Resettlement Caused by Jatigede Dam Project -Consequence of Long Delayed Implementation of a Project

Author

Listed:
  • Opan Suhendi Suwartapradja
  • Ryo Fujikura
  • Sunardi
  • Regina Hoi Yee Fu

Abstract

Jatigede dam was constructed in Sumedang Regency of West Java Province, Indonesia. It was planned as early as the 1960s. The World Bank cancelled its financing for the reason of insufficient resettlement planning in 1986, but land acquisition for the dam continued and cash compensation was provided to affected villagers. In spite of the suspension of land acquisition in 1997, the Chinese Government became the new sponsor and dam construction started in 2005. Inundation began in 2015 and the villagers were resettled mainly to the vicinity of the reservoir. The construction was completed in 2015. Most of the cash compensation was provided during the mid-1980s. As three decades have passed since the provision of the compensation, resettlers who received the money conceived that the dam construction project has been cancelled. They spent the money at their original place and did not invest for the resettlement. Today, most of the resettlers are jobless and poor. Their incomes are below the international poverty line. Aquaculture at the reservoir is one of the possible options to improve local economy, but the local government prohibits it to avoid deterioration of water quality.

Suggested Citation

  • Opan Suhendi Suwartapradja & Ryo Fujikura & Sunardi & Regina Hoi Yee Fu, 2019. "Resettlement Caused by Jatigede Dam Project -Consequence of Long Delayed Implementation of a Project," Journal of Asian Development, Macrothink Institute, vol. 5(1), pages 31-44, February.
  • Handle: RePEc:mth:jad888:v:5:y:2019:i:1:p:31-44
    as

    Download full text from publisher

    File URL: http://www.macrothink.org/journal/index.php/jad/article/view/14422/11390
    Download Restriction: no

    File URL: http://www.macrothink.org/journal/index.php/jad/article/view/14422
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Syafruddin Karimi & Werry Taifur, 2013. "Resettlement and development: a survey of two of Indonesia's Koto Panjang resettlement villages," International Journal of Water Resources Development, Taylor & Francis Journals, vol. 29(1), pages 35-49.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Ryo Fujikura & Mikiyasu Nakayama, 2019. "Overview: Livelihood Re-Establishment After Resettlement due to Dam Construction," Journal of Asian Development, Macrothink Institute, vol. 5(1), pages 1-11, February.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Dengcai Yan & Guoqing Shi & Zijiang Hu & Haibao Wang, 2017. "Resettlement for the Danjiangkou Dam heightening project in China: planning, implementation and effects," International Journal of Water Resources Development, Taylor & Francis Journals, vol. 33(4), pages 609-627, July.
    2. Pham Huu Ty & A. C. M. Van Westen & Annelies Zoomers, 2013. "Compensation and Resettlement Policies after Compulsory Land Acquisition for Hydropower Development in Vietnam: Policy and Practice," Land, MDPI, vol. 2(4), pages 1-27, November.
    3. Zheng, Tengfei & Qiang, Maoshan & Chen, Wenchao & Xia, Bingqing & Wang, Jianing, 2016. "An externality evaluation model for hydropower projects: A case study of the Three Gorges Project," Energy, Elsevier, vol. 108(C), pages 74-85.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:mth:jad888:v:5:y:2019:i:1:p:31-44. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Technical Support Office The email address of this maintainer does not seem to be valid anymore. Please ask Technical Support Office to update the entry or send us the correct address (email available below). General contact details of provider: http://www.macrothink.org/journal/index.php/jad .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.