Metaheuristics for multi-mode capital-constrained project payment scheduling

Contents:

Author Info

  • He, Zhengwen
  • Liu, Renjing
  • Jia, Tao
Registered author(s):

    Abstract

    This paper involves the multi-mode capital-constrained project payment scheduling problem, where the objective is to assign activity modes and payments so as to maximize the net present value (NPV) of the contractor under the constraint of capital availability. In the light of different payment patterns adopted, four optimization models are constructed using the event-based method. For the NP-hardness of the problem, metaheuristics, including tabu search and simulated annealing, are developed and compared with multi-start iterative improvement and random sampling based on a computational experiment performed on a data set generated randomly. The results indicate that the loop nested tabu search is the most promising procedure for the problem studied. Moreover, the effects of several key parameters on the contractor’s NPV are investigated and the following conclusions are drawn: The contractor’s NPV rises with the increase of the contractor’s initial capital availability, the payment number, the payment proportion, or the project deadline; the contractor has a decreasing marginal return as the contractor’s initial capital availability goes up; the contractor’s NPVs under the milestone event based payment pattern are not less than those under the other three payment patterns.

    Download Info

    If you experience problems downloading a file, check if you have the proper application to view it first. In case of further problems read the IDEAS help page. Note that these files are not on the IDEAS site. Please be patient as the files may be large.
    File URL: http://www.sciencedirect.com/science/article/pii/S037722171200536X
    Download Restriction: Full text for ScienceDirect subscribers only

    As the access to this document is restricted, you may want to look for a different version under "Related research" (further below) or search for a different version of it.

    Bibliographic Info

    Article provided by Elsevier in its journal European Journal of Operational Research.

    Volume (Year): 223 (2012)
    Issue (Month): 3 ()
    Pages: 605-613

    as in new window
    Handle: RePEc:eee:ejores:v:223:y:2012:i:3:p:605-613

    Contact details of provider:
    Web page: http://www.elsevier.com/locate/eor

    Related research

    Keywords: Project scheduling; Payments; Net present value; Capital constraint; Metaheuristics;

