IDEAS home Printed from https://ideas.repec.org/a/spr/jsched/v23y2020i3d10.1007_s10951-020-00651-w.html
   My bibliography  Save this article

Resource-constrained multi-project scheduling: benchmark datasets and decoupled scheduling

Author

Listed:
  • Rob Eynde

    (Ghent University)

  • Mario Vanhoucke

    (Ghent University
    Vlerick Business School
    University College London)

Abstract

In this paper, we propose a new dataset for the resource-constrained multi-project scheduling problem and evaluate the performance of multi-project extensions of the single-project schedule generation schemes. This manuscript contributes to the existing research in three ways. First, we provide an overview of existing benchmark datasets and classify the multi-project literature based on the type of datasets that are used in these studies. Furthermore, we evaluate the existing summary measures that are used to classify instances and provide adaptations to the data generation procedure of Browning and Yassine (J Scheduling 13(2):143-161, 2010a). With this adapted generator we propose a new dataset that is complimentary to the existing ones. Second, we propose decoupled versions of the single-project scheduling schemes, building on insights from the existing literature. A computational experiment shows that the decoupled variants outperform the existing priority rule heuristics and that the best priority rules differ for the two objective functions under study. Furthermore, we analyse the effect of the different parameters on the performance of the heuristics. Third, we implement a genetic algorithm that incorporates specific multi-project operators and test it on all datasets. The experiment shows that the new datasets are challenging and provide opportunities for future research.

Suggested Citation

  • Rob Eynde & Mario Vanhoucke, 2020. "Resource-constrained multi-project scheduling: benchmark datasets and decoupled scheduling," Journal of Scheduling, Springer, vol. 23(3), pages 301-325, June.
  • Handle: RePEc:spr:jsched:v:23:y:2020:i:3:d:10.1007_s10951-020-00651-w
    DOI: 10.1007/s10951-020-00651-w
    as

    Download full text from publisher

    File URL: http://link.springer.com/10.1007/s10951-020-00651-w
    File Function: Abstract
    Download Restriction: Access to the full text of the articles in this series is restricted.

