Single-machine common due date total earliness/tardiness scheduling with machine unavailability

Author

Listed:
  • Kerem Bülbül

    (Sabancı University)

  • Safia Kedad-Sidhoum

    (Sorbonne Universités, Université Pierre et Marie Curie)

  • Halil Şen

    (Inria Bordeaux - Sud-Ouest, Institut de Mathématiques de Bordeaux UMR 5251)

Abstract

Research on non-regular performance measures is at best scarce in the deterministic machine scheduling literature with machine unavailability constraints. Moreover, almost all existing works in this area assume either that processing on jobs interrupted by an interval of machine unavailability may be resumed without any additional setup/processing or that all prior processing is lost. In this work, we intend to partially fill these gaps by studying the problem of scheduling a single machine so as to minimize the total deviation of the job completion times from an unrestrictive common due date when one or several fixed intervals of unavailability are present in the planning horizon. We also put serious effort into investigating models with semi-resumable jobs so that processing on a job interrupted by an interval of machine unavailability may later be resumed at the expense of some extra processing time. The conventional assumptions regarding resumability are also taken into account. Several interesting cases are identified and explored, depending on the resumability scheme and the location of the interval of machine unavailability with respect to the common due date. The focus of analysis is on structural properties and drawing the boundary between polynomially solvable and $$\mathcal {NP}$$ NP -complete cases. Pseudo-polynomial dynamic programming algorithms are devised for $$\mathcal {NP}$$ NP -complete variants in the ordinary sense.

Suggested Citation

  • Kerem Bülbül & Safia Kedad-Sidhoum & Halil Şen, 2019. "Single-machine common due date total earliness/tardiness scheduling with machine unavailability," Journal of Scheduling, Springer, vol. 22(5), pages 543-565, October.
  • Handle: RePEc:spr:jsched:v:22:y:2019:i:5:d:10.1007_s10951-018-0585-x
    DOI: 10.1007/s10951-018-0585-x
    as

    Download full text from publisher

    File URL: http://link.springer.com/10.1007/s10951-018-0585-x
    File Function: Abstract
    Download Restriction: Access to the full text of the articles in this series is restricted.

