Causes and Effects of Cost Overrun on Construction Project in Bahrain: Part I (Ranking of Cost Overrun Factors and Risk Mapping)

Author

Listed:
  • Hedaya Abusafiya
  • Saad Suliman

Abstract

Cost performance is one of the basic criteria for measuring construction project success. Despite its proven importance it is not uncommon to see a construction project failing to achieve its objectives within the specified cost. The paper attempts to identify the major causes of cost overrun in Bahrain construction sector, and to assess the effect of these causes on cost overrun. A list of these causes was collected through an extensive literature review, historical construction projects records and expert opinions. In total 45 factors were short-listed to be made part of questionnaire used in a survey conducted with representatives from local contracting, consulting, and client firms. Findings are presented in form of tables that classify cost overrun factors, and their ranking. The overall results showed that frequent design changes, mistakes during construction, and schedule delay were considered as the most important factors of cost overrun causes in Bahrain construction industry.

Suggested Citation

  • Hedaya Abusafiya & Saad Suliman, 2017. "Causes and Effects of Cost Overrun on Construction Project in Bahrain: Part I (Ranking of Cost Overrun Factors and Risk Mapping)," Modern Applied Science, Canadian Center of Science and Education, vol. 11(7), pages 1-20, July.
  • Handle: RePEc:ibn:masjnl:v:11:y:2017:i:7:p:20
    as

    Download full text from publisher

    File URL: https://ccsenet.org/journal/index.php/mas/article/download/65054/37148
    Download Restriction: no

    File URL: https://ccsenet.org/journal/index.php/mas/article/view/65054
    Download Restriction: no
    ---><---

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Francisco Pinheiro Catalão & Carlos Oliveira Cruz & Joaquim Miranda Sarmento, 2023. "The entanglement of time and cost deviations in public projects," Annals of Public and Cooperative Economics, Wiley Blackwell, vol. 94(1), pages 241-272, March.

    More about this item

    JEL classification:

    • R00 - Urban, Rural, Regional, Real Estate, and Transportation Economics - - General - - - General
    • Z0 - Other Special Topics - - General

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:ibn:masjnl:v:11:y:2017:i:7:p:20. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Canadian Center of Science and Education (email available below). General contact details of provider: https://edirc.repec.org/data/cepflch.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.