Estimation of Costs and Durations of Construction of Urban Roads Using ANN and SVM

Author

Listed:
  • Igor Peško
  • Vladimir Mučenski
  • Miloš Šešlija
  • Nebojša Radović
  • Aleksandra Vujkov
  • Dragana Bibić
  • Milena Krklješ

Abstract

Offer preparation has always been a specific part of a building process which has significant impact on company business. Due to the fact that income greatly depends on offer’s precision and the balance between planned costs, both direct and overheads, and wished profit, it is necessary to prepare a precise offer within required time and available resources which are always insufficient. The paper presents a research of precision that can be achieved while using artificial intelligence for estimation of cost and duration in construction projects. Both artificial neural networks (ANNs) and support vector machines (SVM) are analysed and compared. The best SVM has shown higher precision, when estimating costs, with mean absolute percentage error (MAPE) of 7.06% compared to the most precise ANNs which has achieved precision of 25.38%. Estimation of works duration has proved to be more difficult. The best MAPEs were 22.77% and 26.26% for SVM and ANN, respectively.

Suggested Citation

  • Igor Peško & Vladimir Mučenski & Miloš Šešlija & Nebojša Radović & Aleksandra Vujkov & Dragana Bibić & Milena Krklješ, 2017. "Estimation of Costs and Durations of Construction of Urban Roads Using ANN and SVM," Complexity, Hindawi, vol. 2017, pages 1-13, December.
  • Handle: RePEc:hin:complx:2450370
    DOI: 10.1155/2017/2450370
    as

    Download full text from publisher

    File URL: http://downloads.hindawi.com/journals/8503/2017/2450370.pdf
    Download Restriction: no

    File URL: http://downloads.hindawi.com/journals/8503/2017/2450370.xml
    Download Restriction: no

    File URL: https://libkey.io/10.1155/2017/2450370?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Ajibade Ayodeji Aibinu & Thomas Pasco, 2008. "The accuracy of pre-tender building cost estimates in Australia," Construction Management and Economics, Taylor & Francis Journals, vol. 26(12), pages 1257-1269.
    2. Martin Skitmore, 2002. "Raftery curve construction for tender price forecasts," Construction Management and Economics, Taylor & Francis Journals, vol. 20(1), pages 83-89.
    3. Remer, Donald S. & Buchanan, Harry R., 2000. "Estimating the cost for doing a cost estimate," International Journal of Production Economics, Elsevier, vol. 66(2), pages 101-104, June.
    4. John Gunner & Martin Skitmore, 1999. "Comparative analysis of pre-bid forecasting of building prices based on Singapore data," Construction Management and Economics, Taylor & Francis Journals, vol. 17(5), pages 635-646.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Federico Nuñez-Piña & Joselito Medina-Marin & Juan Carlos Seck-Tuoh-Mora & Norberto Hernandez-Romero & Eva Selene Hernandez-Gress, 2018. "Modeling of Throughput in Production Lines Using Response Surface Methodology and Artificial Neural Networks," Complexity, Hindawi, vol. 2018, pages 1-10, January.
    2. Fatemeh Mostofi & Vedat Toğan & Yunus Emre Ayözen & Onur Behzat Tokdemir, 2022. "Predicting the Impact of Construction Rework Cost Using an Ensemble Classifier," Sustainability, MDPI, vol. 14(22), pages 1-19, November.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Stephen Ngai & Derek Drew & H. P. Lo & Martin Skitmore, 2002. "A theoretical framework for determining the minimum number of bidders in construction bidding competitions," Construction Management and Economics, Taylor & Francis Journals, vol. 20(6), pages 473-482.
    2. Miranda Sarmento, J.J. & Renneboog, Luc, 2017. "Cost overruns in public sector investment projects," Other publications TiSEM 51799a3e-4c78-4dbd-b330-b, Tilburg University, School of Economics and Management.
    3. Heinz Herrmann, 2019. "How to Increase Profits Through Predictive Analytics When Only Few Competitors’ Bids Are Known," FIIB Business Review, , vol. 8(1), pages 61-76, March.
    4. Tomáš Bruckner & Filip Vencovský, 2020. "The Process of Unit Price Extraction from Public Sector Contracts," Acta Informatica Pragensia, Prague University of Economics and Business, vol. 2020(2), pages 170-183.
    5. Cezar SIMION-MELINTE, 2016. "Factors Influencing The Choice Of Cost Estimates Types And The Accuracy Of Estimates For Construction Projects," Proceedings of the INTERNATIONAL MANAGEMENT CONFERENCE, Faculty of Management, Academy of Economic Studies, Bucharest, Romania, vol. 10(1), pages 50-56, November.
    6. Daisy Yeung & Martin Skitmore, 2012. "A method for systematically pooling data in very early stage construction price forecasting," Construction Management and Economics, Taylor & Francis Journals, vol. 30(11), pages 929-939, November.
    7. Xiaohong Li & John Ogier & John Cullen, 2006. "An economic modelling approach for public sector construction workload planning," Construction Management and Economics, Taylor & Francis Journals, vol. 24(11), pages 1137-1147.
    8. Miranda Sarmento, J.J., 2014. "Public private partnerships," Other publications TiSEM c7d4c978-234c-4f88-83ed-1, Tilburg University, School of Economics and Management.
    9. Tomáš Bruckner & Filip Vencovský, . "The Process of Unit Price Extraction from Public Sector Contracts," Acta Informatica Pragensia, Prague University of Economics and Business, vol. 0.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:hin:complx:2450370. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Mohamed Abdelhakeem (email available below). General contact details of provider: https://www.hindawi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.