    File URL: https://libkey.io/10.1007/s10951-020-00651-w?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Gonçalves, J.F. & Mendes, J.J.M. & Resende, M.G.C., 2008. "A genetic algorithm for the resource constrained multi-project scheduling problem," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1171-1190, September.
    2. Geiger, Martin Josef, 2017. "A multi-threaded local search algorithm and computer implementation for the multi-mode, resource-constrained multi-project scheduling problem," European Journal of Operational Research, Elsevier, vol. 256(3), pages 729-741.
    3. Krüger, Doreen & Scholl, Armin, 2009. "A heuristic solution framework for the resource constrained (multi-)project scheduling problem with sequence-dependent transfer times," European Journal of Operational Research, Elsevier, vol. 197(2), pages 492-508, September.
    4. Antonio Lova & Pilar Tormos, 2001. "Analysis of Scheduling Schemes and Heuristic Rules Performance in Resource-Constrained Multiproject Scheduling," Annals of Operations Research, Springer, vol. 102(1), pages 263-286, February.
    5. Beşikci, Umut & Bilge, Ümit & Ulusoy, Gündüz, 2015. "Multi-mode resource constrained multi-project scheduling and resource portfolio problem," European Journal of Operational Research, Elsevier, vol. 240(1), pages 22-31.
    6. I. Kurtulus & E. W. Davis, 1982. "Multi-Project Scheduling: Categorization of Heuristic Rules Performance," Management Science, INFORMS, vol. 28(2), pages 161-172, February.
    7. Lova, Antonio & Maroto, Concepcion & Tormos, Pilar, 2000. "A multicriteria heuristic method to improve resource allocation in multiproject scheduling," European Journal of Operational Research, Elsevier, vol. 127(2), pages 408-424, December.
    8. Deckro, Richard F. & Winkofsky, E. P. & E. Hebert, John & Gagnon, Roger, 1991. "A decomposition approach to multi-project scheduling," European Journal of Operational Research, Elsevier, vol. 51(1), pages 110-118, March.
    9. John Dumond & Vincent A. Mabert, 1988. "Evaluating Project Scheduling and Due Date Assignment Procedures: An Experimental Analysis," Management Science, INFORMS, vol. 34(1), pages 101-118, January.
    10. Xiaoming Wang & Qingxin Chen & Ning Mao & Xindu Chen & Zhantao Li, 2015. "Proactive approach for stochastic RCMPSP based on multi-priority rule combinations," International Journal of Production Research, Taylor & Francis Journals, vol. 53(4), pages 1098-1110, February.
    11. Browning, Tyson R. & Yassine, Ali A., 2010. "Resource-constrained multi-project scheduling: Priority rule performance revisited," International Journal of Production Economics, Elsevier, vol. 126(2), pages 212-228, August.
    12. Adhau, Sunil & Mittal, M.L. & Mittal, Abhinav, 2013. "A multi-agent system for decentralized multi-project scheduling with resource transfers," International Journal of Production Economics, Elsevier, vol. 146(2), pages 646-661.
    13. Sönke Hartmann, 1998. "A competitive genetic algorithm for resource‐constrained project scheduling," Naval Research Logistics (NRL), John Wiley & Sons, vol. 45(7), pages 733-750, October.
    14. Giuseppe Confessore & Stefano Giordani & Silvia Rismondo, 2007. "A market-based multi-agent system model for decentralized multi-project scheduling," Annals of Operations Research, Springer, vol. 150(1), pages 115-135, March.
    15. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    16. Huan Neng Chiu & Deng Maw Tsai, 2002. "An efficient search procedure for the resource-constrained multi-project scheduling problem with discounted cash flows," Construction Management and Economics, Taylor & Francis Journals, vol. 20(1), pages 55-66.
    17. M.L. Mittal & Arun Kanda, 2009. "Two-phase heuristics for scheduling of multiple projects," International Journal of Operational Research, Inderscience Enterprises Ltd, vol. 4(2), pages 159-177.
    18. Lawrence, Stephen R. & Morton, Thomas E., 1993. "Resource-constrained multi-project scheduling with tardy costs: Comparing myopic, bottleneck, and resource pricing heuristics," European Journal of Operational Research, Elsevier, vol. 64(2), pages 168-187, January.
    19. Vanhoucke, Mario & Coelho, Jose & Debels, Dieter & Maenhout, Broos & Tavares, Luis V., 2008. "An evaluation of the adequacy of project network generators with systematically sampled networks," European Journal of Operational Research, Elsevier, vol. 187(2), pages 511-524, June.
    20. Yang, Kum-Khiong & Sum, Chee-Chuong, 1997. "An evaluation of due date, resource allocation, project release, and activity scheduling rules in a multiproject environment," European Journal of Operational Research, Elsevier, vol. 103(1), pages 139-154, November.
    21. Vercellis, Carlo, 1994. "Constrained multi-project plannings problems: A Lagrangean decomposition approach," European Journal of Operational Research, Elsevier, vol. 78(2), pages 267-275, October.
    22. Kolisch, Rainer & Sprecher, Arno, 1997. "PSPLIB - A project scheduling problem library : OR Software - ORSEP Operations Research Software Exchange Program," European Journal of Operational Research, Elsevier, vol. 96(1), pages 205-216, January.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Van Eynde, Rob & Vanhoucke, Mario, 2022. "New summary measures and datasets for the multi-project scheduling problem," European Journal of Operational Research, Elsevier, vol. 299(3), pages 853-868.
    2. Bredael, Dries & Vanhoucke, Mario, 2023. "Multi-project scheduling: A benchmark analysis of metaheuristic algorithms on various optimisation criteria and due dates," European Journal of Operational Research, Elsevier, vol. 308(1), pages 54-75.
