Project scheduling in a lean environment to maximize value and minimize overruns

Author

Listed:
  • Claudio Szwarcfiter

    (Technion—Israel Institute of Technology)

  • Yale T. Herer

    (Technion—Israel Institute of Technology)

  • Avraham Shtub

    (Technion—Israel Institute of Technology)

Abstract

Motivated by the recent trend in delivering projects with value or benefit to stakeholders and seeking to reduce the significant fraction of projects plagued by schedule and budget overruns, researchers are looking at lean project management (LPM) as a possible solution. This paper outlines a new approach to project scheduling in an LPM framework. We develop and solve a math program for balancing project time, cost, value, and risk, seeking to maximize the project value subject to schedule and budget constraints in multimode stochastic projects. Each activity mode contains fixed and resource cost information and duration data, and may be associated with one or more value attributes, thereby integrating project and product scope. By selecting a mode for each activity, the value of the project is determined, and stability is achieved by complying with on-schedule and on-budget probability thresholds. We solve the problem by applying a reinforcement learning-based heuristic, a tool known for obtaining fast solutions in a variety of applications in uncertain environments. We validate the method by comparing the results to two benchmarks—those obtained by solving a mixed-integer program, and the values obtained by adapting a recently published genetic algorithm. Our method generates competitive values faster than the benchmarks, making this approach interesting for the planning stage of a project, when multiple project tradespace alternatives are explored and solved, and runtime is limited. Our approach can be applied by decision-makers to calculate an efficient frontier with the best project plans for given on-schedule and on-budget probabilities.

Suggested Citation

  • Claudio Szwarcfiter & Yale T. Herer & Avraham Shtub, 2022. "Project scheduling in a lean environment to maximize value and minimize overruns," Journal of Scheduling, Springer, vol. 25(2), pages 177-190, April.
  • Handle: RePEc:spr:jsched:v:25:y:2022:i:2:d:10.1007_s10951-022-00727-9
    DOI: 10.1007/s10951-022-00727-9
    as

    Download full text from publisher

    File URL: http://link.springer.com/10.1007/s10951-022-00727-9
    File Function: Abstract
    Download Restriction: Access to the full text of the articles in this series is restricted.

