Efficient sensitivity analysis of PERT network performance measures to significant changes in activity time parameters

Author

Listed:
  • R A Bowman

    (Graduate College of Union University)

Abstract

Using a Program Evaluation and Review Technique network model of a project schedule, a method is presented to estimate the effects of changes to the probability distribution for any activity time on several project schedule measures. Computational results show this method to be significantly faster and more accurate than a previously published approach, which estimated the effects of changes to the means of normally distributed activity times on expected project completion time and activity criticality. In addition, the new method allows more flexibility to model changes to activity times, including independent changes to parameters and even changes in the distributional form. Finally, the new method estimates the effects of these changes on several additional performance measures, including the probability of meeting a specified due date and a project (penalty) cost function. All desired estimates are obtained from a single set of simulation runs.

Suggested Citation

  • R A Bowman, 2007. "Efficient sensitivity analysis of PERT network performance measures to significant changes in activity time parameters," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 58(10), pages 1354-1360, October.
  • Handle: RePEc:pal:jorsoc:v:58:y:2007:i:10:d:10.1057_palgrave.jors.2602297
    DOI: 10.1057/palgrave.jors.2602297
    as

    Download full text from publisher

    File URL: http://link.springer.com/10.1057/palgrave.jors.2602297
    File Function: Abstract
    Download Restriction: Access to full text is restricted to subscribers.