    File URL: https://libkey.io/10.1007/s10951-018-0585-x?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Ming Liu & Shijin Wang & Chengbin Chu & Feng Chu, 2016. "An improved exact algorithm for single-machine scheduling to minimise the number of tardy jobs with periodic maintenance," International Journal of Production Research, Taylor & Francis Journals, vol. 54(12), pages 3591-3602, June.
    2. Guoqing Wang & Hongyi Sun & Chengbin Chu, 2005. "Preemptive Scheduling with Availability Constraints to Minimize Total Weighted Completion Times," Annals of Operations Research, Springer, vol. 133(1), pages 183-192, January.
    3. Lee, Chung-Yee, 1999. "Two-machine flowshop scheduling with availability constraints," European Journal of Operational Research, Elsevier, vol. 114(2), pages 420-429, April.
    4. Nicholas G. Hall & Wieslaw Kubiak & Suresh P. Sethi, 1991. "Earliness–Tardiness Scheduling Problems, II: Deviation of Completion Times About a Restrictive Common Due Date," Operations Research, INFORMS, vol. 39(5), pages 847-856, October.
    5. Chen, Wen-Jinn, 2009. "Minimizing number of tardy jobs on a single machine subject to periodic maintenance," Omega, Elsevier, vol. 37(3), pages 591-599, June.
    6. Maciej Drozdowski & Florian Jaehn & Radosław Paszkowski, 2017. "Scheduling Position-Dependent Maintenance Operations," Operations Research, INFORMS, vol. 65(6), pages 1657-1677, December.
    7. Schmidt, Gunter, 2000. "Scheduling with limited machine availability," European Journal of Operational Research, Elsevier, vol. 121(1), pages 1-15, February.
    8. Kenneth R. Baker & Gary D. Scudder, 1990. "Sequencing with Earliness and Tardiness Penalties: A Review," Operations Research, INFORMS, vol. 38(1), pages 22-36, February.
    9. Nicholas G. Hall & Marc E. Posner, 1991. "Earliness-Tardiness Scheduling Problems, I: Weighted Deviation of Completion Times About a Common Due Date," Operations Research, INFORMS, vol. 39(5), pages 836-846, October.
    10. Hamilton Emmons, 1987. "Scheduling to a common due date on parallel uniform processors," Naval Research Logistics (NRL), John Wiley & Sons, vol. 34(6), pages 803-810, December.
    11. Detienne, Boris, 2014. "A mixed integer linear programming approach to minimize the number of late jobs with and without machine availability constraints," European Journal of Operational Research, Elsevier, vol. 235(3), pages 540-552.
    12. V. Jorge Leon & S. David Wu, 1992. "On scheduling with ready‐times, due‐dates and vacations," Naval Research Logistics (NRL), John Wiley & Sons, vol. 39(1), pages 53-65, February.
    13. Uttarayan Bagchi & Robert S. Sullivan & Y. L. Chang, 1986. "Minimizing mean absolute deviation of completion times about a common due date," Naval Research Logistics Quarterly, John Wiley & Sons, vol. 33(2), pages 227-240, May.
    14. Hoogeveen, J. A. & van de Velde, S. L., 1991. "Scheduling around a small common due date," European Journal of Operational Research, Elsevier, vol. 55(2), pages 237-242, November.
    15. A. Federgruen & G. Mosheiov, 1997. "Single Machine Scheduling Problems with General Breakdowns, Earliness and Tardiness Costs," Operations Research, INFORMS, vol. 45(1), pages 66-71, February.
    16. John J. Kanet, 1981. "Minimizing the average deviation of job completion times about a common due date," Naval Research Logistics Quarterly, John Wiley & Sons, vol. 28(4), pages 643-651, December.
    17. Kacem, Imed & Chu, Chengbin, 2008. "Efficient branch-and-bound algorithm for minimizing the weighted sum of completion times on a single machine with one availability constraint," International Journal of Production Economics, Elsevier, vol. 112(1), pages 138-150, March.
    18. Michael R. Garey & Robert E. Tarjan & Gordon T. Wilfong, 1988. "One-Processor Scheduling with Symmetric Earliness and Tardiness Penalties," Mathematics of Operations Research, INFORMS, vol. 13(2), pages 330-348, May.
    19. Gregory H. Graves & Chung‐Yee Lee, 1999. "Scheduling maintenance and semiresumable jobs on a single machine," Naval Research Logistics (NRL), John Wiley & Sons, vol. 46(7), pages 845-863, October.
    20. John J. Kanet & V. Sridharan, 2000. "Scheduling with Inserted Idle Time: Problem Taxonomy and Literature Review," Operations Research, INFORMS, vol. 48(1), pages 99-110, February.
    21. Nicholas G. Hall, 1986. "Single‐ and multiple‐processor models for minimizing completion time variance," Naval Research Logistics Quarterly, John Wiley & Sons, vol. 33(1), pages 49-54, February.
    22. Yin, Yunqiang & Wang, Yan & Cheng, T.C.E. & Liu, Wenqi & Li, Jinhai, 2017. "Parallel-machine scheduling of deteriorating jobs with potential machine disruptions," Omega, Elsevier, vol. 69(C), pages 17-28.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Koulamas, Christos & Kyparisis, George J., 2023. "A classification of dynamic programming formulations for offline deterministic single-machine scheduling problems," European Journal of Operational Research, Elsevier, vol. 305(3), pages 999-1017.
    2. Baruch Mor & Gur Mosheiov, 2021. "A note on the single machine CON and CONW problems with lot scheduling," Journal of Combinatorial Optimization, Springer, vol. 42(2), pages 327-338, August.