    3. Brachmann, Robert & Kolisch, Rainer, 2021. "The impact of flexibility on engineer-to-order production planning," International Journal of Production Economics, Elsevier, vol. 239(C).
    4. Gómez Sánchez, Mariam & Lalla-Ruiz, Eduardo & Fernández Gil, Alejandro & Castro, Carlos & Voß, Stefan, 2023. "Resource-constrained multi-project scheduling problem: A survey," European Journal of Operational Research, Elsevier, vol. 309(3), pages 958-976.
    5. Wuliang Peng & Jiali lin & Jingwen Zhang & Liangwei Chen, 2022. "A bi-objective hierarchical program scheduling problem and its solution based on NSGA-III," Annals of Operations Research, Springer, vol. 308(1), pages 389-414, January.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Bredael, Dries & Vanhoucke, Mario, 2023. "Multi-project scheduling: A benchmark analysis of metaheuristic algorithms on various optimisation criteria and due dates," European Journal of Operational Research, Elsevier, vol. 308(1), pages 54-75.
    2. Gómez Sánchez, Mariam & Lalla-Ruiz, Eduardo & Fernández Gil, Alejandro & Castro, Carlos & Voß, Stefan, 2023. "Resource-constrained multi-project scheduling problem: A survey," European Journal of Operational Research, Elsevier, vol. 309(3), pages 958-976.
    3. Wuliang Peng & Jiali lin & Jingwen Zhang & Liangwei Chen, 2022. "A bi-objective hierarchical program scheduling problem and its solution based on NSGA-III," Annals of Operations Research, Springer, vol. 308(1), pages 389-414, January.
    4. Ben Issa, Samer & Patterson, Raymond A. & Tu, Yiliu, 2021. "Solving resource-constrained multi-project environment under different activity assumptions," International Journal of Production Economics, Elsevier, vol. 232(C).
    5. Browning, Tyson R. & Yassine, Ali A., 2010. "Resource-constrained multi-project scheduling: Priority rule performance revisited," International Journal of Production Economics, Elsevier, vol. 126(2), pages 212-228, August.
    6. Krüger, Doreen & Scholl, Armin, 2009. "A heuristic solution framework for the resource constrained (multi-)project scheduling problem with sequence-dependent transfer times," European Journal of Operational Research, Elsevier, vol. 197(2), pages 492-508, September.
    7. Hartmann, Sönke & Briskorn, Dirk, 2010. "A survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 207(1), pages 1-14, November.
    8. Anıl Can & Gündüz Ulusoy, 2014. "Multi-project scheduling with two-stage decomposition," Annals of Operations Research, Springer, vol. 217(1), pages 95-116, June.
    9. Hartmann, Sönke & Briskorn, Dirk, 2008. "A survey of variants and extensions of the resource-constrained project scheduling problem," Working Paper Series 02/2008, Hamburg School of Business Administration (HSBA).
    10. He, Yukang & Jia, Tao & Zheng, Weibo, 2023. "Tabu search for dedicated resource-constrained multiproject scheduling to minimise the maximal cash flow gap under uncertainty," European Journal of Operational Research, Elsevier, vol. 310(1), pages 34-52.
    11. Gonçalves, J.F. & Mendes, J.J.M. & Resende, M.G.C., 2008. "A genetic algorithm for the resource constrained multi-project scheduling problem," European Journal of Operational Research, Elsevier, vol. 189(3), pages 1171-1190, September.
    12. Esmaeil MEHDIZADEH & Hamidreza AKBARI, 2017. "A Novel Vibration Damping Optimization Algorithm for Resource Constrained Multi- Project Scheduling Problem," ECONOMIC COMPUTATION AND ECONOMIC CYBERNETICS STUDIES AND RESEARCH, Faculty of Economic Cybernetics, Statistics and Informatics, vol. 51(2), pages 291-309.
    13. He, Naihui & Zhang, David Z. & Yuce, Baris, 2022. "Integrated multi-project planning and scheduling - a multiagent approach," European Journal of Operational Research, Elsevier, vol. 302(2), pages 688-699.
    14. Van Eynde, Rob & Vanhoucke, Mario, 2022. "New summary measures and datasets for the multi-project scheduling problem," European Journal of Operational Research, Elsevier, vol. 299(3), pages 853-868.
    15. M. Suresh & Pankaj Dutta & Karuna Jain, 2015. "Resource Constrained Multi-Project Scheduling Problem with Resource Transfer Times," Asia-Pacific Journal of Operational Research (APJOR), World Scientific Publishing Co. Pte. Ltd., vol. 32(06), pages 1-30, December.
    16. Luise-Sophie Hoffmann & Carolin Kellenbrink & Stefan Helber, 2020. "Simultaneous structuring and scheduling of multiple projects with flexible project structures," Journal of Business Economics, Springer, vol. 90(5), pages 679-711, June.
    17. Hans, E.W. & Herroelen, W. & Leus, R. & Wullink, G., 2007. "A hierarchical approach to multi-project planning under uncertainty," Omega, Elsevier, vol. 35(5), pages 563-577, October.
    18. Mohammad Rostami & Morteza Bagherpour, 2020. "A lagrangian relaxation algorithm for facility location of resource-constrained decentralized multi-project scheduling problems," Operational Research, Springer, vol. 20(2), pages 857-897, June.
    19. Feifei Li & Zhe Xu, 2018. "A multi-agent system for distributed multi-project scheduling with two-stage decomposition," PLOS ONE, Public Library of Science, vol. 13(10), pages 1-24, October.
    20. Hartmann, Sönke & Briskorn, Dirk, 2022. "An updated survey of variants and extensions of the resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 297(1), pages 1-14.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:spr:jsched:v:23:y:2020:i:3:d:10.1007_s10951-020-00651-w. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Sonal Shukla or Springer Nature Abstracting and Indexing (email available below). General contact details of provider: http://www.springer.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.