    File URL: https://libkey.io/10.1007/s10951-022-00727-9?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Hongbo Li & Erik Demeulemeester, 2016. "A genetic algorithm for the robust resource leveling problem," Journal of Scheduling, Springer, vol. 19(1), pages 43-60, February.
    2. Izack Cohen & Michal Iluz & Avraham Shtub, 2014. "A Simulation‐Based Approach in Support of Project Management Training for Systems Engineers," Systems Engineering, John Wiley & Sons, vol. 17(1), pages 26-36, March.
    3. Van Peteghem, Vincent & Vanhoucke, Mario, 2014. "An experimental investigation of metaheuristics for the multi-mode resource-constrained project scheduling problem on new dataset instances," European Journal of Operational Research, Elsevier, vol. 235(1), pages 62-72.
    4. Cyril Briand & Sandra Ulrich Ngueveu & Přemysl Šůcha, 2017. "Finding an optimal Nash equilibrium to the multi-agent project scheduling problem," Journal of Scheduling, Springer, vol. 20(5), pages 475-491, October.
    5. Cohen, Izack & Iluz, Michal, 2015. "When cost–effective design strategies are not enough: Evidence from an experimental study on the role of redundant goals," Omega, Elsevier, vol. 56(C), pages 99-111.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Itai Lishner & Avraham Shtub, 2022. "Using an Artificial Neural Network for Improving the Prediction of Project Duration," Mathematics, MDPI, vol. 10(22), pages 1-16, November.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Luis F. Machado-Domínguez & Carlos D. Paternina-Arboleda & Jorge I. Vélez & Agustin Barrios-Sarmiento, 2021. "A memetic algorithm to address the multi-node resource-constrained project scheduling problem," Journal of Scheduling, Springer, vol. 24(4), pages 413-429, August.
    2. Ripon K. Chakrabortty & Ruhul A. Sarker & Daryl L. Essam, 2020. "Single mode resource constrained project scheduling with unreliable resources," Operational Research, Springer, vol. 20(3), pages 1369-1403, September.
    3. Beşikci, Umut & Bilge, Ümit & Ulusoy, Gündüz, 2015. "Multi-mode resource constrained multi-project scheduling and resource portfolio problem," European Journal of Operational Research, Elsevier, vol. 240(1), pages 22-31.
    4. Paraskevopoulos, Dimitris C. & Laporte, Gilbert & Repoussis, Panagiotis P. & Tarantilis, Christos D., 2017. "Resource constrained routing and scheduling: Review and research prospects," European Journal of Operational Research, Elsevier, vol. 263(3), pages 737-754.
    5. Hongbo Li & Linwen Zheng & Hanyu Zhu, 2023. "Resource leveling in projects with flexible structures," Annals of Operations Research, Springer, vol. 321(1), pages 311-342, February.
    6. Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
    7. Šůcha, Přemysl & Agnetis, Alessandro & Šidlovský, Marko & Briand, Cyril, 2021. "Nash equilibrium solutions in multi-agent project scheduling with milestones," European Journal of Operational Research, Elsevier, vol. 294(1), pages 29-41.
    8. Alessandro Agnetis & Cyril Briand & Sandra Ulrich Ngueveu & Přemysl Šůcha, 2020. "Price of anarchy and price of stability in multi-agent project scheduling," Annals of Operations Research, Springer, vol. 285(1), pages 97-119, February.
    9. Behrad Barghi & Shahram Shadrokh Sikari, 2022. "Meta-heuristic Solution with Considering Setup Time for Multi-Skilled Project Scheduling Problem," SN Operations Research Forum, Springer, vol. 3(1), pages 1-23, March.
    10. Alfredo S. Ramos & Pablo A. Miranda-Gonzalez & Samuel Nucamendi-Guillén & Elias Olivares-Benitez, 2023. "A Formulation for the Stochastic Multi-Mode Resource-Constrained Project Scheduling Problem Solved with a Multi-Start Iterated Local Search Metaheuristic," Mathematics, MDPI, vol. 11(2), pages 1-25, January.
    11. Tritschler, Martin & Naber, Anulark & Kolisch, Rainer, 2017. "A hybrid metaheuristic for resource-constrained project scheduling with flexible resource profiles," European Journal of Operational Research, Elsevier, vol. 262(1), pages 262-273.
    12. J. C. Gonçalves-Dosantos & I. García-Jurado & J. Costa, 2020. "Sharing delay costs in stochastic scheduling problems with delays," 4OR, Springer, vol. 18(4), pages 457-476, December.
    13. Vanhoucke, Mario & Coelho, José, 2016. "An approach using SAT solvers for the RCPSP with logical constraints," European Journal of Operational Research, Elsevier, vol. 249(2), pages 577-591.
    14. Zsolt T. Kosztyán & István Szalkai, 2020. "Multimode resource-constrained project scheduling in flexible projects," Journal of Global Optimization, Springer, vol. 76(1), pages 211-241, January.
    15. Geiger, Martin Josef, 2017. "A multi-threaded local search algorithm and computer implementation for the multi-mode, resource-constrained multi-project scheduling problem," European Journal of Operational Research, Elsevier, vol. 256(3), pages 729-741.
    16. Patrick Gerhards, 2020. "The multi-mode resource investment problem: a benchmark library and a computational study of lower and upper bounds," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 42(4), pages 901-933, December.
    17. Ben Issa, Samer & Patterson, Raymond A. & Tu, Yiliu, 2021. "Solving resource-constrained multi-project environment under different activity assumptions," International Journal of Production Economics, Elsevier, vol. 232(C).
    18. Lei Lei & Michael Pinedo & Lian Qi & Shengbin Wang & Jian Yang, 2015. "Personnel scheduling and supplies provisioning in emergency relief operations," Annals of Operations Research, Springer, vol. 235(1), pages 487-515, December.
    19. Yanyan Wang & Baiqing Sun, 2022. "Multiperiod optimal emergency material allocation considering road network damage and risk under uncertain conditions," Operational Research, Springer, vol. 22(3), pages 2173-2208, July.
    20. Hartmann, Sönke & Briskorn, Dirk, 2022. "An updated survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 297(1), pages 1-14.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:spr:jsched:v:25:y:2022:i:2:d:10.1007_s10951-022-00727-9. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Sonal Shukla or Springer Nature Abstracting and Indexing (email available below). General contact details of provider: http://www.springer.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.