    3. Shi-Sheng Li & Ren-Xia Chen, 2022. "Minimizing total weighted late work on a single-machine with non-availability intervals," Journal of Combinatorial Optimization, Springer, vol. 44(2), pages 1330-1355, September.
    4. Klaus Heeger & Danny Hermelin & George B. Mertzios & Hendrik Molter & Rolf Niedermeier & Dvir Shabtay, 2023. "Equitable scheduling on a single machine," Journal of Scheduling, Springer, vol. 26(2), pages 209-225, April.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Mosheiov, Gur & Shadmon, Michal, 2001. "Minmax earliness-tardiness costs with unit processing time jobs," European Journal of Operational Research, Elsevier, vol. 130(3), pages 638-652, May.
    2. Gordon, Valery & Proth, Jean-Marie & Chu, Chengbin, 2002. "A survey of the state-of-the-art of common due date assignment and scheduling research," European Journal of Operational Research, Elsevier, vol. 139(1), pages 1-25, May.
    3. Hoogeveen, Han, 2005. "Multicriteria scheduling," European Journal of Operational Research, Elsevier, vol. 167(3), pages 592-623, December.
    4. Enrique Gerstl & Gur Mosheiov, 2014. "Single machine just‐in‐time scheduling problems with two competing agents," Naval Research Logistics (NRL), John Wiley & Sons, vol. 61(1), pages 1-16, February.
    5. Sridharan, V. & Zhou, Z., 1996. "A decision theory based scheduling procedure for single-machine weighted earliness and tardiness problems," European Journal of Operational Research, Elsevier, vol. 94(2), pages 292-301, October.
    6. Michael X. Weng & Jose A. Ventura, 1994. "Scheduling about a large common due date with tolerance to minimize mean absolute deviation of completion times," Naval Research Logistics (NRL), John Wiley & Sons, vol. 41(6), pages 843-851, October.
    7. Koulamas, Christos & Kyparisis, George J., 2023. "A classification of dynamic programming formulations for offline deterministic single-machine scheduling problems," European Journal of Operational Research, Elsevier, vol. 305(3), pages 999-1017.
    8. Baker, Kenneth R., 2014. "Minimizing earliness and tardiness costs in stochastic scheduling," European Journal of Operational Research, Elsevier, vol. 236(2), pages 445-452.
    9. C N Potts & V A Strusevich, 2009. "Fifty years of scheduling: a survey of milestones," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 60(1), pages 41-68, May.
    10. Weng, Michael X. & Ventura, Jose A., 1996. "Single-machine earliness-tardiness scheduling about a common due date with tolerances," International Journal of Production Economics, Elsevier, vol. 42(3), pages 217-227, April.
    11. Seyed Habib A. Rahmati & Abbas Ahmadi & Kannan Govindan, 2018. "A novel integrated condition-based maintenance and stochastic flexible job shop scheduling problem: simulation-based optimization approach," Annals of Operations Research, Springer, vol. 269(1), pages 583-621, October.
    12. Zhi-Long Chen, 1997. "Scheduling with batch setup times and earliness-tardiness penalties," European Journal of Operational Research, Elsevier, vol. 96(3), pages 518-537, February.
    13. Lin, Shih-Wei & Chou, Shuo-Yan & Ying, Kuo-Ching, 2007. "A sequential exchange approach for minimizing earliness-tardiness penalties of single-machine scheduling with a common due date," European Journal of Operational Research, Elsevier, vol. 177(2), pages 1294-1301, March.
    14. Ventura, Jose A. & Kim, Daecheol & Garriga, Frederic, 2002. "Single machine earliness-tardiness scheduling with resource-dependent release dates," European Journal of Operational Research, Elsevier, vol. 142(1), pages 52-69, October.
    15. Hans Kellerer & Vitaly A. Strusevich, 2016. "Optimizing the half-product and related quadratic Boolean functions: approximation and scheduling applications," Annals of Operations Research, Springer, vol. 240(1), pages 39-94, May.
    16. Helmut A. Sedding, 2020. "Scheduling jobs with a V-shaped time-dependent processing time," Journal of Scheduling, Springer, vol. 23(6), pages 751-768, December.
    17. Wlodzimierz Szwarc, 1989. "Single‐machine scheduling to minimize absolute deviation of completion times from a common due date," Naval Research Logistics (NRL), John Wiley & Sons, vol. 36(5), pages 663-673, October.
    18. Biskup, Dirk & Feldmann, Martin, 2005. "On scheduling around large restrictive common due windows," European Journal of Operational Research, Elsevier, vol. 162(3), pages 740-761, May.
    19. Alidaee, Bahram & Dragan, Irinel, 1997. "A note on minimizing the weighted sum of tardy and early completion penalties in a single machine: A case of small common due date," European Journal of Operational Research, Elsevier, vol. 96(3), pages 559-563, February.
    20. Yeong‐Dae Kim & Candace Arai Yano, 1994. "Minimizing mean tardiness and earliness in single‐machine scheduling problems with unequal due dates," Naval Research Logistics (NRL), John Wiley & Sons, vol. 41(7), pages 913-933, December.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:spr:jsched:v:22:y:2019:i:5:d:10.1007_s10951-018-0585-x. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Sonal Shukla or Springer Nature Abstracting and Indexing (email available below). General contact details of provider: http://www.springer.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.