A Simulation Model Solved the Problem of Scheduling Drilling Rigs at Clyde Dam

Author

Listed:
  • I. M. Premachandra

    (Commerce Division, University of Otago, PO Box 56, Dunedin, New Zealand)

  • Liliana Gonzalez

    (Commerce Division, University of Otago, PO Box 56, Dunedin, New Zealand)

Abstract

The Clyde Dam in New Zealand is located in an area more unstable than was thought when it was designed. Therefore, Electricorp has taken additional precautions to ensure the stability of the hillsides surrounding it, constructing an underground grout curtain of 1,362 meters along the Clutha River. A grout curtain is constructed by drilling holes in the rock and injecting concrete into them. With a budget of millions of dollars for hiring drilling rigs, the construction company wanted to minimize the idling time of the drilling rigs and finish the project quickly. We developed a simulation model that enabled it to find an efficient drilling schedule, saving about NZ$580,000 on hiring costs for drilling rigs (seven percent of drilling hours hired) and 10 weeks (about 26 percent of project completion time).

Suggested Citation

  • I. M. Premachandra & Liliana Gonzalez, 1996. "A Simulation Model Solved the Problem of Scheduling Drilling Rigs at Clyde Dam," Interfaces, INFORMS, vol. 26(2), pages 80-91, April.
  • Handle: RePEc:inm:orinte:v:26:y:1996:i:2:p:80-91
    DOI: 10.1287/inte.26.2.80
    as

    Download full text from publisher

    File URL: http://dx.doi.org/10.1287/inte.26.2.80
    Download Restriction: no

    File URL: https://libkey.io/10.1287/inte.26.2.80?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Trietsch, Dan & Mazmanyan, Lilit & Gevorgyan, Lilit & Baker, Kenneth R., 2012. "Modeling activity times by the Parkinson distribution with a lognormal core: Theory and validation," European Journal of Operational Research, Elsevier, vol. 216(2), pages 386-396.
    2. Hajdu M. & Isaac S., 2016. "Sixty years of project planning: history and future," Organization, Technology and Management in Construction, Sciendo, vol. 8(1), pages 1499-1510, December.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:inm:orinte:v:26:y:1996:i:2:p:80-91. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Asher (email available below). General contact details of provider: https://edirc.repec.org/data/inforea.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.