Ranking the prevalence of construction cost overrun risk factors in completion of public-private partnership projects: A case of the Sondu-Miriu hydro-electric power project in Kenya

Author

Listed:
  • Pamela Akinyi Oyieyo

    (School of Open and Distance Learning,Department of Extra Mural StudiesUniversity of Nairobi, Nairobi –00100, Kenya)

  • Charles M. Rambo

    (School of Open and Distance Learning,Department of Extra Mural StudiesUniversity of Nairobi, Nairobi –00100, Kenya)

  • Anne Ndiritu

    (School of Open and Distance Learning,Department of Extra Mural StudiesUniversity of Nairobi, Nairobi –00100, Kenya)

Abstract

The purpose of the study was to identify and rank the prevalence and severity of risk factors construction cost overrun in Public-Private Partnership projects using a case study of Sondu-Miriu Hydroelectric Power Project in Kisumu County, Kenya. This study adopted a descriptive design and collected quantitative data analysed quantitatively using descriptive statistics. In total, 85 persons were identified to have taken part in the management and implementation of the study from whom a sample size of 71 participants was obtained. Questionnaires were emailed to the participants providing details of the study and requesting their participation. The study ranked the risk factors based on prevalence and severity from most prevalently severe to least prevalently severe as design changes, emerging tasks affecting delivery, construction task breakdown structure, design variations and failure of contractors to complete different tasks. Thus, stakeholders should participate fully in the project from design to avoid design changes leading to cost overrun. During implementation, the contractor and construction manager should device mechanisms to anticipate changes in the political environment as such changes determines government policies and decisions affecting the project funding, design and scope. Key Words: Prevalence, Cost Overrun, Risk Factors, Construction Projects, Public-Private Partnership

Suggested Citation

  • Pamela Akinyi Oyieyo & Charles M. Rambo & Anne Ndiritu, 2020. "Ranking the prevalence of construction cost overrun risk factors in completion of public-private partnership projects: A case of the Sondu-Miriu hydro-electric power project in Kenya," International Journal of Research in Business and Social Science (2147-4478), Center for the Strategic Studies in Business and Finance, vol. 9(5), pages 351-356, September.
  • Handle: RePEc:rbs:ijbrss:v:9:y:2020:i:5:p:351-356
    DOI: 10.20525/ijrbs.v9i5.863
    as

    Download full text from publisher

    File URL: https://www.ssbfnet.com/ojs/index.php/ijrbs/article/view/863/670
    Download Restriction: no

    File URL: https://doi.org/10.20525/ijrbs.v9i5.863
    Download Restriction: no

    File URL: https://libkey.io/10.20525/ijrbs.v9i5.863?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Asheem Shrestha & Jolanta Tamošaitienė & Igor Martek & M Reza Hosseini & David J Edwards, 2019. "A Principal-Agent Theory Perspective on PPP Risk Allocation," Sustainability, MDPI, vol. 11(22), pages 1-18, November.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Evgeny V. Popov & Viktoriya L. Simonova & Vitaly V. Cherepanov, 2022. "The principal–agent problem amid digital transformation," Upravlenets, Ural State University of Economics, vol. 13(3), pages 2-15, July.
    2. Jolanta Tamošaitienė & Vahidreza Yousefi & Hamed Tabasi, 2021. "Project Portfolio Construction Using Extreme Value Theory," Sustainability, MDPI, vol. 13(2), pages 1-13, January.
    3. Gabriel Castelblanco & Jose Guevara & Harrison Mesa & Diego Flores, 2020. "Risk Allocation in Unsolicited and Solicited Road Public-Private Partnerships: Sustainability and Management Implications," Sustainability, MDPI, vol. 12(11), pages 1-28, June.
    4. Christiono Utomo & Sulfiah Dwi Astarini & Dewa Made Satriya Wibawa Mertha & Yani Rahmawati & Aqsha & Cahyono Bintang Nurcahyo & Maulita Nahdiyah, 2022. "Decision Factors of Stakeholder Integration in Connected Construction for Circular Economics," Sustainability, MDPI, vol. 14(23), pages 1-18, December.
    5. Yan Wang & Yujie Wang & Xiuyu Wu & Jiwang Li, 2020. "Exploring the Risk Factors of Infrastructure PPP Projects for Sustainable Delivery: A Social Network Perspective," Sustainability, MDPI, vol. 12(10), pages 1-26, May.
    6. Lima, Sónia & Brochado, Ana & Marques, Rui Cunha, 2021. "Public-private partnerships in the water sector: A review," Utilities Policy, Elsevier, vol. 69(C).
    7. Hongqiang Wang & Qiaoyan Lin & Yingjie Zhang, 2022. "Risk Cost Measurement of Value for Money Evaluation Based on Case-Based Reasoning and Ontology: A Case Study of the Urban Rail Transit Public-Private Partnership Projects in China," Sustainability, MDPI, vol. 14(9), pages 1-22, May.
    8. Jolanta Tamošaitienė & Hadi Sarvari & Daniel W. M. Chan & Matteo Cristofaro, 2020. "Assessing the Barriers and Risks to Private Sector Participation in Infrastructure Construction Projects in Developing Countries of Middle East," Sustainability, MDPI, vol. 13(1), pages 1-20, December.
    9. Jeffrey Kouton & Wilfried Sanogo & Nandi Djomgoue, 2023. "Risk allocation in energy infrastructure PPPs projects in selected African countries: does institutional quality, PPPs experience and income level make a difference?," Economic Change and Restructuring, Springer, vol. 56(1), pages 537-580, February.
    10. Khwaja Mateen Mazher & Albert P. C. Chan & Rafiq M. Choudhry & Hafiz Zahoor & David J. Edwards & Ahmed M. Ghaithan & Awsan Mohammed & Mubashir Aziz, 2022. "Identifying Measures of Effective Risk Management for Public–Private Partnership Infrastructure Projects in Developing Countries," Sustainability, MDPI, vol. 14(21), pages 1-19, October.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:rbs:ijbrss:v:9:y:2020:i:5:p:351-356. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Umit Hacioglu (email available below). General contact details of provider: https://edirc.repec.org/data/ssbffea.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.