    File URL: https://libkey.io/10.1057/palgrave.jors.2602297?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. R.A. Bowman, 2001. "Due Date-Based Metrics for Activity Importance in Stochastic Activity Networks," Annals of Operations Research, Springer, vol. 102(1), pages 39-48, February.
    2. Richard M. Van Slyke, 1963. "Letter to the Editor---Monte Carlo Methods and the PERT Problem," Operations Research, INFORMS, vol. 11(5), pages 839-860, October.
    3. Elmaghraby, Salah E., 2000. "On criticality and sensitivity in activity networks," European Journal of Operational Research, Elsevier, vol. 127(2), pages 220-238, December.
    4. J-G Cho & B-J Yum, 2004. "Functional estimation of activity criticality indices and sensitivity analysis of expected project completion time," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 55(8), pages 850-859, August.
    5. Elmaghraby, S. E. & Fathi, Y. & Taner, M. R., 1999. "On the sensitivity of project variability to activity mean duration," International Journal of Production Economics, Elsevier, vol. 62(3), pages 219-232, September.
    6. D. G. Malcolm & J. H. Roseboom & C. E. Clark & W. Fazar, 1959. "Application of a Technique for Research and Development Program Evaluation," Operations Research, INFORMS, vol. 7(5), pages 646-669, October.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Cui, Nanfang & Demeulemeester, Erik & Bie, Li, 2016. "Incorporation of activity sensitivity measures into buffer management to manage project schedule riskAuthor-Name: Hu, Xuejun," European Journal of Operational Research, Elsevier, vol. 249(2), pages 717-727.
    2. Catalina García & José Pérez & Salvador Rambaud, 2010. "Proposal of a new distribution in PERT methodology," Annals of Operations Research, Springer, vol. 181(1), pages 515-538, December.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Bowman, R. Alan, 2006. "Developing activity duration specification limits for effective project control," European Journal of Operational Research, Elsevier, vol. 174(2), pages 1191-1204, October.
    2. Fernando Acebes & Javier Pajares & José M. González-Varona & Adolfo López-Paredes, 2021. "Project risk management from the bottom-up: Activity Risk Index," Central European Journal of Operations Research, Springer;Slovak Society for Operations Research;Hungarian Operational Research Society;Czech Society for Operations Research;Österr. Gesellschaft für Operations Research (ÖGOR);Slovenian Society Informatika - Section for Operational Research;Croatian Operational Research Society, vol. 29(4), pages 1375-1396, December.
    3. Xiong, Jian & Leus, Roel & Yang, Zhenyu & Abbass, Hussein A., 2016. "Evolutionary multi-objective resource allocation and scheduling in the Chinese navigation satellite system project," European Journal of Operational Research, Elsevier, vol. 251(2), pages 662-675.
    4. Azaron, Amir & Fatemi Ghomi, S.M.T., 2008. "Lower bound for the mean project completion time in dynamic PERT networks," European Journal of Operational Research, Elsevier, vol. 186(1), pages 120-127, April.
    5. Elise D. Miller-Hooks & Hani S. Mahmassani, 2000. "Least Expected Time Paths in Stochastic, Time-Varying Transportation Networks," Transportation Science, INFORMS, vol. 34(2), pages 198-215, May.
    6. R. Alan Bowman, 2003. "Sensitivity curves for effective project management," Naval Research Logistics (NRL), John Wiley & Sons, vol. 50(5), pages 481-497, August.
    7. Serpell Alfredo Federico & Ferrada Ximena & Rubio Larissa, 2019. "Measuring the performance of project risk management: a preliminary model," Organization, Technology and Management in Construction, Sciendo, vol. 11(1), pages 1984-1991, January.
    8. Stefan Creemers & Erik Demeulemeester & Stijn Vonder, 2014. "A new approach for quantitative risk analysis," Annals of Operations Research, Springer, vol. 213(1), pages 27-65, February.
    9. Vanhoucke, Mario, 2010. "Using activity sensitivity and network topology information to monitor project time performance," Omega, Elsevier, vol. 38(5), pages 359-370, October.
    10. Song, Jie & Martens, Annelies & Vanhoucke, Mario, 2021. "Using Schedule Risk Analysis with resource constraints for project control," European Journal of Operational Research, Elsevier, vol. 288(3), pages 736-752.
    11. Colin, Jeroen & Vanhoucke, Mario, 2014. "Setting tolerance limits for statistical project control using earned value management," Omega, Elsevier, vol. 49(C), pages 107-122.
    12. Creemers, Stefan, 2018. "Moments and distribution of the net present value of a serial project," European Journal of Operational Research, Elsevier, vol. 267(3), pages 835-848.
    13. J-G Cho & B-J Yum, 2004. "Functional estimation of activity criticality indices and sensitivity analysis of expected project completion time," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 55(8), pages 850-859, August.
    14. Martens, Annelies & Vanhoucke, Mario, 2019. "The impact of applying effort to reduce activity variability on the project time and cost performance," European Journal of Operational Research, Elsevier, vol. 277(2), pages 442-453.
    15. Hajdu M. & Isaac S., 2016. "Sixty years of project planning: history and future," Organization, Technology and Management in Construction, Sciendo, vol. 8(1), pages 1499-1510, December.
    16. Vanhoucke, Mario, 2011. "On the dynamic use of project performance and schedule risk information during projecttracking," Omega, Elsevier, vol. 39(4), pages 416-426, August.
    17. Kim, Byung-Cheol, 2022. "Multi-factor dependence modelling with specified marginals and structured association in large-scale project risk assessment," European Journal of Operational Research, Elsevier, vol. 296(2), pages 679-695.
    18. Madadi, M. & Iranmanesh, H., 2012. "A management oriented approach to reduce a project duration and its risk (variability)," European Journal of Operational Research, Elsevier, vol. 219(3), pages 751-761.
    19. Xing Pan & Lunhu Hu & Ziling Xin & Shenghan Zhou & Yanmei Lin & Yong Wu, 2018. "Risk Scenario Generation Based on Importance Measure Analysis," Sustainability, MDPI, vol. 10(9), pages 1-18, September.
    20. Kamburowski, J., 1997. "New validations of PERT times," Omega, Elsevier, vol. 25(3), pages 323-328, June.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:pal:jorsoc:v:58:y:2007:i:10:d:10.1057_palgrave.jors.2602297. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Sonal Shukla or Springer Nature Abstracting and Indexing (email available below). General contact details of provider: http://www.palgrave-journals.com/ .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.