    References

    References listed on IDEAS
    Please report citation or reference errors to , or , if you are the registered author of the cited work, log in to your RePEc Author Service profile, click on "citations" and make appropriate adjustments.:
    as in new window
    1. Brucker, Peter & Drexl, Andreas & Mohring, Rolf & Neumann, Klaus & Pesch, Erwin, 1999. "Resource-constrained project scheduling: Notation, classification, models, and methods," European Journal of Operational Research, Elsevier, vol. 112(1), pages 3-41, January.
    2. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    3. He, Zhengwen & Xu, Yu, 2008. "Multi-mode project payment scheduling problems with bonus-penalty structure," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1191-1207, September.
    4. Weglarz, Jan & Józefowska, Joanna & Mika, Marek & Waligóra, Grzegorz, 2011. "Project scheduling with finite or infinite number of activity processing modes - A survey," European Journal of Operational Research, Elsevier, vol. 208(3), pages 177-205, February.
    5. Bouleimen, K. & Lecocq, H., 2003. "A new efficient simulated annealing algorithm for the resource-constrained project scheduling problem and its multiple mode version," European Journal of Operational Research, Elsevier, vol. 149(2), pages 268-281, September.
    6. Hapke, Maciej & Jaszkiewicz, Andrzej & Slowinski, Roman, 1998. "Interactive analysis of multiple-criteria project scheduling problems," European Journal of Operational Research, Elsevier, vol. 107(2), pages 315-324, June.
    7. Mika, Marek & Waligora, Grzegorz & Weglarz, Jan, 2005. "Simulated annealing and tabu search for multi-mode resource-constrained project scheduling with positive discounted cash flows and different payment models," European Journal of Operational Research, Elsevier, vol. 164(3), pages 639-668, August.
    8. Robert H. Doersch & James H. Patterson, 1977. "Scheduling a Project to Maximize Its Present Value: A Zero-One Programming Approach," Management Science, INFORMS, vol. 23(8), pages 882-889, April.
    9. Waligóra, Grzegorz, 2009. "Tabu search for discrete-continuous scheduling problems with heuristic continuous resource allocation," European Journal of Operational Research, Elsevier, vol. 193(3), pages 849-856, March.
    10. Mika, Marek & Waligora, Grzegorz & Weglarz, Jan, 2008. "Tabu search for multi-mode resource-constrained project scheduling with schedule-dependent setup times," European Journal of Operational Research, Elsevier, vol. 187(3), pages 1238-1250, June.
    11. Shtub, Avraham & LeBlanc, Larry J. & Cai, Ziyong, 1996. "Scheduling programs with repetitive projects: A comparison of a simulated annealing, a genetic and a pair-wise swap algorithm," European Journal of Operational Research, Elsevier, vol. 88(1), pages 124-138, January.
    12. Lambrechts, Olivier & Demeulemeester, Erik & Herroelen, Willy, 2008. "A tabu search procedure for developing robust predictive project schedules," International Journal of Production Economics, Elsevier, vol. 111(2), pages 493-508, February.
    13. Kolisch, R. & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Omega, Elsevier, vol. 29(3), pages 249-272, June.
    14. He, Zhengwen & Wang, Nengmin & Jia, Tao & Xu, Yu, 2009. "Simulated annealing and tabu search for multi-mode project payment scheduling," European Journal of Operational Research, Elsevier, vol. 198(3), pages 688-696, November.
    15. Herroelen, Willy S. & Van Dommelen, Patrick & Demeulemeester, Erik L., 1997. "Project network models with discounted cash flows a guided tour through recent developments," European Journal of Operational Research, Elsevier, vol. 100(1), pages 97-121, July.
    16. A. H. Russell, 1970. "Cash Flows in Networks," Management Science, INFORMS, vol. 16(5), pages 357-373, January.
    17. Kolisch, Rainer & Hartmann, Sönke, 1999. "Heuristic algorithms for the resource-constrained project scheduling problem: classification and computational analysis," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 10966, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
    18. Tsai, Ying-Wei & D. Gemmill, Douglas, 1998. "Using tabu search to schedule activities of stochastic resource-constrained projects," European Journal of Operational Research, Elsevier, vol. 111(1), pages 129-141, November.
    19. Slowinski, Roman & Soniewicki, Boleslaw & Weglarz, Jan, 1994. "DSS for multiobjective project scheduling," European Journal of Operational Research, Elsevier, vol. 79(2), pages 220-229, December.
    20. Kolisch, Rainer & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Publications of Darmstadt Technical University, Institute for Business Studies (BWL) 8114, Darmstadt Technical University, Department of Business Administration, Economics and Law, Institute for Business Studies (BWL).
    21. Ulusoy, Gunduz & Cebelli, Serkan, 2000. "An equitable approach to the payment scheduling problem in project management," European Journal of Operational Research, Elsevier, vol. 127(2), pages 262-278, December.
    22. Etgar, Ran & Shtub, Avraham & LeBlanc, Larry J., 1997. "Scheduling projects to maximize net present value -- the case of time-dependent, contingent cash flows," European Journal of Operational Research, Elsevier, vol. 96(1), pages 90-96, January.
    23. Nalini Dayanand & Rema Padman, 2001. "Project Contracts and Payment Schedules: The Client's Problem," Management Science, INFORMS, vol. 47(12), pages 1654-1667, December.
    24. Viana, Ana & Pinho de Sousa, Jorge, 2000. "Using metaheuristics in multiobjective resource constrained project scheduling," European Journal of Operational Research, Elsevier, vol. 120(2), pages 359-374, January.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as in new window

    Cited by:
    1. Zhang, Jingwen & Elmaghraby, Salah E., 2014. "The relevance of the “alphorn of uncertainty” to the financial management of projects under uncertainty," European Journal of Operational Research, Elsevier, vol. 238(1), pages 65-76.

    Lists

    This item is not listed on Wikipedia, on a reading list or among the top items on IDEAS.

    Statistics

    Access and download statistics

    Corrections

    When requesting a correction, please mention this item's handle: RePEc:eee:ejores:v:223:y:2012:i:3:p:605-613. See general information about how to correct material in RePEc.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: (Zhang, Lei).

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If references are entirely missing, you can add them using this form.

    If the full references list an item that is present in RePEc, but the system did not link to it, you can help with this form.

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your profile, as there may be some citations waiting for confirmation.

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.