. Ahn, Taeho & Erenguc, S. Selcuk, 1998. "The resource constrained project scheduling problem with multiple crashable modes: A heuristic procedure," European Journal of Operational Research, Elsevier, vol. 107(2), pages 250-259, June.

    Lists

    This item is not listed on Wikipedia, on a reading list or among the top items on IDEAS.

    Statistics

    Access and download statistics

    Corrections

    When requesting a correction, please mention this item's handle: RePEc:inm:ormnsc:v:28:y:1982:i:10:p:1197-1210. See general information about how to correct material in RePEc.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: (Mirko Janc).

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If references are entirely missing, you can add them using this form.

    If the full references list an item that is present in RePEc, but the system did not link to it, you can help with this form.

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your profile, as there may be some citations waiting for confirmation.

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.